BASTROP FM 812 (1149-02-033)
Items: 129
County: BASTROP
Length: 0.0000 MILES
Highway: FM 812
District: AUSTIN
Control Number: 1149-02-033
DBE Goal: 0.0%
Project: C 1149-2-33
Guaranty: $100,000.00
Time: 312 WORKING DAYS
Engineer's Estimate: $7,909,275.61
Date: 06/04/2025 (1 year ago)
Contract Number: 6253006
Type: HIGHWAY IMPROVEMENT
Project ID: A00190263
Project Description: INSTALL CONTINUOUS LEFT-TURN LANE
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
DIANA SCHULZE
SHANE SWIMM
MAHENDRAN THIVAKARAN
YETNAYET BOGALE
BASTROP FM 812 (1149-02-033)
Project Name: N/A
Project: C 1149-2-33
Length: 0.0000 MILES
Project Type: CONSTRUCTION
Limits From: 0.19 MI NW OLD SAN ANTONIO/WATTS LANE
Limits To: 0.19 MI SE OF ARTESIAN DRIVE
Project Description: INSTALL CONTINUOUS LEFT-TURN LANE
Informational
Bidders (7)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$7,909,275.61 | |||
| $7,601,604.21 |
-3.89%
-$307,671.40
|
|||
| $7,755,025.58 |
-1.95%
-$154,250.03
|
2.02%
$153,421.37
|
||
| $8,552,546.32 |
8.13%
$643,270.71
|
12.51%
$950,942.11
|
-10.28%
-$797,520.74
|
|
| $8,686,090.06 |
9.82%
$776,814.45
|
14.27%
$1,084,485.85
|
-1.56%
-$133,543.74
|
|
| $9,091,999.91 |
14.95%
$1,182,724.30
|
19.61%
$1,490,395.70
|
-4.67%
-$405,909.85
|
|
| $9,664,285.55 |
22.19%
$1,755,009.94
|
27.13%
$2,062,681.34
|
-6.29%
-$572,285.64
|
|
| $9,735,608.00 |
23.09%
$1,826,332.39
|
28.07%
$2,134,003.79
|
-0.74%
-$71,322.45
|
E
Engineer's Estimate
$7,909,275.61
1
Awarded
$7,601,604.21
Over/Under Est:
-3.89%
-$307,671.40
$7,755,025.58
Over/Under Est:
-1.95%
-$154,250.03
Amt Left:
2.02%
$153,421.37
$8,552,546.32
Over/Under Est:
8.13%
$643,270.71
Amt Left:
12.51%
$950,942.11
Delta:
-10.28%
-$797,520.74
$8,686,090.06
Over/Under Est:
9.82%
$776,814.45
Amt Left:
14.27%
$1,084,485.85
Delta:
-1.56%
-$133,543.74
$9,091,999.91
Over/Under Est:
14.95%
$1,182,724.30
Amt Left:
19.61%
$1,490,395.70
Delta:
-4.67%
-$405,909.85
$9,664,285.55
Over/Under Est:
22.19%
$1,755,009.94
Amt Left:
27.13%
$2,062,681.34
Delta:
-6.29%
-$572,285.64
$9,735,608.00
Over/Under Est:
23.09%
$1,826,332.39
Amt Left:
28.07%
$2,134,003.79
Delta:
-0.74%
-$71,322.45
| Subcontractor | Percentage | Amount |
|---|---|---|
| LONE STAR PAVING COMPANY | 30.67% | $2,331,412.01 |
| ENVIRONMENTAL SAFETY SERVICES, INC. | 7.30% | $554,917.11 |
| *AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. | 2.23% | $169,515.77 |
| D. I. J. CONSTRUCTION, INC. | 1.73% | $131,507.75 |
| GBC GENERAL BARRICADE COMPANY LLC | 0.26% | $19,764.17 |
| Total: | 42.19% | $3,207,116.81 |
Bid Items & Bid Tabulations
129
Total
0 of 129
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
| Description | Amount |
|---|---|
| EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) | $7,000.00 |
| LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) | $74,300.00 |
| SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) | $35,000.00 |
| CONTRACTOR FORCE ACCOUNT WORK (NON-PART) | $2,000.00 |
| STATE FORCE ACCOUNT WORK (NON-PART) | $1,000.00 |
| Total: | $119,300.00 |