Show Job Controls
Bid Cobra

BASTROP SH 71 (0265-03-048)

Items: 24

County: BASTROP
Length: N/A
Highway: SH 71
District: AUSTIN
Control Number: 0265-03-048
DBE Goal: N/A
Project: STP 2017(548)HES
Guaranty: N/A
Time: 32 WORKING DAYS
Engineer's Estimate: $307,374.50
Date: 01/05/2017 (9 years ago)
Contract Number: N/A
Type: LENGTHEN LEFT TURN LANE
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (6)
E
Engineer's Estimate
$307,374.50
Over/Under Est: -6.78% -$20,849.20
Over/Under Est: 5.29% $16,246.20
Amt Left: 12.95% $37,095.40
Over/Under Est: 5.33% $16,392.08
Amt Left: 13% $37,241.28
Delta: -0.05% -$145.88
Over/Under Est: 10.6% $32,589.80
Amt Left: 18.65% $53,439.00
Delta: -5.00% -$16,197.72
Over/Under Est: 11.25% $34,587.28
Amt Left: 19.35% $55,436.48
Delta: -0.59% -$1,997.48
Over/Under Est: 21% $64,554.76
Amt Left: 29.81% $85,403.96
Delta: -8.76% -$29,967.48

Bid Items & Bid Tabulations

24 Total 0 of 24
BASTROP  |  SH 71  |  AUSTIN  |  0265-03-048  |  01/05/2017  |  $307,374.50  |  STP 2017(548)HES  |  LENGTHEN LEFT TURN LANE  |  32 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
AARON CONCRETE CONTRACTORS, L.P.
ANGEL BROTHERS HOLDINGS CORP.
ACME BRIDGE COMPANY, INC.
AUSTIN MATERIALS, LLC
DEAN WORD COMPANY, LTD.
HUNTER INDUSTRIES, LTD.
PREPARING ROW
STA 22.000 $1,500.000 $1,000.000 $200.000 $1,000.000 $500.000 $1,789.480 $1,143.960
EXCAVATION (ROADWAY)
CY 430.000 $20.000 $27.000 $20.000 $25.000 $30.000 $35.364 $43.650
SUBGRADE WIDENING (ORD COMP)
STA 22.000 $1,000.000 $800.000 $1,000.000 $350.000 $500.000 $1,452.773 $1,995.000
FURNISHING AND PLACING TOPSOIL (4")
SY 7,360.000 $2.500 $1.000 $1.200 $2.100 $6.000 $3.064 $2.440
CELL FBR MLCH SEED(PERM)(RURAL)(CLAY)
SY 7,360.000 $0.700 $0.300 $0.290 $0.350 $0.520 $0.258 $0.250
VEGETATIVE WATERING
MG 147.500 $40.000 $34.000 $50.000 $53.600 $155.000 $33.325 $36.640
SOIL RETENTION BLANKETS (CL 1) (TY A)
SY 7,360.000 $1.200 $1.300 $1.300 $1.600 $1.250 $1.185 $1.150
FL BS (CMP IN PLC)(TY A GR 5)(FNAL POS)
CY 991.000 $60.000 $73.000 $96.000 $75.000 $56.000 $71.332 $72.070
PRIME COAT (AE-P)
GAL 740.000 $5.500 $3.500 $8.500 $4.550 $3.500 $10.266 $8.760
D-GR HMA(SQ) TY-B PG64-22
TON 572.000 $100.000 $89.000 $90.000 $116.000 $78.500 $71.627 $114.600
D-GR HMA(SQ) TY-D SAC-B PG70-22
TON 379.000 $110.000 $120.000 $130.000 $118.000 $87.900 $84.753 $121.950
MOBILIZATION
LS 1.000 $27,500.000 $22,000.000 $32,000.000 $27,200.000 $33,990.000 $36,677.142 $41,803.920
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 2.000 $3,000.000 $1,100.000 $5,000.000 $2,000.000 $19,645.000 $5,233.988 $2,413.700
TEMP SEDMT CONT FENCE (INSTALL)
LF 100.000 $5.000 $5.600 $8.000 $7.000 $12.000 $5.150 $5.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 100.000 $2.500 $2.800 $1.000 $3.500 $8.000 $2.575 $2.500
RELOCATE SM RD SN SUP&AM TY 10BWG
EA 2.000 $350.000 $550.000 $570.000 $700.000 $490.000 $504.700 $490.000
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 200.000 $1.200 $1.100 $1.200 $2.500 $1.810 $1.913 $1.550
REFL PAV MRK TY I (W)8"(DOT)(100MIL)
LF 76.000 $1.000 $2.100 $1.900 $2.100 $1.900 $1.545 $1.900
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 2,106.000 $0.750 $1.600 $1.450 $1.100 $1.450 $0.793 $1.450
REFL PAV MRK TY I (W)(ARROW)(100MIL)
EA 4.000 $200.000 $250.000 $225.000 $210.000 $225.000 $154.500 $225.000
REFL PAV MRK TY I (W)(WORD)(100MIL)
EA 4.000 $150.000 $250.000 $225.000 $210.000 $225.000 $154.500 $225.000
REF PROF PAV MRK TY I(Y)4"(SLD)(100MIL)
LF 2,406.000 $1.000 $2.200 $1.970 $7.000 $1.970 $5.150 $1.970
REFL PAV MRKR TY II-C-R
EA 123.000 $5.000 $5.500 $4.900 $6.100 $4.900 $4.460 $4.900
ELIM EXT PAV MRK & MRKS (4")
LF 1,804.000 $1.000 $1.100 $2.170 $0.520 $0.970 $0.381 $0.970
Totals: $307,374.500 $286,525.300 $323,620.700 $323,766.580 $339,964.300 $341,961.826 $371,929.260