BASTROP CR (0914-18-110)
Items: 40
County: BASTROP
Length: N/A
Highway: CR
District: AUSTIN
Control Number: 0914-18-110
DBE Goal: N/A
Project: BR 2018(884)
Guaranty: N/A
Time: 77 WORKING DAYS
Engineer's Estimate: $413,678.53
Date: 11/06/2018 (7 years ago)
Contract Number: N/A
Type: REPLACE BRIDGE AND APPROACHES
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Bidders (12)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$413,678.53 | |||
| $399,604.26 |
-3.4%
-$14,074.27
|
|||
| $449,720.95 |
8.71%
$36,042.42
|
12.54%
$50,116.69
|
||
| $460,537.41 |
11.33%
$46,858.88
|
15.25%
$60,933.15
|
-2.41%
-$10,816.46
|
|
| $469,396.25 |
13.47%
$55,717.72
|
17.47%
$69,791.99
|
-1.92%
-$8,858.84
|
|
| $469,524.55 |
13.5%
$55,846.02
|
17.5%
$69,920.29
|
-0.03%
-$128.30
|
|
| $475,960.00 |
15.06%
$62,281.47
|
19.11%
$76,355.74
|
-1.37%
-$6,435.45
|
|
| $480,384.46 |
16.13%
$66,705.93
|
20.22%
$80,780.20
|
-0.93%
-$4,424.46
|
|
| $493,674.30 |
19.34%
$79,995.77
|
23.54%
$94,070.04
|
-2.77%
-$13,289.84
|
|
| $516,806.53 |
24.93%
$103,128.00
|
29.33%
$117,202.27
|
-4.69%
-$23,132.23
|
|
| $529,565.50 |
28.01%
$115,886.97
|
32.52%
$129,961.24
|
-2.47%
-$12,758.97
|
|
| $554,210.70 |
33.97%
$140,532.17
|
38.69%
$154,606.44
|
-4.65%
-$24,645.20
|
|
| $571,400.00 |
38.13%
$157,721.47
|
42.99%
$171,795.74
|
-3.10%
-$17,189.30
|
E
Engineer's Estimate
$413,678.53
1
Awarded
$399,604.26
Over/Under Est:
-3.4%
-$14,074.27
$449,720.95
Over/Under Est:
8.71%
$36,042.42
Amt Left:
12.54%
$50,116.69
$460,537.41
Over/Under Est:
11.33%
$46,858.88
Amt Left:
15.25%
$60,933.15
Delta:
-2.41%
-$10,816.46
$469,396.25
Over/Under Est:
13.47%
$55,717.72
Amt Left:
17.47%
$69,791.99
Delta:
-1.92%
-$8,858.84
$469,524.55
Over/Under Est:
13.5%
$55,846.02
Amt Left:
17.5%
$69,920.29
Delta:
-0.03%
-$128.30
$475,960.00
Over/Under Est:
15.06%
$62,281.47
Amt Left:
19.11%
$76,355.74
Delta:
-1.37%
-$6,435.45
$480,384.46
Over/Under Est:
16.13%
$66,705.93
Amt Left:
20.22%
$80,780.20
Delta:
-0.93%
-$4,424.46
$493,674.30
Over/Under Est:
19.34%
$79,995.77
Amt Left:
23.54%
$94,070.04
Delta:
-2.77%
-$13,289.84
$516,806.53
Over/Under Est:
24.93%
$103,128.00
Amt Left:
29.33%
$117,202.27
Delta:
-4.69%
-$23,132.23
$529,565.50
Over/Under Est:
28.01%
$115,886.97
Amt Left:
32.52%
$129,961.24
Delta:
-2.47%
-$12,758.97
$554,210.70
Over/Under Est:
33.97%
$140,532.17
Amt Left:
38.69%
$154,606.44
Delta:
-4.65%
-$24,645.20
$571,400.00
Over/Under Est:
38.13%
$157,721.47
Amt Left:
42.99%
$171,795.74
Delta:
-3.10%
-$17,189.30
Bid Items & Bid Tabulations
40
Total
0 of 40