BELL FM 1123 (1308-01-024)

Items: 82

County: BELL
Length: N/A
Highway: FM 1123
District: WACO
Control Number: 1308-01-024
DBE Goal: N/A
Project: BR 1602(576)
Guaranty: N/A
Time: 298 WORKING DAYS
Engineer's Estimate: $3,317,843.75
Date: 04/05/2017 (9 years ago)
Contract Number: N/A
Type: REPLACE BRIDGE & APPROACHES
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (10)
E
Engineer's Estimate
$3,317,843.75
$2,950,399.18
Over/Under Est: -11.07% -$367,444.57
Over/Under Est: -10.95% -$363,322.85
Amt Left: 0.14% $4,121.72
Over/Under Est: -6.7% -$222,211.64
Amt Left: 4.92% $145,232.93
Delta: -4.78% -$141,111.21
Over/Under Est: -6.61% -$219,172.32
Amt Left: 5.03% $148,272.25
Delta: -0.10% -$3,039.32
$3,129,646.55
Over/Under Est: -5.67% -$188,197.20
Amt Left: 6.08% $179,247.37
Delta: -1.00% -$30,975.12
Over/Under Est: -1.07% -$35,348.28
Amt Left: 11.26% $332,096.29
Delta: -4.88% -$152,848.92
$3,328,626.85
Over/Under Est: 0.33% $10,783.10
Amt Left: 12.82% $378,227.67
Delta: -1.41% -$46,131.38
Over/Under Est: 6.06% $201,137.35
Amt Left: 19.27% $568,581.92
Delta: -5.72% -$190,354.25
Over/Under Est: 6.6% $219,122.35
Amt Left: 19.88% $586,566.92
Delta: -0.51% -$17,985.00
Over/Under Est: 8.29% $274,912.30
Amt Left: 21.77% $642,356.87
Delta: -1.58% -$55,789.95

Bid Items & Bid Tabulations

82 Total 0 of 82
BELL  |  FM 1123  |  WACO  |  1308-01-024  |  04/05/2017  |  $3,317,843.75  |  BR 1602(576)  |  REPLACE BRIDGE & APPROACHES  |  298 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
J.D. ABRAMS, L.P.
JAMES CONSTRUCTION GROUP, L.L.C.
ANGEL BROTHERS HOLDINGS CORP.
AUSTIN BRIDGE & ROAD SERVICES, LP
CHASCO CONSTRUCTORS
KNIFE RIVER CORPORATION - SOUTH
PIERCE R & B LLC
HODGES AND SON CONSTRUCTION COMPANY, INC.
ELLIS-MCGINNIS CONSTRUCTION CO.
RAGLE CONSTRUCTION, INC.
PREPARING ROW
STA 18.960 $1,800.000 $15,000.000 $7,500.000 $6,200.000 $7,500.000 $6,350.000 $3,000.000 $2,500.000 $4,000.000 $10,800.000 $18,750.000
PREPARING ROW (TREE) (36" TO 48" DIA)
EA 4.000 $2,000.000 $2,500.000 $1,500.000 $2,000.000 $7,500.000 $2,100.000 $1,000.000 $2,000.000 $2,000.000 $2,800.000 $2,500.000
REMOVING STAB BASE & ASPH PAV (0-6")
SY 214.000 $5.000 $7.000 $6.000 $7.000 $15.000 $4.600 $12.680 $25.000 $20.000 $12.000 $8.000
REMOVING STAB BASE & ASPH PAV (12.5")
SY 3,842.000 $7.000 $6.000 $10.000 $7.000 $15.000 $5.000 $6.860 $10.000 $8.000 $6.000 $8.000
REMOVE STAB BS & ASPH PAV (7.5"-15.5")
SY 837.000 $8.000 $6.000 $10.000 $7.000 $15.000 $5.000 $10.380 $9.000 $10.000 $8.000 $10.000
EXCAVATION (ROADWAY)
CY 9,915.000 $10.000 $10.000 $15.000 $17.000 $13.000 $15.000 $10.370 $12.000 $15.000 $16.000 $9.500
EMBANKMENT (FINAL)(DENS CONT)(TY B)
CY 4,743.000 $10.000 $11.000 $10.000 $17.000 $14.000 $8.000 $12.580 $17.500 $20.000 $13.000 $14.000
FURNISHING AND PLACING TOPSOIL (4")
SY 11,377.000 $1.500 $1.300 $3.000 $1.000 $2.250 $2.500 $1.750 $4.500 $4.000 $4.000 $1.500
BLOCK SODDING
SY 1,000.000 $3.000 $4.800 $4.670 $4.600 $4.550 $4.750 $5.000 $5.600 $4.000 $4.600 $6.000
DRILL SEEDING (PERM) (RURAL) (CLAY)
SY 11,377.000 $0.750 $0.170 $0.160 $0.160 $0.160 $0.170 $0.170 $0.270 $1.000 $0.200 $0.160
DRILL SEEDING (TEMP) (WARM)
SY 7,259.000 $0.750 $0.130 $0.120 $0.120 $0.120 $0.140 $0.120 $0.250 $0.400 $0.500 $0.120
DRILL SEEDING (TEMP) (COOL)
SY 7,259.000 $0.750 $0.130 $0.120 $0.120 $0.120 $0.140 $0.120 $0.250 $0.400 $0.500 $0.120
VEGETATIVE WATERING
MG 209.900 $40.000 $19.000 $14.000 $24.000 $25.000 $25.000 $25.000 $70.000 $1.000 $38.000 $20.000
SOIL RETENTION BLANKETS (CL 2) (TY F)
SY 6,129.000 $2.000 $2.300 $1.870 $1.000 $1.820 $1.900 $2.000 $1.480 $4.000 $1.900 $1.820
FL BS (CMP IN PLC)(TY D GR 4)(FNAL POS)
CY 1,276.000 $40.000 $60.000 $42.000 $48.000 $55.000 $62.000 $55.000 $39.000 $50.000 $58.000 $45.000
PRIME COAT(MC-30 OR AE-P)
GAL 730.000 $7.000 $4.500 $4.200 $8.500 $4.000 $5.750 $10.000 $5.860 $6.000 $4.000 $5.500
ASPH (CRS-2)
GAL 2,571.000 $7.500 $3.500 $3.500 $4.500 $3.150 $3.700 $3.500 $12.950 $6.000 $3.200 $5.500
AGGR(TY-D GR-4 OR TY-L GR-4)
CY 46.000 $250.000 $400.000 $400.000 $360.000 $390.000 $685.000 $250.000 $763.000 $800.000 $390.000 $725.000
D-GR HMA TY-D SAC-B PG64-22
TON 334.000 $100.000 $119.000 $115.000 $115.000 $125.000 $116.000 $125.000 $115.000 $120.000 $103.000 $110.000
D-GR HMA TY B SAC-B PG (64-22)
TON 92.000 $90.000 $153.000 $150.000 $105.000 $175.000 $162.000 $165.000 $163.000 $160.000 $133.000 $155.000
CEM STABIL BKFL
CY 281.000 $160.000 $100.000 $120.000 $130.000 $125.000 $120.000 $175.000 $190.000 $250.000 $200.000 $105.000
TEMPORARY SPL SHORING
SF 2,471.000 $25.000 $12.000 $15.000 $23.000 $30.000 $30.000 $45.000 $35.000 $20.000 $25.000 $20.000
DRILL SHAFT (18 IN)
LF 84.000 $100.000 $115.000 $180.000 $110.000 $100.000 $104.000 $130.000 $175.000 $80.000 $140.000 $105.000
DRILL SHAFT (36 IN)
LF 697.000 $205.000 $215.000 $250.000 $205.000 $175.000 $213.000 $210.000 $195.000 $180.000 $293.000 $215.000
CL C CONC (ABUT)
CY 68.900 $1,000.000 $1,100.000 $800.000 $850.000 $900.000 $580.000 $700.000 $900.000 $900.000 $950.000 $850.000
CL C CONC (BENT)
CY 153.200 $1,200.000 $1,100.000 $900.000 $850.000 $1,000.000 $880.000 $1,100.000 $950.000 $900.000 $920.000 $1,200.000
REINF CONC SLAB
SF 30,960.000 $18.000 $15.000 $13.000 $16.000 $14.000 $13.500 $17.000 $15.750 $18.000 $18.300 $16.450
APPROACH SLAB
CY 93.500 $450.000 $350.000 $400.000 $480.000 $525.000 $390.000 $475.000 $395.000 $600.000 $480.000 $375.000
PRESTR CONC GIRDER (TX54)
LF 3,582.900 $160.000 $136.000 $155.000 $138.000 $125.000 $143.000 $162.000 $147.000 $170.000 $148.000 $150.000
RIPRAP (STONE PROTECTION)(18 IN)
CY 1,312.000 $115.000 $95.000 $70.000 $90.000 $125.000 $93.500 $92.000 $121.000 $110.000 $85.000 $100.000
RIPRAP (MOW STRIP)(4 IN)
CY 30.000 $460.000 $650.000 $500.000 $440.000 $575.000 $555.000 $575.000 $550.000 $500.000 $620.000 $465.000
RAIL (TY T66)
LF 1,496.100 $215.000 $110.000 $115.000 $100.000 $110.000 $182.000 $110.000 $138.000 $100.000 $150.000 $72.000
SEALED EXPANSION JOINT (4 IN) (SEJ - A)
LF 131.000 $100.000 $105.000 $90.000 $90.000 $95.000 $83.000 $87.000 $85.000 $80.000 $95.000 $85.000
CONC BOX CULV (5 FT X 3 FT)
LF 81.000 $275.000 $250.000 $200.000 $270.000 $300.000 $302.000 $280.000 $283.000 $400.000 $420.000 $370.000
RC PIPE (CL III)(18 IN)
LF 60.000 $60.000 $80.000 $70.000 $90.000 $85.000 $70.000 $66.000 $58.000 $60.000 $85.000 $72.000
RC PIPE (CL III)(24 IN)
LF 60.000 $75.000 $95.000 $80.000 $100.000 $95.000 $85.000 $77.000 $66.000 $100.000 $100.000 $87.000
WINGWALL (PW - 1) (HW=4 FT)
EA 1.000 $8,000.000 $5,250.000 $6,500.000 $5,000.000 $7,500.000 $5,200.000 $8,200.000 $6,200.000 $6,000.000 $9,300.000 $6,700.000
SET (TY I)(S= 5 FT)(HW= 4 FT)(6:1) (P)
EA 1.000 $7,000.000 $5,100.000 $10,000.000 $8,500.000 $6,500.000 $8,500.000 $9,900.000 $8,000.000 $6,000.000 $8,500.000 $3,850.000
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 4.000 $800.000 $1,100.000 $700.000 $1,500.000 $1,200.000 $1,260.000 $1,000.000 $955.000 $2,000.000 $1,150.000 $1,400.000
SET (TY II) (24 IN) (RCP) (6: 1) (P)
EA 4.000 $1,100.000 $1,250.000 $800.000 $1,800.000 $1,500.000 $1,750.000 $1,150.000 $1,100.000 $2,500.000 $1,450.000 $2,500.000
REMOV STR (PIPE)
LF 177.000 $15.000 $15.000 $14.000 $14.000 $25.000 $20.000 $18.000 $15.000 $5.000 $40.000 $17.000
REMOV STR (BRIDGE 100 - 499 FT LENGTH)
EA 1.000 $75,000.000 $20,000.000 $50,000.000 $50,000.000 $40,000.000 $50,000.000 $55,000.000 $50,000.000 $60,000.000 $24,800.000 $32,000.000
MOBILIZATION
LS 1.000 $260,000.000 $100,000.000 $267,000.000 $310,000.000 $300,000.000 $285,000.000 $320,000.000 $328,000.000 $310,000.000 $300,000.000 $355,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 14.000 $3,000.000 $1,700.000 $2,000.000 $2,000.000 $4,200.000 $2,000.000 $2,000.000 $3,500.000 $6,000.000 $895.000 $20,000.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 138.000 $40.000 $33.000 $30.000 $27.000 $26.200 $27.000 $30.000 $27.750 $40.000 $42.000 $26.200
ROCK FILTER DAMS (INSTALL) (TY 3)
LF 224.000 $50.000 $44.000 $40.000 $35.000 $35.100 $36.000 $40.000 $51.500 $40.000 $72.000 $35.100
ROCK FILTER DAMS (REMOVE)
LF 362.000 $10.000 $9.000 $8.000 $7.000 $7.000 $7.000 $7.000 $11.700 $20.000 $10.000 $7.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 546.000 $15.000 $15.000 $14.000 $10.000 $13.500 $15.000 $15.000 $24.350 $5.000 $16.000 $13.500
CONSTRUCTION EXITS (REMOVE)
SY 546.000 $8.000 $8.000 $6.000 $4.000 $6.000 $6.000 $6.000 $8.300 $1.000 $5.000 $6.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 2,777.000 $3.000 $4.000 $2.500 $2.400 $2.250 $3.000 $4.500 $3.000 $3.000 $3.800 $2.250
TEMP SEDMT CONT FENCE (REMOVE)
LF 2,777.000 $1.000 $0.500 $0.300 $0.250 $0.250 $0.250 $0.250 $0.760 $1.000 $1.600 $0.250
CONSTRUCTING DETOURS
SY 912.000 $50.000 $80.000 $70.000 $110.000 $90.000 $88.000 $95.000 $90.000 $124.000 $145.000 $70.000
ONE-WAY TRAF CONT (PORT TRAF SIG)
MO 8.000 $6,000.000 $4,000.000 $1,550.000 $3,600.000 $0.010 $5,000.000 $5,900.000 $6,500.000 $5,000.000 $3,000.000 $2,500.000
PORT CTB (DES SOURCE)(SGL SLP)(TY 1)
LF 240.000 $10.000 $25.000 $15.000 $33.000 $25.000 $40.000 $30.000 $20.000 $40.000 $12.000 $12.000
PORT CTB (STKPL)(SGL SLP)(TY 1)
LF 240.000 $7.000 $23.000 $10.000 $33.000 $25.000 $40.000 $30.000 $20.000 $40.000 $11.000 $12.000
DRIVEWAYS (ACP)
SY 496.000 $40.000 $49.000 $40.000 $47.000 $40.000 $40.000 $60.000 $50.000 $40.000 $41.000 $37.000
MTL W-BEAM GD FEN (STEEL POST)
LF 375.000 $22.000 $20.000 $19.360 $19.000 $20.000 $20.000 $21.000 $21.380 $24.000 $20.000 $20.210
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 4.000 $1,650.000 $1,500.000 $1,464.620 $1,800.000 $1,428.000 $1,500.000 $2,200.000 $1,485.000 $1,800.000 $1,430.000 $1,400.000
GUARDRAIL END TREATMENT (INSTALL)
EA 4.000 $2,150.000 $2,500.000 $2,415.390 $2,500.000 $2,355.000 $2,500.000 $2,600.000 $2,410.000 $2,400.000 $2,355.000 $2,280.000
CRASH CUSH ATTEN (STKPL)
EA 2.000 $2,000.000 $750.000 $512.820 $520.000 $500.000 $550.000 $750.000 $975.000 $2,000.000 $630.000 $900.000
CRASH CUSH ATTEN (INSTL)(S)(N)(TL2)
EA 2.000 $5,000.000 $12,000.000 $9,128.210 $9,200.000 $6,000.000 $9,250.000 $8,500.000 $7,380.000 $10,000.000 $11,000.000 $7,000.000
WIRE FENCE (TY C)
LF 2,058.000 $12.000 $11.000 $4.000 $5.000 $10.000 $7.000 $12.000 $12.000 $10.000 $12.000 $12.000
GATE (TY 1)
EA 3.000 $1,000.000 $650.000 $850.000 $500.000 $550.000 $950.000 $560.000 $750.000 $1,000.000 $480.000 $800.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 2.000 $470.000 $600.000 $475.600 $430.000 $463.710 $475.000 $519.000 $477.000 $500.000 $425.000 $463.710
IN SM RD SN SUP&AM TYTWT(1)WS(P)
EA 10.000 $350.000 $370.000 $343.590 $350.000 $335.000 $350.000 $375.000 $374.000 $500.000 $350.000 $335.000
IN SM RD SN SUP&AM (RAIL MOUNT)
EA 5.000 $2,600.000 $2,700.000 $2,438.670 $1,800.000 $2,377.000 $2,450.000 $2,665.000 $1,775.000 $500.000 $1,780.000 $2,377.000
RELOCATE SM RD SN SUP&AM TY 10BWG
EA 1.000 $430.000 $400.000 $278.580 $320.000 $271.670 $290.000 $300.000 $376.000 $400.000 $300.000 $271.670
REMOVE SM RD SN SUP&AM
EA 25.000 $100.000 $85.000 $76.920 $100.000 $75.000 $80.000 $80.000 $100.000 $100.000 $40.000 $75.000
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
EA 16.000 $23.000 $15.000 $10.260 $20.000 $10.000 $11.000 $11.000 $28.000 $40.000 $10.000 $23.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 6.000 $35.000 $20.000 $14.100 $25.000 $13.750 $14.000 $15.000 $44.000 $40.000 $14.000 $33.000
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
LF 2,712.000 $0.300 $0.700 $0.550 $0.580 $0.550 $0.600 $0.620 $0.600 $0.600 $0.800 $0.750
WK ZN PAV MRK REMOV (REFL) TY II-A-A
EA 48.000 $4.250 $15.000 $10.000 $10.000 $10.000 $10.500 $11.200 $11.780 $10.000 $9.500 $9.450
WK ZN PAV MRK REMOV (W)4"(SLD)
LF 4,671.000 $0.500 $0.900 $0.670 $0.700 $0.670 $0.700 $0.750 $0.720 $0.800 $0.900 $0.850
WK ZN PAV MRK REMOV (W)24"(SLD)
LF 22.000 $6.000 $10.000 $6.000 $6.200 $6.000 $6.500 $6.720 $9.000 $10.000 $15.000 $14.950
WK ZN PAV MRK REMOV (Y)4"(SLD)
LF 1,920.000 $0.500 $0.900 $0.670 $0.700 $0.670 $0.700 $0.750 $0.740 $0.800 $0.900 $0.850
PAVEMENT SEALER 4"
LF 3,108.000 $0.300 $0.200 $0.150 $0.150 $0.150 $0.160 $0.170 $0.180 $0.200 $0.300 $0.250
RE PM W/RET REQ TY I (W)4"(SLD)(090MIL)
LF 4,393.000 $1.000 $0.450 $0.440 $0.450 $0.440 $0.460 $0.490 $0.480 $0.600 $0.600 $0.600
RE PM W/RET REQ TY I (Y)4"(BRK)(090MIL)
LF 381.000 $1.000 $0.550 $0.500 $0.520 $0.500 $0.650 $0.560 $0.690 $0.600 $0.600 $0.600
RE PM W/RET REQ TY I (Y)4"(SLD)(090MIL)
LF 4,793.000 $1.000 $0.450 $0.440 $0.450 $0.440 $0.460 $0.490 $0.470 $0.600 $0.600 $0.600
REFL PAV MRKR TY II-A-A
EA 81.000 $9.000 $8.100 $8.000 $8.000 $8.000 $8.500 $8.960 $9.160 $10.000 $6.800 $6.750
ELIM EXT PAV MRK & MRKS (4")
LF 3,957.000 $0.500 $0.600 $0.570 $0.600 $0.570 $0.600 $0.640 $0.610 $0.600 $0.900 $0.850
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $12,500.000 $6,000.000 $6,025.000 $8,000.000 $4,000.000 $7,000.000 $15,000.000 $8,000.000 $15,000.000 $16,000.000 $10,000.000
Totals: $3,317,843.750 $2,950,399.180 $2,954,520.900 $3,095,632.110 $3,098,671.430 $3,129,646.550 $3,282,495.470 $3,328,626.850 $3,518,981.100 $3,536,966.100 $3,592,756.050