BEE CR (0916-25-019)

Items: 38

County: BEE
Length: N/A
Highway: CR
District: CORPUS CHRISTI
Control Number: 0916-25-019
DBE Goal: N/A
Project: BR 2023(296)
Guaranty: N/A
Time: 87 WORKING DAYS
Engineer's Estimate: $636,898.59
Date: 05/04/2023 (3 years ago)
Contract Number: N/A
Type: BRIDGE REPLACEMENT
Mail/Deliver Bids To: N/A
NICK NOVOSAD
ROBERTO A JIMENEZ
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (6)
E
Engineer's Estimate
$636,898.59
$569,954.80
Over/Under Est: -10.51% -$66,943.79
Over/Under Est: -7.48% -$47,666.89
Amt Left: 3.38% $19,276.90
Over/Under Est: -0.02% -$142.13
Amt Left: 11.72% $66,801.66
Delta: -8.07% -$47,524.76
Over/Under Est: 9.25% $58,924.60
Amt Left: 22.08% $125,868.39
Delta: -9.28% -$59,066.73
Over/Under Est: 9.47% $60,306.22
Amt Left: 22.33% $127,250.01
Delta: -0.20% -$1,381.62
$862,850.00
Over/Under Est: 35.48% $225,951.41
Amt Left: 51.39% $292,895.20
Delta: -23.76% -$165,645.19
Subcontractor Percentage Amount
JH CONTRACT FIELD SERVICES, LLC 5.95% $35,979.03
SOUTHWEST ROAD & SAFETY CONTRACTORS, LTD. 5.64% $34,104.49
HIGHWAY BARRICADES AND SERVICES, LLC 1.04% $6,288.77
Total: 12.63% $76,372.29

Bid Items & Bid Tabulations

38 Total 0 of 38
BEE  |  CR  |  CORPUS CHRISTI  |  0916-25-019  |  05/04/2023  |  $636,898.59  |  BR 2023(296)  |  BRIDGE REPL  |  87 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
ACEE CONSTRUCTION LLC.
CONSTAR CONSTRUCTION
LISKA CONSTRUCTION COMPANY, INC.
A GREATER AUSTIN DEVELOPMENT COMPANY, LTD.
E-Z BEL CONSTRUCTION, LLC
CK NEWBERRY, LLC
PREPARING ROW
STA 2.250 $5,000.000 $6,250.000 $1,200.000 $4,025.000 $10,500.000 $5,000.000 $20,000.000
EXCAVATION (ROADWAY)
CY 68.520 $22.000 $50.000 $25.000 $48.000 $112.000 $40.000 $125.000
EMBANKMENT (FINAL)(DENS CONT)(TY C)
CY 210.890 $35.000 $50.000 $30.000 $50.000 $75.000 $25.000 $100.000
BROADCAST SEED (PERM) (RURAL) (SANDY)
SY 620.000 $0.500 $3.100 $2.000 $5.000 $2.350 $2.260 $6.000
VEGETATIVE WATERING
MG 12.000 $75.000 $195.000 $110.000 $100.000 $240.000 $200.000 $100.000
FL BS (CMP IN PLC)(TYA GR1-2)(FNAL POS)
CY 64.000 $130.000 $225.000 $140.000 $210.000 $260.000 $160.000 $260.000
LIME (HYDRATED LIME (SLURRY))
TON 15.000 $500.000 $515.000 $450.000 $399.000 $400.000 $500.000 $450.000
LIME TRT (SUBGRADE)(8")
SY 640.000 $10.000 $12.500 $20.000 $39.000 $26.800 $8.000 $15.000
PRIME COAT (MC-30)
GAL 113.000 $8.000 $17.500 $46.000 $36.250 $35.600 $34.540 $25.000
ASPH (MULTI OPTION)
GAL 220.000 $6.000 $18.500 $23.000 $17.750 $18.200 $16.880 $10.000
AGGR(TY-PB GR-3 SAC-B)
CY 7.000 $375.000 $650.000 $1,800.000 $1,438.500 $1,415.000 $1,370.000 $1,000.000
AGGR(TY-PB GR-4 SAC-B)
CY 5.000 $300.000 $725.000 $2,500.000 $1,953.000 $1,915.000 $1,859.800 $1,200.000
ASPH(AC-15P, HFRS-2P OR CRS-2P)
GAL 181.000 $8.000 $17.500 $34.000 $27.000 $26.500 $25.740 $11.000
CEM STABIL BKFL
CY 76.000 $200.000 $155.000 $140.000 $233.000 $318.000 $250.000 $300.000
DRILL SHAFT (36 IN)
LF 180.000 $700.000 $365.000 $440.000 $400.000 $377.000 $350.000 $425.000
CL C CONC (ABUT)
CY 33.000 $1,300.000 $1,375.000 $1,100.000 $1,800.000 $1,290.000 $1,950.000 $2,000.000
CL C CONC (RAIL FOUNDATION)
CY 17.000 $700.000 $1,100.000 $660.000 $720.000 $835.000 $1,010.000 $1,500.000
REINF CONC SLAB
SF 1,820.000 $27.000 $27.500 $25.000 $40.000 $44.000 $40.000 $55.000
PRESTR CONC GIRDER (TX28)
LF 278.000 $200.000 $190.000 $350.000 $222.000 $275.800 $350.000 $300.000
RIPRAP (CONC)(5 IN)
CY 31.000 $700.000 $535.000 $620.000 $700.000 $783.000 $1,360.000 $700.000
RIPRAP (STONE PROTECTION)(24 IN)
CY 91.000 $220.000 $230.000 $190.000 $225.000 $239.000 $275.000 $300.000
RIPRAP (MOW STRIP)(4 IN)
CY 8.000 $600.000 $560.000 $660.000 $940.000 $1,265.000 $1,350.000 $1,200.000
RAIL (TY T221)
LF 292.000 $150.000 $157.500 $120.000 $165.000 $134.000 $282.000 $225.000
ARMOR JOINT (SEALED)
LF 51.000 $150.000 $164.150 $120.000 $160.000 $145.000 $207.000 $200.000
REMOV STR (BRIDGE 0 - 99 FT LENGTH)
EA 1.000 $25,000.000 $27,500.000 $20,000.000 $21,500.000 $33,255.000 $15,100.000 $50,000.000
MOBILIZATION
LS 1.000 $62,785.000 $56,000.000 $53,000.000 $47,500.000 $69,580.000 $40,000.000 $80,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 6.000 $5,000.000 $3,333.350 $2,400.000 $1,400.000 $3,350.000 $2,500.000 $6,000.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 60.000 $35.000 $96.600 $70.000 $68.000 $78.000 $75.000 $80.000
ROCK FILTER DAMS (REMOVE)
LF 60.000 $15.000 $71.400 $20.000 $20.000 $24.000 $25.000 $15.000
MTL W-BEAM GD FEN (TIM POST)
LF 50.000 $35.000 $68.000 $40.000 $68.000 $30.650 $100.000 $65.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 2.000 $2,300.000 $2,373.000 $3,400.000 $2,340.000 $3,163.000 $2,325.000 $2,500.000
REMOVE METAL BEAM GUARD FENCE
LF 50.000 $3.000 $3.150 $14.000 $20.000 $3.100 $5.000 $10.000
GUARDRAIL END TREATMENT (INSTALL)
EA 2.000 $3,400.000 $3,454.500 $4,000.000 $4,100.000 $3,390.000 $3,605.000 $4,500.000
CRASH CUSH ATTEN (INSTL) (S) (TL3)
EA 2.000 $25,000.000 $8,977.500 $15,000.000 $13,900.000 $8,807.000 $9,725.000 $13,000.000
IN SM RD SN SUP&AM TYS80(1)SA(T)
EA 2.000 $1,000.000 $976.500 $500.000 $1,000.000 $958.000 $1,200.000 $2,300.000
REMOVE SM RD SN SUP&AM
EA 3.000 $130.000 $89.250 $300.000 $100.000 $100.000 $100.000 $300.000
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
EA 6.000 $30.000 $37.800 $60.000 $50.000 $37.000 $25.000 $50.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 4.000 $42.000 $42.000 $60.000 $50.000 $41.000 $25.000 $55.000
Totals: $636,898.590 $569,954.800 $589,231.700 $636,756.460 $695,823.190 $697,204.810 $862,850.000