AUSTIN FM 1456 (1410-01-026)
Items: 59
County: AUSTIN
Length: 2.1490 MILES
Highway: FM 1456
District: YOAKUM
Control Number: 1410-01-026
DBE Goal: 0.0%
Project: STP 2026(573)HES
Guaranty: $55,000.00
Time: 135 WORKING DAYS
Engineer's Estimate: $2,755,373.81
Date: 05/06/2026 (5 weeks ago)
Contract Number: 5263021
Type: HAZARD ELIMINATION & SAFETY
Project ID: A00193380
Contract Type: Federal
Project Description: PROVIDE ADDITIONAL PAVED SURFACES - HSIP 2022
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
RYAN SIMPER
JEFFREY KALINA
AUSTIN FM 1456 (1410-01-026)
Project Name: N/A
Project: STP 2026(573)HES
Length: 2.0000 MILES
Project Type: CONSTRUCTION
Limits From: 2 MI WEST OF SH 159
Limits To: SH 159
Project Description: PROVIDE ADDITIONAL PAVED SURFACES - HSIP 2022
Bidders (8)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$2,755,373.81 | |||
| $2,587,895.46 |
-6.08%
-$167,478.35
|
|||
| $2,697,120.28 |
-2.11%
-$58,253.53
|
4.22%
$109,224.82
|
||
| $2,718,147.15 |
-1.35%
-$37,226.66
|
5.03%
$130,251.69
|
-0.78%
-$21,026.87
|
|
| $2,862,555.21 |
3.89%
$107,181.40
|
10.61%
$274,659.75
|
-5.31%
-$144,408.06
|
|
| $2,971,970.66 |
7.86%
$216,596.85
|
14.84%
$384,075.20
|
-3.82%
-$109,415.45
|
|
| $3,126,637.62 |
13.47%
$371,263.81
|
20.82%
$538,742.16
|
-5.20%
-$154,666.96
|
|
| $3,261,136.77 |
18.36%
$505,762.96
|
26.02%
$673,241.31
|
-4.30%
-$134,499.15
|
|
| $3,659,349.50 |
32.81%
$903,975.69
|
41.4%
$1,071,454.04
|
-12.21%
-$398,212.73
|
E
Engineer's Estimate
$2,755,373.81
1
Awarded
$2,587,895.46
Over/Under Est:
-6.08%
-$167,478.35
$2,697,120.28
Over/Under Est:
-2.11%
-$58,253.53
Amt Left:
4.22%
$109,224.82
$2,718,147.15
Over/Under Est:
-1.35%
-$37,226.66
Amt Left:
5.03%
$130,251.69
Delta:
-0.78%
-$21,026.87
$2,862,555.21
Over/Under Est:
3.89%
$107,181.40
Amt Left:
10.61%
$274,659.75
Delta:
-5.31%
-$144,408.06
$2,971,970.66
Over/Under Est:
7.86%
$216,596.85
Amt Left:
14.84%
$384,075.20
Delta:
-3.82%
-$109,415.45
$3,126,637.62
Over/Under Est:
13.47%
$371,263.81
Amt Left:
20.82%
$538,742.16
Delta:
-5.20%
-$154,666.96
$3,261,136.77
Over/Under Est:
18.36%
$505,762.96
Amt Left:
26.02%
$673,241.31
Delta:
-4.30%
-$134,499.15
$3,659,349.50
Over/Under Est:
32.81%
$903,975.69
Amt Left:
41.4%
$1,071,454.04
Delta:
-12.21%
-$398,212.73
Bid Items & Bid Tabulations
59
Total
0 of 59
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
| Description | Amount |
|---|---|
| EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) | $500.00 |
| SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) | $1,000.00 |
| Total: | $1,500.00 |