BASTROP FM 812 (1149-02-033)

Items: 129

County: BASTROP
Length: 0.0000 MILES
Highway: FM 812
District: AUSTIN
Control Number: 1149-02-033
DBE Goal: 0.0%
Project: C 1149-2-33
Guaranty: $100,000.00
Time: 312 WORKING DAYS
Engineer's Estimate: $7,909,275.61
Date: 06/04/2025 (1 year ago)
Contract Number: 6253006
Type: HIGHWAY IMPROVEMENT
Project ID: A00190263
Project Description: INSTALL CONTINUOUS LEFT-TURN LANE
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
DIANA SCHULZE
SHANE SWIMM
MAHENDRAN THIVAKARAN
YETNAYET BOGALE
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (7)
E
Engineer's Estimate
$7,909,275.61
$7,601,604.21
Over/Under Est: -3.89% -$307,671.40
Over/Under Est: -1.95% -$154,250.03
Amt Left: 2.02% $153,421.37
Over/Under Est: 8.13% $643,270.71
Amt Left: 12.51% $950,942.11
Delta: -10.28% -$797,520.74
$8,686,090.06
Over/Under Est: 9.82% $776,814.45
Amt Left: 14.27% $1,084,485.85
Delta: -1.56% -$133,543.74
Over/Under Est: 14.95% $1,182,724.30
Amt Left: 19.61% $1,490,395.70
Delta: -4.67% -$405,909.85
Over/Under Est: 22.19% $1,755,009.94
Amt Left: 27.13% $2,062,681.34
Delta: -6.29% -$572,285.64
Over/Under Est: 23.09% $1,826,332.39
Amt Left: 28.07% $2,134,003.79
Delta: -0.74% -$71,322.45
Subcontractor Percentage Amount
LONE STAR PAVING COMPANY 30.67% $2,331,412.01
ENVIRONMENTAL SAFETY SERVICES, INC. 7.30% $554,917.11
*AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. 2.23% $169,515.77
D. I. J. CONSTRUCTION, INC. 1.73% $131,507.75
GBC GENERAL BARRICADE COMPANY LLC 0.26% $19,764.17
Total: 42.19% $3,207,116.81

Bid Items & Bid Tabulations

129 Total 0 of 129
BASTROP  |  FM 812  |  AUSTIN  |  1149-02-033  |  06/04/2025  |  $7,909,275.61  |  C 1149-2-33  |  HWY IMPRV  |  312 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
DAN WILLIAMS COMPANY
HUNTER INDUSTRIES, LTD.
ACME BRIDGE COMPANY, INC.
C. E. BARKER, LTD.
DEAN WORD COMPANY, LTD.
AARON CONCRETE CONTRACTORS, LLC
JOE BLAND CONSTRUCTION LLC
PREPARING ROW
STA 156.100 $2,000.000 $2,500.000 $2,697.310 $1,370.000 $5,500.000 $1,150.000 $650.000 $2,000.000
EXCAV (ROADWAY)
CY 12,219.000 $20.500 $17.000 $24.700 $22.400 $26.030 $34.350 $31.000 $30.000
EMBANK (FNL)(OC)(TY B)
CY 5,214.000 $20.000 $25.000 $24.700 $10.100 $27.840 $29.650 $10.000 $25.000
EMBANK (FNL)(OC)(TY C)
CY 1,613.000 $50.000 $48.500 $87.010 $58.900 $27.840 $133.250 $100.000 $75.000
FURN & PLACE TOPSOIL (4")
SY 52,742.000 $2.000 $1.250 $1.620 $1.590 $2.170 $2.300 $1.900 $3.000
BROADCAST SEED (TEMP_WARM_COOL)
SY 52,742.000 $0.300 $0.170 $0.170 $0.120 $0.120 $0.300 $0.150 $0.500
DRILL SEED (PERM_RURAL_CLAY)
SY 52,742.000 $0.350 $0.200 $0.200 $0.160 $0.150 $0.300 $0.180 $0.500
VEGETATIVE WATERING
TGL 886.000 $42.500 $8.000 $24.500 $39.400 $61.390 $163.600 $35.000 $50.000
SOIL RET BLKT(SL_MOD_CLAY_LONG)
SY 52,742.000 $1.400 $1.750 $1.700 $0.800 $0.790 $1.000 $1.000 $2.000
FL BS (CMP IN PLC)(TY D GR 5)(FNAL POS)
CY 11,487.000 $69.000 $55.000 $70.950 $84.300 $74.340 $86.650 $95.000 $120.000
PRIME COAT (MULTI OPTION)
GAL 8,726.000 $5.250 $3.500 $4.820 $3.650 $3.610 $5.500 $4.300 $4.000
D-GR HMA TY-B PG64-22
TON 4,484.000 $122.500 $130.000 $115.900 $127.000 $125.780 $116.800 $150.000 $130.000
D-GR HMA TY-D PG76-22
TON 2,799.000 $140.000 $170.000 $121.400 $173.000 $171.150 $135.750 $205.000 $178.000
D-GR HMA TY-D PG76-22 (LEVEL-UP)
TON 2,046.000 $152.500 $150.000 $123.800 $148.000 $146.400 $152.900 $175.000 $155.000
TOM-C PG76-22 SAC-B
TON 4,051.000 $162.500 $160.000 $157.700 $158.000 $156.710 $142.900 $187.000 $165.000
STRUCT EXCAV (BOX)
CY 428.000 $27.000 $1.000 $100.400 $15.500 $56.710 $54.000 $165.000 $80.000
FLOWABLE BACKFILL
CY 83.000 $375.000 $250.000 $334.670 $439.000 $219.860 $261.400 $268.000 $295.000
TRENCH EXCAVATION PROTECTION
LF 146.000 $85.000 $1.000 $18.960 $10.300 $56.960 $179.550 $6.000 $10.000
TEMPORARY SPL SHORING
SF 6,762.000 $37.500 $7.000 $7.000 $35.200 $5.160 $4.700 $31.000 $36.000
TEMPORARY SPL SHORING (COFFERDAM)
SF 600.000 $100.000 $15.000 $100.000 $24.800 $36.090 $222.850 $61.000 $36.000
DRILL SHAFT (TRF SIG POLE) (30 IN)
LF 22.000 $375.000 $350.000 $496.800 $501.000 $465.720 $533.550 $403.000 $380.000
RIPRAP (CONC)(4 IN)
CY 2.370 $1,700.000 $1,500.000 $1,673.700 $776.000 $881.510 $1,589.950 $932.000 $2,600.000
RIPRAP (CONC)(5 IN)
CY 920.000 $500.000 $450.000 $585.790 $569.000 $701.080 $616.900 $854.000 $675.000
RIPRAP (MOW STRIP)(4 IN)
CY 224.000 $550.000 $700.000 $613.690 $776.000 $520.660 $795.950 $936.000 $805.000
RIPRAP (STONE PROTECTION)(15 IN)
CY 28.000 $350.000 $270.000 $250.000 $569.000 $283.530 $246.500 $357.000 $350.000
CONC BOX CULV (9 FT X 8 FT)
LF 116.000 $1,400.000 $1,500.000 $1,697.940 $1,760.000 $1,331.770 $2,178.700 $1,460.000 $2,125.000
CONC BOX CULV (10 FT X 9 FT)
LF 30.000 $2,500.000 $2,500.000 $2,570.250 $2,120.000 $1,577.310 $3,156.900 $1,820.000 $2,615.000
RC PIPE (CL III)(18 IN)
LF 1,838.000 $90.000 $70.000 $109.320 $93.100 $184.230 $81.950 $120.000 $160.000
RC PIPE (CL IV)(24 IN)
LF 27.000 $300.000 $370.000 $139.450 $136.000 $194.420 $885.000 $654.000 $240.000
RC PIPE (CL IV)(30 IN)
LF 13.000 $400.000 $435.000 $390.450 $204.000 $211.040 $1,024.000 $752.000 $425.000
RC PIPE (ARCH)(CL III)(DES 1)
LF 138.000 $250.000 $160.000 $273.310 $295.000 $283.410 $220.600 $310.000 $245.000
WINGWALL (PW - 1) (HW=10 FT)
EA 1.000 $70,000.000 $50,000.000 $52,096.710 $44,100.000 $36,085.000 $81,626.000 $94,000.000 $70,500.000
WINGWALL (PW - 1) (HW=12 FT)
EA 1.000 $99,000.000 $68,000.000 $66,375.890 $51,100.000 $36,085.000 $115,510.800 $118,000.000 $82,500.000
HEADWALL (CH - PW - 0)(DIA= 24 IN)(MOD)
EA 3.000 $8,500.000 $19,000.000 $35,140.180 $14,000.000 $21,651.000 $57,614.700 $10,800.000 $30,250.000
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 94.000 $1,450.000 $2,600.000 $1,840.680 $1,430.000 $3,260.020 $1,925.800 $2,000.000 $2,300.000
SET (TY II) (24 IN) (RCP) (3: 1) (C)
EA 1.000 $3,250.000 $2,500.000 $3,625.570 $1,790.000 $3,371.370 $2,607.500 $1,625.000 $3,600.000
SET (TY II) (24 IN) (RCP) (4: 1) (C)
EA 1.000 $3,250.000 $2,600.000 $3,904.460 $2,010.000 $3,468.280 $2,578.350 $2,560.000 $3,800.000
SET (TY II) (30 IN) (RCP) (3: 1) (C)
EA 2.000 $3,250.000 $3,500.000 $3,569.800 $2,530.000 $3,781.710 $3,318.500 $3,300.000 $4,600.000
ADJUSTING MANHOLES
EA 1.000 $6,500.000 $3,200.000 $6,900.000 $9,980.000 $541.280 $13,687.650 $6,340.000 $1,000.000
REMOV STR (SET)
EA 74.000 $525.000 $400.000 $669.340 $569.000 $360.850 $826.800 $760.000 $725.000
REMOV STR (HEADWALL)
EA 3.000 $2,250.000 $2,250.000 $2,454.230 $1,600.000 $5,412.750 $4,378.850 $3,500.000 $1,500.000
REMOV STR (PIPE)
LF 1,322.000 $22.500 $18.000 $27.890 $23.800 $21.650 $16.950 $36.000 $20.000
MOBILIZATION
LS 1.000 $639,300.000 $750,000.000 $647,077.100 $800,000.000 $765,000.000 $650,000.000 $975,000.000 $295,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 19.000 $7,500.000 $15,000.000 $8,129.720 $36,110.000 $1,773.320 $9,867.000 $2,300.000 $17,825.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $12,000.000 $12,500.000 $7,876.990 $15,000.000 $20,620.000 $21,974.150 $10,500.000 $25,000.000
TMA (STATIONARY)
DAY 25.000 $300.000 $450.000 $210.050 $260.000 $1,031.000 $534.250 $640.000 $225.000
TMA (MOBILE OPERATION)
HR 20.000 $150.000 $75.000 $105.030 $119.000 $154.650 $144.900 $100.000 $110.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 191.000 $42.500 $47.500 $47.500 $61.100 $60.930 $68.450 $72.000 $55.000
ROCK FILTER DAMS (INSTALL) (TY 4)
LF 100.000 $80.000 $90.000 $90.000 $72.500 $72.260 $81.450 $86.000 $75.000
ROCK FILTER DAMS (REMOVE)
LF 291.000 $12.500 $22.500 $22.500 $21.500 $21.460 $24.150 $25.000 $35.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 6,213.000 $5.520 $4.000 $3.650 $3.750 $3.740 $4.200 $4.500 $5.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 6,213.000 $1.250 $1.000 $0.500 $1.100 $1.100 $1.300 $1.300 $2.000
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 100.000 $7.880 $8.000 $7.500 $12.800 $12.730 $14.450 $15.000 $10.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 100.000 $2.690 $1.000 $1.000 $1.550 $1.540 $1.800 $1.800 $2.000
CONSTRUCTING DETOURS
SY 929.000 $150.000 $150.000 $76.700 $139.000 $118.570 $183.250 $152.000 $170.000
ONE-WAY TRAF CONT (PORT TRAF SIG)
MO 4.000 $8,500.000 $5,000.000 $4,588.380 $4,200.000 $6,186.000 $10,889.900 $19,600.000 $7,500.000
PTB (FUR&INST)(SSCB OR CSB)(TY1)OR(STL)
LF 1,410.000 $55.000 $20.000 $30.000 $15.200 $80.930 $30.150 $89.000 $90.000
PTB (MOVE)(SSCB OR CSB)(TY1)OR(STL)
LF 1,500.000 $30.000 $7.000 $15.000 $17.300 $10.830 $9.700 $29.000 $22.000
PTB (REMOVE)(SSCB OR CSB)(TY1)OR(STL)
LF 1,410.000 $25.000 $12.000 $13.000 $15.000 $21.140 $17.950 $33.000 $23.000
INTERSECTIONS (ACP)
SY 2,095.000 $70.000 $80.000 $74.990 $94.700 $52.580 $83.950 $94.000 $58.000
DRIVEWAYS (CONC)
SY 122.000 $150.000 $125.000 $102.650 $109.000 $53.610 $176.250 $31.000 $225.000
DRIVEWAYS (ACP)
SY 2,059.000 $67.500 $80.000 $61.700 $91.000 $56.710 $189.750 $95.000 $190.000
MTL W-BEAM GD FEN (TIM POST)
LF 4,037.500 $25.500 $23.000 $28.360 $24.800 $25.030 $27.850 $38.000 $32.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 10.000 $1,700.000 $1,500.000 $1,325.440 $1,400.000 $1,486.570 $1,566.000 $2,150.000 $1,850.000
REMOVE METAL BEAM GUARD FENCE
LF 925.000 $6.000 $4.000 $3.180 $2.600 $8.250 $3.000 $7.000 $6.000
REMOVE DOWNSTREAM ANCHOR TERMINAL
EA 6.000 $150.000 $300.000 $249.180 $259.000 $154.910 $290.050 $182.000 $155.000
GUARDRAIL END TREATMENT (INSTALL)
EA 10.000 $3,500.000 $4,500.000 $3,234.060 $3,100.000 $3,734.730 $3,479.900 $4,900.000 $4,220.000
GUARDRAIL END TREATMENT (REMOVE)
EA 6.000 $500.000 $300.000 $360.520 $259.000 $428.400 $290.050 $370.000 $325.000
CRASH CUSH ATTEN (MOVE & RESET)
EA 8.000 $1,250.000 $1,000.000 $1,776.080 $853.000 $1,704.000 $992.700 $1,280.000 $1,100.000
CRASH CUSH ATTEN (REMOVE)
EA 6.000 $800.000 $850.000 $858.880 $1,280.000 $1,224.230 $641.350 $875.000 $750.000
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
EA 6.000 $9,000.000 $6,500.000 $8,562.320 $7,190.000 $9,498.160 $8,153.500 $12,700.000 $10,950.000
WIRE FENCE (TY A)
LF 100.000 $35.000 $45.000 $36.530 $35.600 $51.550 $39.800 $42.000 $40.000
WIRE FENCE (TY C)
LF 100.000 $35.000 $45.000 $38.970 $38.000 $51.550 $42.600 $45.000 $52.000
GATE (TY 1)
EA 2.000 $1,000.000 $1,250.000 $980.820 $956.000 $515.500 $1,073.050 $1,130.000 $1,925.000
MAILBOX INSTALL-S (TWW-POST) TY 4
EA 14.000 $310.000 $325.000 $339.310 $233.000 $231.980 $365.500 $275.000 $750.000
MAILBOX INSTALL-D (TWW-POST) TY 4
EA 2.000 $400.000 $325.000 $381.730 $269.000 $268.060 $365.500 $320.000 $785.000
MAILBOX INSTALL-M (TWW-POST) TY 4
EA 16.000 $900.000 $775.000 $954.310 $620.000 $618.600 $887.300 $735.000 $1,250.000
CONDT (PVC) (SCH 80) (2")
LF 200.000 $25.000 $40.000 $32.000 $34.800 $16.740 $37.150 $54.000 $50.000
CONDT (PVC) (SCH 80) (3")
LF 115.000 $25.000 $41.000 $45.000 $49.000 $16.740 $52.300 $55.000 $52.000
ELEC CONDR (NO.8) BARE
LF 750.000 $1.900 $3.000 $2.700 $2.950 $2.300 $3.200 $4.000 $4.000
ELEC CONDR (NO.8) INSULATED
LF 1,260.000 $2.000 $4.000 $2.700 $2.950 $2.610 $3.200 $5.400 $5.000
ELEC CONDR (NO.6) BARE
LF 60.000 $2.750 $4.000 $3.350 $3.650 $2.740 $4.000 $5.400 $5.000
ELEC CONDR (NO.6) INSULATED
LF 120.000 $2.750 $5.000 $3.350 $3.650 $5.160 $4.000 $6.700 $6.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 29.000 $685.000 $525.000 $726.340 $672.000 $670.150 $602.050 $800.000 $995.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 19.000 $950.000 $625.000 $842.980 $724.000 $721.700 $695.850 $860.000 $1,085.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T-2EXT)
EA 4.000 $850.000 $675.000 $922.500 $801.000 $799.030 $770.300 $850.000 $1,200.000
IN SM RD SN SUP&AM TY10BWG(1)SA(U)
EA 2.000 $1,000.000 $825.000 $1,187.590 $905.000 $902.130 $946.550 $1,070.000 $1,400.000
IN SM RD SN SUP&AM TYS80(1)SA(T-2EXT)
EA 2.000 $1,100.000 $850.000 $1,214.100 $977.000 $974.300 $981.400 $1,160.000 $1,500.000
REMOVE SM RD SN SUP&AM
EA 122.000 $160.000 $100.000 $106.030 $103.000 $103.100 $86.950 $123.000 $115.000
INSTL DEL ASSM (D-SW)SZ 2(WC)GND(BI)
EA 4.000 $100.000 $35.000 $77.410 $56.900 $56.710 $40.600 $67.000 $70.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 59.000 $65.000 $35.000 $48.780 $46.500 $46.400 $28.850 $55.000 $50.000
WK ZN PAV MRK NON-REMOV (W)6"(SLD)
LF 10,134.000 $0.500 $0.350 $0.350 $0.360 $1.550 $0.500 $0.450 $1.000
WK ZN PAV MRK NON-REMOV (W)8"(SLD)
LF 300.000 $1.500 $0.550 $0.550 $0.410 $2.060 $0.500 $0.500 $1.000
WK ZN PAV MRK NON-REMOV (W)24"(SLD)
LF 87.000 $4.000 $12.000 $12.000 $5.200 $6.700 $5.700 $6.100 $5.000
WK ZN PAV MRK NON-REMOV (W)(ARROW)
EA 2.000 $100.000 $275.000 $275.000 $103.000 $139.190 $115.950 $122.000 $80.000
WK ZN PAV MRK NON-REMOV(W)(WORD)
EA 2.000 $100.000 $350.000 $350.000 $103.000 $170.120 $115.950 $122.000 $80.000
WK ZN PAV MRK NON-REMOV (Y)6"(BRK)
LF 210.000 $2.000 $0.420 $0.420 $0.570 $2.060 $0.800 $0.700 $1.000
WK ZN PAV MRK NON-REMOV (Y)6"(SLD)
LF 10,716.000 $0.500 $0.350 $0.350 $0.360 $1.550 $0.500 $0.400 $1.000
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 15.000 $3.000 $2.500 $1.630 $17.100 $0.930 $3.700 $0.900 $1.000
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 2,064.000 $1.750 $2.500 $1.630 $1.750 $0.930 $3.700 $1.900 $1.000
REFL PAV MRK TY I (W)8"(SLD)(090MIL)
LF 300.000 $1.500 $1.300 $1.300 $1.400 $2.060 $1.500 $1.700 $3.000
REFL PAV MRK TY I (W)24"(SLD)(090MIL)
LF 118.000 $12.000 $13.500 $13.500 $6.700 $6.700 $7.500 $8.000 $12.000
REFL PAV MRK TY I (W)(ARROW)(090MIL)
EA 6.000 $225.000 $325.000 $325.000 $181.000 $139.190 $202.900 $215.000 $205.000
REFL PAV MRK TY I (W)(WORD)(090MIL)
EA 2.000 $275.000 $395.000 $395.000 $207.000 $170.120 $232.050 $245.000 $290.000
RE PM TY II (W) 6" (SLD)
LF 30,084.000 $0.400 $0.230 $0.230 $0.310 $0.670 $0.300 $0.400 $1.000
RE PM TY II (W) 8" (SLD)
LF 300.000 $1.000 $0.320 $0.320 $0.410 $1.030 $0.500 $0.500 $1.000
RE PM TY II (W) 24" (SLD)
LF 118.000 $4.000 $2.580 $2.500 $4.150 $3.090 $4.700 $5.000 $4.000
RE PM TY II (W) (ARROW)
EA 6.000 $85.000 $25.000 $25.000 $85.300 $103.100 $95.600 $100.000 $80.000
RE PM TY II (W) (WORD)
EA 2.000 $100.000 $35.000 $35.000 $95.700 $103.100 $107.300 $113.000 $80.000
RE PM TY II (Y) 6" (BRK)
LF 6,860.000 $1.000 $0.250 $0.250 $0.410 $0.670 $0.500 $0.500 $1.000
RE PM TY II (Y) 6" (SLD)
LF 31,037.000 $0.650 $0.230 $0.230 $0.310 $0.670 $0.300 $0.400 $1.000
RE PROFILE PM TY I(W)6"(SLD)(090MIL)
LF 30,084.000 $1.250 $1.200 $1.200 $1.050 $1.550 $1.300 $1.200 $1.000
RE PROFILE PM TY I(Y)6"(SLD)(090MIL)
LF 31,037.000 $1.300 $1.200 $1.200 $1.050 $1.550 $1.300 $1.200 $1.000
RE PROFILE PM TY I(Y)6"(BRK)(090MIL)
LF 6,860.000 $1.400 $1.300 $1.300 $1.050 $2.060 $1.300 $1.200 $1.000
REFL PAV MRKR TY I-C
EA 16.000 $10.000 $8.000 $8.000 $6.200 $8.250 $7.000 $7.400 $6.000
REFL PAV MRKR TY II-A-A
EA 606.000 $10.000 $7.250 $7.250 $6.200 $5.670 $7.000 $7.400 $6.000
ELIM EXT PM & MRKS (4")
LF 8,400.000 $1.500 $0.950 $0.950 $0.570 $0.520 $0.800 $0.800 $1.000
INSTALL HWY TRF SIG (SYSTEM)
EA 1.000 $27,500.000 $20,000.000 $13,000.000 $14,100.000 $37,547.360 $15,079.350 $18,800.000 $18,750.000
VEH SIG SEC (12")LED(GRN)
EA 8.000 $375.000 $475.000 $420.000 $457.000 $341.330 $487.250 $638.000 $650.000
VEH SIG SEC (12")LED(YEL)
EA 8.000 $375.000 $475.000 $420.000 $457.000 $341.330 $487.250 $638.000 $650.000
VEH SIG SEC (12")LED(RED)
EA 8.000 $375.000 $475.000 $420.000 $457.000 $341.330 $487.250 $638.000 $650.000
BACKPLATE W/REFL BRDR(3 SEC)
EA 8.000 $200.000 $243.000 $190.000 $207.000 $232.660 $220.350 $326.000 $350.000
TRF SIG CBL (TY A)(14 AWG)(5 CONDR)
LF 1,006.000 $2.500 $5.000 $3.000 $3.250 $2.560 $3.500 $6.700 $6.000
INSTL RDSD FLSH BCN ASSM (SOLAR PWRD)
EA 2.000 $12,000.000 $9,000.000 $9,900.000 $10,800.000 $7,294.480 $11,483.500 $10,500.000 $9,950.000
INS TRF SIG PL AM(S)1 ARM(24')LUM
EA 2.000 $12,000.000 $21,500.000 $13,200.000 $14,400.000 $15,434.750 $15,311.400 $24,400.000 $23,500.000
BONDING COURSE
GAL 13,363.000 $4.500 $3.500 $3.660 $3.650 $3.610 $13.000 $4.300 $4.000
GEOGRID REINFORCE EMBANKMENTS (TY A)
SY 8,959.000 $10.000 $3.000 $2.020 $5.500 $3.530 $4.000 $8.150 $9.000
RVDS (PRESENCE DETECTION ONLY)
EA 4.000 $8,000.000 $8,500.000 $8,800.000 $9,580.000 $8,043.130 $10,207.550 $9,500.000 $9,000.000
RVDS (ADVANCE DETENTION ONLY)
EA 2.000 $8,000.000 $8,500.000 $13,800.000 $15,000.000 $13,149.660 $16,007.550 $9,500.000 $9,000.000
Totals: $7,909,275.610 $7,601,604.210 $7,755,025.580 $8,552,546.320 $8,686,090.054 $9,091,999.906 $9,664,285.550 $9,735,608.000
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) $7,000.00
LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) $74,300.00
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) $35,000.00
CONTRACTOR FORCE ACCOUNT WORK (NON-PART) $2,000.00
STATE FORCE ACCOUNT WORK (NON-PART) $1,000.00
Total: $119,300.00