Show Job Controls
Bid Cobra

BASTROP FM 696 (1073-01-021)

Items: 63

County: BASTROP
Length: 0.0000 MILES
Highway: FM 696
District: AUSTIN
Control Number: 1073-01-021
DBE Goal: 0.0%
Project: C 1073-1-21
Guaranty: $100,000.00
Time: 140 WORKING DAYS
Engineer's Estimate: $8,424,891.46
Date: 10/08/2025 (8 months ago)
Contract Number: 10253006
Type: PREVENTIVE MAINTENANCE
Project ID: A00178516
Project Description: FDR, LEVEL UP AND TOM
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
DIANA SCHULZE
SHANE SWIMM
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (9)
E
Engineer's Estimate
$8,424,891.46
$6,445,912.15
Over/Under Est: -23.49% -$1,978,979.31
$6,879,000.62
Over/Under Est: -18.35% -$1,545,890.84
Amt Left: 6.72% $433,088.47
Over/Under Est: -16.12% -$1,358,280.26
Amt Left: 9.63% $620,699.05
Delta: -2.73% -$187,610.58
Over/Under Est: -15.85% -$1,335,259.35
Amt Left: 9.99% $643,719.96
Delta: -0.33% -$23,020.91
Over/Under Est: -15.63% -$1,316,425.55
Amt Left: 10.28% $662,553.76
Delta: -0.27% -$18,833.80
$7,519,559.00
Over/Under Est: -10.75% -$905,332.46
Amt Left: 16.66% $1,073,646.85
Delta: -5.78% -$411,093.09
Over/Under Est: -3.46% -$291,827.66
Amt Left: 26.17% $1,687,151.65
Delta: -8.16% -$613,504.80
Over/Under Est: 4.72% $397,993.19
Amt Left: 36.88% $2,376,972.50
Delta: -8.48% -$689,820.85
Over/Under Est: 7.74% $652,202.22
Amt Left: 40.82% $2,631,181.53
Delta: -2.88% -$254,209.03
Subcontractor Percentage Amount
SOUTH TEXAS TRAFFIC ALLIANCE INC. 3.16% $206,464.61
D. I. J. CONSTRUCTION, INC. 2.18% $142,434.44
AVILA AND SON'S L.L.C. 1.49% $97,351.98
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. 1.29% $84,284.60
EGGEMEYER LAND CLEARING, LLC 0.35% $22,867.92
PROFESSIONAL TRAFFIC CONTROL LLC 0.07% $4,573.58
Total: 8.54% $557,977.13

Bid Items & Bid Tabulations

63 Total 0 of 63
BASTROP  |  FM 696  |  AUSTIN  |  1073-01-021  |  10/08/2025  |  $8,424,891.46  |  C 1073-1-21  |  PREVENT MAINT  |  140 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
DEAN WORD COMPANY, LTD.
DAN WILLIAMS COMPANY
LARRY YOUNG PAVING, INC.
TEXAS MATERIALS GROUP, INC.
HUNTER INDUSTRIES, LTD.
CHASCO CONSTRUCTORS
BIG CREEK CONSTRUCTION, LTD.
JOE BLAND CONSTRUCTION LLC
AARON CONCRETE CONTRACTORS, LLC
PREPARING ROW
STA 112.000 $1,000.000 $1,150.000 $1,000.000 $240.000 $430.000 $1,010.100 $1,500.000 $500.000 $1,000.000 $449.000
REMOV CONC (MOWSTRIP)
SY 533.000 $20.000 $23.750 $16.000 $18.000 $20.000 $13.600 $16.000 $20.000 $20.000 $17.000
RMV (4") TRT/UNTRT BASE & ASPH PAV
SY 58,620.000 $5.250 $1.500 $2.550 $1.500 $2.160 $3.400 $3.500 $3.250 $1.600 $3.000
RMV (5") TRT/UNTRT BASE & ASPH PAV
SY 58,620.000 $5.110 $1.750 $5.500 $2.000 $2.630 $3.970 $4.750 $4.650 $1.800 $3.000
EXCAV (ROADWAY)
CY 11,848.000 $20.000 $16.000 $13.500 $16.000 $17.000 $18.200 $21.000 $19.000 $28.000 $64.000
EMBANK (FNL)(OC)(TY B)
CY 1,999.000 $25.000 $9.250 $30.000 $11.000 $14.000 $17.000 $21.000 $27.000 $20.000 $22.000
EMBANK (FNL)(OC)(TY C)
CY 751.000 $75.000 $22.500 $52.000 $23.000 $29.000 $36.000 $65.000 $40.000 $70.000 $90.000
BACKFILL (TY A)
STA 146.000 $250.000 $244.750 $220.000 $250.000 $146.000 $158.000 $690.000 $190.000 $1,175.000 $590.000
FURN & PLACE TOPSOIL (4")
SY 50,433.000 $2.750 $0.750 $1.200 $1.000 $1.930 $1.580 $1.500 $3.000 $3.000 $5.000
BROADCAST SEED (PERM_RURAL_CLAY)
SY 50,433.000 $0.300 $0.250 $0.250 $0.250 $0.140 $0.140 $0.200 $0.220 $0.250 $0.170
BROADCAST SEED (TEMP_WARM_COOL)
SY 50,433.000 $0.300 $0.250 $0.250 $0.250 $0.120 $0.120 $0.150 $0.220 $0.200 $0.150
VEGETATIVE WATERING
TGL 847.000 $40.000 $0.500 $5.000 $41.000 $39.000 $23.800 $25.000 $25.000 $50.000 $74.000
SOIL RET BLKT(SL_MOD_CLAY_SHORT)
SY 50,433.000 $1.850 $0.750 $1.000 $0.750 $0.590 $0.590 $0.600 $1.250 $1.000 $1.000
FL BS (CMP IN PLC)(TY D GR 5)(FNAL POS)
CY 13,976.000 $68.500 $63.000 $54.000 $71.000 $69.900 $69.280 $63.000 $66.000 $105.000 $87.000
GEOGRID BASE REINFORCEMENT (TYPE 1)
SY 66,162.000 $2.250 $1.250 $1.120 $1.500 $0.620 $1.230 $1.700 $1.500 $4.000 $3.000
REWORK BS MTL (TY B)(8")(ORD COMP)
SY 59,315.000 $5.500 $4.750 $4.250 $6.000 $10.900 $5.100 $9.000 $10.000 $9.000 $9.000
PRIME COAT (AE-P)
GAL 11,763.000 $5.500 $3.500 $5.000 $6.500 $5.000 $4.660 $5.500 $4.500 $4.000 $6.000
D-GR HMA TY-B PG64-22
TON 12,410.000 $96.700 $80.250 $82.000 $80.000 $79.000 $91.100 $82.000 $106.000 $97.000 $91.000
D-GR HMA TY-D PG76-22
TON 4,584.000 $140.000 $94.500 $105.000 $120.000 $102.000 $101.100 $107.000 $115.000 $129.000 $117.000
D-GR HMA TY-D PG76-22 (LEVEL-UP)
TON 392.000 $190.000 $115.500 $123.000 $130.000 $121.000 $103.400 $127.000 $125.000 $126.000 $144.000
TOM-C PG76-22 SAC-B
TON 7,722.000 $150.000 $130.000 $125.000 $120.000 $122.000 $124.200 $128.000 $132.000 $148.000 $142.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(5")
SY 5,000.000 $65.000 $35.750 $36.000 $31.000 $39.000 $38.640 $46.000 $40.000 $47.000 $44.000
PLANE & TEXT ASPH CONC PAV(0" TO 2")
SY 10,222.000 $3.500 $2.250 $1.550 $1.500 $1.600 $2.100 $1.600 $3.000 $3.000 $1.000
RIPRAP (MOW STRIP)(4 IN)
CY 72.000 $700.000 $741.500 $525.000 $650.000 $680.000 $715.000 $700.000 $660.000 $765.000 $958.000
MOBILIZATION
LS 1.000 $773,500.000 $435,000.000 $665,000.000 $650,000.000 $600,000.000 $654,652.810 $473,000.000 $800,000.000 $150,000.000 $546,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 9.000 $5,000.000 $13,065.250 $13,500.000 $14,250.000 $6,450.000 $10,056.540 $3,500.000 $10,000.000 $16,250.000 $1,439.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $8,750.000 $11,221.250 $10,000.000 $1,200.000 $8,250.000 $3,576.900 $7,622.000 $12,000.000 $23,825.000 $19,983.000
TMA (STATIONARY)
DAY 122.000 $281.000 $50.000 $200.000 $250.000 $200.000 $127.750 $260.000 $230.000 $215.000 $356.000
TMA (MOBILE OPERATION)
DAY 122.000 $300.000 $1.000 $0.010 $690.000 $25.000 $281.040 $400.000 $95.000 $985.000 $1,018.000
ROCK FILTER DAMS (INSTALL) (TY 1)
LF 415.000 $39.400 $31.250 $39.000 $38.000 $30.000 $29.570 $35.000 $25.000 $40.000 $36.000
ROCK FILTER DAMS (REMOVE)
LF 415.000 $16.200 $13.250 $15.000 $16.000 $12.500 $12.480 $13.000 $5.000 $30.000 $15.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 3,385.000 $4.500 $4.250 $5.000 $5.000 $3.900 $3.900 $5.000 $3.500 $5.000 $5.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 3,385.000 $1.250 $1.000 $1.250 $1.000 $0.820 $0.820 $0.750 $1.000 $1.000 $1.000
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 1,290.000 $4.000 $5.250 $6.000 $6.250 $4.950 $4.950 $6.000 $6.500 $8.000 $6.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 1,290.000 $2.000 $1.250 $1.500 $1.250 $1.030 $1.030 $1.000 $1.000 $2.000 $1.000
CONSTRUCTING DETOURS (TY2)
SY 4,941.000 $75.000 $103.000 $94.000 $93.000 $98.000 $85.490 $105.000 $110.000 $124.000 $115.000
PTB (FUR&INST)(F SHAPE)(TY 1) OR (STL)
LF 2,640.000 $22.700 $58.000 $35.000 $86.000 $30.000 $42.000 $60.000 $50.000 $100.000 $27.000
PTB (MOVE)(F SHAPE)(TY 1) OR (STL)
LF 7,920.000 $9.250 $1.750 $12.500 $14.000 $30.000 $16.000 $14.000 $12.000 $25.000 $43.000
PTB (REMOVE)(F SHAPE)(TY 1) OR (STL)
LF 2,640.000 $15.400 $52.750 $20.000 $23.000 $14.500 $15.000 $25.000 $15.000 $25.000 $10.000
MILL RUMBLE STRIPS (ASPH) (CENTERLINE)
LF 11,318.000 $2.500 $0.250 $0.550 $0.400 $0.750 $0.880 $0.600 $0.600 $1.000 $1.000
MTL W-BEAM GD FEN (TIM POST)
LF 800.000 $27.500 $26.000 $22.500 $27.000 $24.500 $28.300 $30.000 $31.000 $30.000 $30.000
REMOVE METAL BEAM GUARD FENCE
LF 1,000.000 $1.750 $2.500 $6.000 $6.250 $3.000 $3.000 $5.000 $4.500 $5.000 $4.000
GUARDRAIL END TREATMENT (INSTALL)
EA 8.000 $3,253.000 $3,631.000 $4,000.000 $3,700.000 $2,935.000 $3,405.000 $4,000.000 $3,400.000 $3,625.000 $3,995.000
GUARDRAIL END TREATMENT (REMOVE)
EA 8.000 $595.560 $238.500 $300.000 $350.000 $275.000 $275.000 $350.000 $450.000 $300.000 $333.000
CRASH CUSH ATTEN (MOVE & RESET)
EA 6.000 $2,750.940 $821.250 $10,000.000 $1,600.000 $1,200.000 $1,100.000 $2,500.000 $1,950.000 $1,000.000 $1,150.000
CRASH CUSH ATTEN (REMOVE)
EA 2.000 $1,662.020 $582.500 $5,000.000 $950.000 $620.000 $975.000 $600.000 $1,050.000 $550.000 $605.000
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
EA 2.000 $10,500.000 $1,810.250 $15,000.000 $7,700.000 $8,400.000 $7,985.000 $9,000.000 $8,900.000 $7,875.000 $8,715.000
RELOCATE EXISTING MAILBOX
EA 1.000 $426.130 $270.250 $500.000 $350.000 $295.000 $424.760 $350.000 $550.000 $1,000.000 $393.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 7.000 $752.810 $736.750 $800.000 $950.000 $820.000 $1,157.680 $925.000 $850.000 $900.000 $1,092.000
REMOVE SM RD SN SUP&AM
EA 9.000 $139.070 $116.500 $125.000 $180.000 $150.000 $183.230 $170.000 $140.000 $165.000 $200.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 12.000 $38.000 $47.750 $55.000 $57.000 $46.500 $74.960 $55.000 $40.000 $50.000 $62.000
WK ZN PAV MRK NON-REMOV (W)6"(SLD)
LF 94,948.000 $1.000 $0.250 $0.200 $0.250 $0.200 $0.250 $0.250 $0.280 $0.250 $0.300
WK ZN PAV MRK NON-REMOV (Y)6"(BRK)
LF 1,952.000 $1.000 $0.300 $0.280 $0.250 $0.280 $0.250 $0.300 $0.280 $0.500 $0.300
WK ZN PAV MRK NON-REMOV (Y)6"(SLD)
LF 87,141.000 $1.000 $0.300 $0.280 $0.250 $0.280 $0.250 $0.300 $0.280 $0.300 $0.300
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 1,457.000 $1.620 $2.000 $2.000 $1.000 $1.610 $1.500 $2.200 $2.000 $1.000 $3.000
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 96.000 $13.070 $21.250 $20.000 $25.000 $20.000 $7.000 $21.000 $13.000 $22.000 $8.000
REFL PAV MRK TY I (W)(RR XING)(100MIL)
EA 2.000 $585.470 $816.250 $770.000 $980.000 $770.000 $610.000 $800.000 $825.000 $850.000 $738.000
RE PROFILE PM TY I(W)6"(SLD)(100MIL)
LF 50,804.000 $1.000 $1.000 $0.820 $1.000 $0.820 $0.920 $0.900 $1.050 $1.000 $1.000
RE PROFILE PM TY I(Y)6"(SLD)(100MIL)
LF 42,997.000 $1.300 $1.000 $0.820 $1.000 $0.820 $0.950 $0.900 $1.050 $1.000 $1.000
RE PROFILE PM TY I(Y)6"(BRK)(100MIL)
LF 1,952.000 $1.020 $1.000 $0.850 $1.000 $0.850 $0.950 $0.900 $1.050 $1.000 $1.000
REFL PAV MRKR TY II-A-A
EA 638.000 $7.160 $6.500 $6.100 $7.750 $6.100 $4.300 $6.500 $5.500 $7.000 $5.000
ELIM EXT PM & MRKS (6")
LF 63,202.000 $0.800 $0.250 $0.200 $0.250 $0.200 $0.340 $0.250 $0.550 $0.250 $0.410
BONDING COURSE
GAL 11,960.000 $4.250 $3.750 $4.900 $6.250 $5.500 $3.310 $5.000 $4.000 $4.000 $6.000
Totals: $8,424,891.460 $6,445,912.150 $6,879,000.620 $7,066,611.200 $7,089,632.110 $7,108,465.910 $7,519,559.000 $8,133,063.800 $8,822,884.650 $9,077,093.680
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
RAILROAD FLAGGING: RAILROAD FORCE ACCOUNT WORK (NON-PART) $3,000.00
LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) $3,000.00
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) $3,000.00
ENVIRONMENTAL: CONTRACTOR FORCE ACCOUNT WORK (NONPART) $3,000.00
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) $5,000.00
Total: $17,000.00