BASTROP FM 969 (1186-02-028)
Items: 63
County: BASTROP
Length: 1.6510 MILES
Highway: FM 969
District: AUSTIN
Control Number: 1186-02-028
DBE Goal: 0.0%
Project: STP 2026(607)VRU
Guaranty: $67,000.00
Time: 99 WORKING DAYS
Engineer's Estimate: $3,339,793.85
Date: 05/06/2026 (5 weeks ago)
Contract Number: 5263017
Type: HAZARD ELIMINATION & SAFETY
Project ID: A00193147
Contract Type: Federal
Project Description: SAFETY TREAT FIXED OBJECTS, WIDEN LANE(S), WIDEN PAVED SHOULDERS (TO >5 FT.)
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
DIANA SCHULZE
SHANE SWIMM
BASTROP FM 969 (1186-02-028)
Project Name: N/A
Project: STP 2026(607)VRU
Length: 1.6510 MILES
Project Type: CONSTRUCTION
Limits From: 0.18 MI N OF UTLEY RD
Limits To: HOWARD LN
Project Description: SAFETY TREAT FIXED OBJECTS, WIDEN LANE(S), WIDEN PAVED SHOULDERS (TO >5 FT.)
Bidders (8)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$3,339,793.85 | |||
| $3,189,428.56 |
-4.5%
-$150,365.29
|
|||
| $3,287,460.68 |
-1.57%
-$52,333.17
|
3.07%
$98,032.12
|
||
| $3,293,757.70 |
-1.38%
-$46,036.15
|
3.27%
$104,329.14
|
-0.19%
-$6,297.02
|
|
| $3,309,502.87 |
-0.91%
-$30,290.98
|
3.76%
$120,074.31
|
-0.48%
-$15,745.17
|
|
| $3,639,859.55 |
8.98%
$300,065.70
|
14.12%
$450,430.99
|
-9.98%
-$330,356.68
|
|
| $3,649,743.15 |
9.28%
$309,949.30
|
14.43%
$460,314.59
|
-0.27%
-$9,883.60
|
|
| $3,785,605.87 |
13.35%
$445,812.02
|
18.69%
$596,177.31
|
-3.72%
-$135,862.72
|
|
| $3,867,053.00 |
15.79%
$527,259.15
|
21.25%
$677,624.44
|
-2.15%
-$81,447.13
|
E
Engineer's Estimate
$3,339,793.85
1
Awarded
$3,189,428.56
Over/Under Est:
-4.5%
-$150,365.29
$3,287,460.68
Over/Under Est:
-1.57%
-$52,333.17
Amt Left:
3.07%
$98,032.12
$3,293,757.70
Over/Under Est:
-1.38%
-$46,036.15
Amt Left:
3.27%
$104,329.14
Delta:
-0.19%
-$6,297.02
$3,309,502.87
Over/Under Est:
-0.91%
-$30,290.98
Amt Left:
3.76%
$120,074.31
Delta:
-0.48%
-$15,745.17
$3,639,859.55
Over/Under Est:
8.98%
$300,065.70
Amt Left:
14.12%
$450,430.99
Delta:
-9.98%
-$330,356.68
$3,649,743.15
Over/Under Est:
9.28%
$309,949.30
Amt Left:
14.43%
$460,314.59
Delta:
-0.27%
-$9,883.60
$3,785,605.87
Over/Under Est:
13.35%
$445,812.02
Amt Left:
18.69%
$596,177.31
Delta:
-3.72%
-$135,862.72
$3,867,053.00
Over/Under Est:
15.79%
$527,259.15
Amt Left:
21.25%
$677,624.44
Delta:
-2.15%
-$81,447.13
Bid Items & Bid Tabulations
63
Total
0 of 63
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
| Description | Amount |
|---|---|
| EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) | $2,500.00 |
| LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (PART) | $2,500.00 |
| SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) | $2,500.00 |
| Total: | $7,500.00 |