BEE FM 796 (1118-01-019)

Items: 43

County: BEE
Length: N/A
Highway: FM 796
District: CORPUS CHRISTI
Control Number: 1118-01-019
DBE Goal: N/A
Project: BR 1702(491)
Guaranty: N/A
Time: 68 WORKING DAYS
Engineer's Estimate: $442,154.00
Date: 07/11/2017 (8 years ago)
Contract Number: N/A
Type: REPLACE BRIDGE AND APPROACHES
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (9)
E
Engineer's Estimate
$442,154.00
1
$444,575.50
Over/Under Est: 0.55% $2,421.50
Over/Under Est: 10.41% $46,030.00
Amt Left: 9.81% $43,608.50
Over/Under Est: 29.74% $131,502.60
Amt Left: 29.03% $129,081.10
Delta: -17.51% -$85,472.60
$589,549.00
Over/Under Est: 33.34% $147,395.00
Amt Left: 32.61% $144,973.50
Delta: -2.77% -$15,892.40
Over/Under Est: 37.83% $167,246.00
Amt Left: 37.07% $164,824.50
Delta: -3.37% -$19,851.00
Over/Under Est: 47.07% $208,133.60
Amt Left: 46.27% $205,712.10
Delta: -6.71% -$40,887.60
$658,645.20
Over/Under Est: 48.96% $216,491.20
Amt Left: 48.15% $214,069.70
Delta: -1.29% -$8,357.60
Over/Under Est: 50.76% $224,458.50
Amt Left: 49.94% $222,037.00
Delta: -1.21% -$7,967.30
Over/Under Est: 64.38% $284,662.00
Amt Left: 63.49% $282,240.50
Delta: -9.03% -$60,203.50

Bid Items & Bid Tabulations

43 Total 0 of 43
BEE  |  FM 796  |  CORPUS CHRISTI  |  1118-01-019  |  07/11/2017  |  $442,154.00  |  BR 1702(491)  |  REPLACE BRIDGE AND APPROACHES  |  68 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
3LW CIVIL LLC
LISKA CONSTRUCTION COMPANY, INC.
HILL COUNTRY BRIDGE, INC.
TMES LLC
MAIN LANE INDUSTRIES LTD.
ACME BRIDGE COMPANY, INC.
RELMCO, INC.
A GREATER AUSTIN DEVELOPMENT CONCRETE CONSTRUCTION, L.L.C.
SALINAS CONSTRUCTION TECHNOLOGIES, LTD.
PREPARING ROW
STA 7.000 $3,000.000 $500.000 $500.000 $1,700.000 $3,000.000 $3,000.000 $1,560.000 $9,000.000 $1,000.000 $726.030
EXCAVATION (ROADWAY)
CY 1,042.000 $9.000 $20.000 $8.000 $21.000 $15.000 $18.000 $14.600 $10.000 $45.000 $14.070
EXCAVATION (CHANNEL)
CY 69.000 $15.000 $20.000 $13.300 $22.000 $50.000 $25.000 $35.800 $35.000 $85.000 $30.040
BACKFILL (TY A OR B)
STA 6.000 $115.000 $200.000 $248.670 $1,630.000 $500.000 $800.000 $263.000 $500.000 $500.000 $675.120
FL BS (CMP IN PLC)(TYA GR1-2)(FNAL POS)
CY 990.000 $50.000 $70.000 $76.470 $76.500 $82.000 $80.000 $121.000 $75.000 $85.000 $85.230
PRIME COAT (MC-30)
GAL 480.000 $3.500 $6.000 $8.940 $5.350 $8.000 $5.000 $8.200 $6.000 $5.000 $5.840
ASPH (MULTI OPTION)
GAL 882.000 $2.250 $6.000 $4.900 $2.950 $6.000 $5.000 $4.500 $6.000 $2.750 $4.370
ASPH(AC-15P, HFRS-2P OR CRS-2P)
GAL 724.000 $2.500 $6.000 $5.300 $2.950 $7.000 $5.000 $4.500 $6.000 $2.750 $4.660
AGGR(TY-PB GR-4S OR TY-PB GR-4)(SAC-B)
CY 20.000 $75.000 $250.000 $247.500 $161.250 $300.000 $350.000 $246.000 $175.000 $150.000 $240.560
AGGR(TY-PB GR-3 OR TY-PB GR-3S)(SAC-B)
CY 26.000 $75.000 $250.000 $228.460 $161.250 $300.000 $350.000 $246.000 $175.000 $150.000 $253.540
CEM STABIL BKFL
CY 44.000 $100.000 $220.000 $125.000 $171.000 $175.000 $200.000 $266.000 $140.000 $250.000 $178.680
DRILL SHAFT (36 IN)
LF 280.000 $225.000 $100.000 $243.560 $249.000 $285.250 $300.000 $235.000 $265.000 $275.000 $259.300
CL C CONC (ABUT)
CY 36.800 $800.000 $800.000 $824.280 $748.000 $850.000 $1,200.000 $1,130.000 $1,200.000 $1,100.000 $1,155.320
REINF CONC SLAB
SF 2,210.000 $14.000 $14.000 $22.820 $22.250 $19.000 $30.000 $28.900 $24.000 $26.000 $20.990
PRESTR CONC BOX BEAM (5XB20)
LF 258.000 $200.000 $200.000 $218.180 $240.000 $259.000 $240.000 $338.000 $226.200 $285.000 $293.090
RIPRAP (CONC)(5 IN)
CY 31.000 $400.000 $400.000 $500.000 $735.000 $550.000 $500.000 $1,130.000 $500.000 $580.000 $837.010
RIPRAP (MOW STRIP)(4 IN)
CY 30.000 $450.000 $400.000 $535.000 $712.000 $550.000 $500.000 $902.000 $500.000 $850.000 $668.730
RAIL (TY T223)
LF 158.000 $100.000 $80.000 $100.000 $98.000 $110.000 $170.000 $123.000 $95.000 $170.000 $206.440
ARMOR JOINT (SEALED)
LF 60.000 $65.000 $90.000 $49.500 $60.000 $96.000 $80.000 $105.000 $94.900 $150.000 $141.730
REMOV STR (BRIDGE 0 - 99 FT LENGTH)
EA 1.000 $25,000.000 $10,000.000 $11,500.000 $30,000.000 $13,000.000 $18,000.000 $13,500.000 $25,000.000 $20,000.000 $25,276.350
MOBILIZATION
LS 1.000 $29,000.000 $50,000.000 $46,000.000 $57,000.000 $52,000.000 $50,000.000 $53,200.000 $60,000.000 $66,000.000 $130,247.720
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 4.000 $5,000.000 $2,000.000 $2,356.480 $3,150.000 $2,945.000 $2,000.000 $722.000 $8,000.000 $4,500.000 $1,066.200
ROCK FILTER DAMS (INSTALL) (TY 3)
LF 60.000 $45.000 $50.000 $56.670 $71.000 $65.000 $63.000 $66.300 $65.000 $71.000 $101.570
ROCK FILTER DAMS (REMOVE)
LF 60.000 $8.500 $7.500 $11.000 $25.000 $20.000 $7.000 $7.400 $30.000 $7.800 $29.850
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 78.000 $20.000 $25.000 $15.750 $30.000 $55.000 $41.000 $43.100 $45.000 $45.500 $31.330
CONSTRUCTION EXITS (REMOVE)
SY 78.000 $6.000 $10.000 $5.500 $12.000 $10.000 $7.000 $7.400 $20.000 $7.800 $12.080
BIODEG EROSN CONT LOGS (INSTL) (18")
LF 300.000 $6.000 $8.000 $7.430 $7.500 $6.000 $6.000 $6.400 $8.000 $6.700 $8.530
BIODEG EROSN CONT LOGS (REMOVE)
LF 300.000 $1.000 $3.000 $2.200 $2.750 $2.000 $1.500 $1.600 $3.000 $1.700 $2.540
MTL W-BEAM GD FEN (TIM POST)
LF 200.000 $18.500 $23.500 $20.700 $19.850 $30.000 $20.000 $20.900 $22.000 $22.000 $26.360
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 4.000 $1,500.000 $1,420.000 $1,321.720 $2,379.000 $2,100.000 $1,300.000 $1,340.000 $1,400.000 $1,800.000 $1,587.360
REMOVE METAL BEAM GUARD FENCE
LF 200.000 $1.250 $2.000 $2.220 $1.610 $3.000 $2.000 $2.100 $2.000 $2.200 $2.710
RM MTL BM GD FEN TRANS (T101)
EA 4.000 $100.000 $150.000 $150.000 $752.000 $200.000 $150.000 $159.000 $150.000 $170.000 $215.730
GUARDRAIL END TREATMENT (INSTALL)
EA 4.000 $2,200.000 $2,170.000 $2,445.450 $2,014.000 $2,800.000 $2,400.000 $2,470.000 $2,100.000 $2,600.000 $2,412.360
GUARDRAIL END TREATMENT (REMOVE)
EA 4.000 $180.000 $270.000 $200.000 $177.250 $200.000 $200.000 $212.000 $250.000 $220.000 $322.360
IN SM RD SN SUP&AM TYS80(1)SA(P)
EA 1.000 $250.000 $475.000 $920.420 $456.500 $800.000 $793.000 $758.000 $1,100.000 $800.000 $1,308.150
REMOVE SM RD SN SUP&AM
EA 3.000 $60.000 $50.000 $50.000 $69.800 $150.000 $150.000 $159.000 $45.000 $170.000 $65.150
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 16.000 $22.000 $21.000 $27.900 $24.150 $35.000 $30.000 $27.400 $20.000 $29.000 $35.780
REF PROF PAV MRK TY I(W)4"(SLD)(100MIL)
LF 1,400.000 $0.500 $4.000 $3.390 $3.760 $4.200 $3.500 $3.700 $3.850 $2.500 $11.070
REF PROF PAV MRK TY I(Y)4"(BRK)(100MIL)
LF 180.000 $0.500 $4.000 $3.550 $3.760 $4.200 $3.500 $3.700 $3.850 $2.500 $22.560
REF PROF PAV MRK TY I(Y)4"(SLD)(100MIL)
LF 700.000 $0.650 $4.000 $3.390 $3.760 $4.200 $3.500 $3.700 $3.850 $2.500 $16.640
REFL PAV MRKR TY II-A-A
EA 18.000 $3.000 $9.250 $13.540 $8.600 $9.500 $10.000 $8.500 $8.800 $9.400 $60.640
GEOGRID BASE REINFORCEMENT (TY I)
SY 2,686.000 $1.250 $2.000 $1.640 $1.100 $5.000 $2.000 $2.900 $2.200 $3.400 $3.230
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $10,000.000 $9,000.000 $1,655.500 $4,500.000 $5,400.000 $4,000.000 $63.700 $15,000.000 $5,500.000 $10,811.620
Totals: $442,154.000 $444,575.500 $488,184.004 $573,656.600 $589,549.000 $609,400.000 $650,287.600 $658,645.200 $666,612.500 $726,816.006