PREPARING ROW
|
STA
|
405.000
|
$611.850
|
$479.700
|
$200.000
|
$134.870
|
|
|
|
EXCAVATION (ROADWAY)
|
CY
|
78,889.000
|
$12.000
|
$13.680
|
$14.200
|
$14.310
|
|
|
|
EMBANKMENT (FINAL)(ORD COMP)(TY B)
|
CY
|
3,935.000
|
$24.000
|
$14.940
|
$9.800
|
$13.880
|
|
|
|
FURNISHING AND PLACING TOPSOIL (4")
|
SY
|
249,924.000
|
$1.100
|
$1.140
|
$1.300
|
$1.500
|
|
|
|
BROADCAST SEED (PERM) (RURAL) (CLAY)
|
SY
|
249,924.000
|
$0.200
|
$0.180
|
$0.170
|
$0.220
|
|
|
|
BROADCAST SEED (TEMP) (WARM)
|
SY
|
124,962.000
|
$0.160
|
$0.140
|
$0.150
|
$0.170
|
|
|
|
BROADCAST SEED (TEMP) (COOL)
|
SY
|
124,962.000
|
$0.120
|
$0.140
|
$0.150
|
$0.170
|
|
|
|
VEGETATIVE WATERING
|
MG
|
3,899.000
|
$22.660
|
$17.100
|
$24.000
|
$41.210
|
|
|
|
PROOF ROLLING
|
HR
|
84.000
|
$75.000
|
$128.700
|
$140.000
|
$102.620
|
|
|
|
FL BS (CMP IN PLC)(TYD GR1-2)(FNAL POS)
|
CY
|
18,446.000
|
$55.000
|
$58.420
|
$87.000
|
$87.090
|
|
|
|
REWORK BS MATL (TY B) (5") (ORD COMP)
|
SY
|
31,065.000
|
$4.000
|
$2.340
|
$1.250
|
$2.770
|
|
|
|
FOG SEAL (CSS-1H)
|
GAL
|
8,936.000
|
$4.000
|
$3.940
|
$8.000
|
$3.960
|
|
|
|
ASPH (AC-15P, AC-20-5TR OR AC-20XP)
|
GAL
|
38,294.000
|
$5.290
|
$5.040
|
$4.550
|
$5.090
|
|
|
|
AGGR (TY-PB GR-4)
|
CY
|
1,161.000
|
$97.400
|
$115.330
|
$159.000
|
$147.210
|
|
|
|
STRUCT EXCAV (BOX)
|
CY
|
195.000
|
$20.000
|
$10.490
|
$10.200
|
$34.650
|
|
|
|
STRUCT EXCAV (PIPE)
|
CY
|
99.000
|
$5.000
|
$10.490
|
$10.200
|
$54.710
|
|
|
|
CUT & RESTORING PAV
|
SY
|
108.000
|
$111.520
|
$252.760
|
$320.000
|
$162.440
|
|
|
|
TRENCH EXCAVATION PROTECTION
|
LF
|
199.000
|
$3.350
|
$10.490
|
$10.200
|
$12.800
|
|
|
|
TEMPORARY SPL SHORING
|
SF
|
1,048.000
|
$26.210
|
$20.990
|
$21.000
|
$68.600
|
|
|
|
RIPRAP (CONC)(4 IN)
|
CY
|
2.000
|
$511.170
|
$945.030
|
$920.000
|
$1,390.880
|
|
|
|
CMP (GAL STL 18 IN)
|
LF
|
215.000
|
$80.000
|
$87.890
|
$85.500
|
$95.370
|
|
|
|
CMP (GAL STL 24 IN)
|
LF
|
239.000
|
$300.000
|
$122.750
|
$120.000
|
$91.440
|
|
|
|
CONC BOX CULV (8 FT X 3 FT)
|
LF
|
56.000
|
$846.240
|
$1,576.640
|
$1,430.000
|
$1,200.100
|
|
|
|
RC PIPE (CL III)(24 IN)
|
LF
|
143.000
|
$135.510
|
$304.250
|
$68.500
|
$138.820
|
|
|
|
HEADWALL (CH - PW - 0) (DIA= 24 IN)
|
EA
|
1.000
|
$8,667.000
|
$8,389.750
|
$8,100.000
|
$11,973.610
|
|
|
|
WINGWALL (PW - 1) (HW=8 FT)
|
EA
|
2.000
|
$30,973.000
|
$18,890.060
|
$25,600.000
|
$22,304.360
|
|
|
|
SET (TY II) (18 IN) (CMP) (6: 1) (P)
|
EA
|
8.000
|
$1,124.000
|
$1,574.000
|
$1,530.000
|
$1,289.320
|
|
|
|
SET (TY II) (24 IN) (CMP) (6: 1) (P)
|
EA
|
10.000
|
$2,637.000
|
$1,679.000
|
$1,630.000
|
$1,639.320
|
|
|
|
SET (TY II) (24 IN) (RCP) (4: 1) (C)
|
EA
|
1.000
|
$2,000.000
|
$1,731.500
|
$1,685.000
|
$1,458.070
|
|
|
|
SET (TY II) (24 IN) (RCP) (6: 1) (P)
|
EA
|
2.000
|
$2,650.000
|
$2,099.010
|
$2,040.000
|
$1,639.320
|
|
|
|
CLEAN EXIST CULVERTS
|
EA
|
20.000
|
$3,682.000
|
$1,049.390
|
$2,550.000
|
$2,732.880
|
|
|
|
REMOV STR (SET)
|
EA
|
16.000
|
$400.000
|
$838.970
|
$816.000
|
$464.880
|
|
|
|
REMOV STR (PIPE)
|
LF
|
517.000
|
$25.090
|
$22.040
|
$21.400
|
$17.980
|
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$1,074,115.890
|
$1,201,336.000
|
$890,000.000
|
$908,000.000
|
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
18.000
|
$10,000.000
|
$3,652.690
|
$5,500.000
|
$1,750.310
|
|
|
|
ROCK FILTER DAMS (INSTALL) (TY 2)
|
LF
|
1,965.000
|
$35.000
|
$41.600
|
$40.500
|
$35.780
|
|
|
|
ROCK FILTER DAMS (INSTALL) (TY 3)
|
LF
|
811.000
|
$71.780
|
$82.000
|
$122.000
|
$90.760
|
|
|
|
ROCK FILTER DAMS (REMOVE)
|
LF
|
2,776.000
|
$7.750
|
$10.000
|
$11.700
|
$11.410
|
|
|
|
CONSTRUCTION EXITS (INSTALL) (TY 1)
|
SY
|
780.000
|
$19.830
|
$23.000
|
$22.150
|
$26.760
|
|
|
|
CONSTRUCTION EXITS (REMOVE)
|
SY
|
780.000
|
$6.550
|
$2.000
|
$6.400
|
$2.930
|
|
|
|
TEMP SEDMT CONT FENCE (INSTALL)
|
LF
|
27,225.000
|
$3.610
|
$2.350
|
$3.600
|
$2.630
|
|
|
|
TEMP SEDMT CONT FENCE (REMOVE)
|
LF
|
27,225.000
|
$0.590
|
$0.750
|
$0.500
|
$0.870
|
|
|
|
CONSTRUCTING DETOURS
|
SY
|
3,079.000
|
$66.460
|
$40.500
|
$65.000
|
$117.940
|
|
|
|
ONE-WAY TRAF CONT (PILOT CAR)
|
HR
|
408.000
|
$128.700
|
$128.700
|
$144.000
|
$121.580
|
|
|
|
ONE-WAY TRAF CONT (PORT TRAF SIG)
|
MO
|
34.000
|
$4,800.000
|
$5,675.080
|
$4,300.000
|
$5,752.100
|
|
|
|
PORT CTB (FUR & INST)(LOW PROF)(TY 1)
|
LF
|
1,940.000
|
$43.230
|
$49.570
|
$73.000
|
$24.210
|
|
|
|
PORT CTB (FUR & INST)(LOW PROF)(TY 2)
|
LF
|
200.000
|
$39.860
|
$45.810
|
$68.000
|
$32.690
|
|
|
|
PORT CTB (MOVE)(LOW PROF)(TY 1)
|
LF
|
3,800.000
|
$5.060
|
$23.910
|
$17.500
|
$8.110
|
|
|
|
PORT CTB (MOVE)(LOW PROF)(TY 2)
|
LF
|
240.000
|
$8.010
|
$23.440
|
$17.500
|
$10.630
|
|
|
|
PORT CTB (REMOVE)(LOW PROF)(TY 1)
|
LF
|
1,940.000
|
$4.580
|
$31.280
|
$24.000
|
$11.710
|
|
|
|
PORT CTB (REMOVE)(LOW PROF)(TY 2)
|
LF
|
200.000
|
$5.720
|
$15.570
|
$24.000
|
$20.190
|
|
|
|
DRIVEWAYS AND TURNOUTS (SURF TREAT)
|
SY
|
3,505.000
|
$55.860
|
$40.500
|
$21.000
|
$32.220
|
|
|
|
RUMBLE STRIPS (SHOULDER) ASPHALT
|
LF
|
78,556.000
|
$0.180
|
$0.180
|
$0.170
|
$0.190
|
|
|
|
RUMBLE STRIPS (CENTERLINE) ASPHALT
|
LF
|
39,484.000
|
$0.190
|
$0.180
|
$0.170
|
$0.220
|
|
|
|
MTL W-BEAM GD FEN (TIM POST)
|
LF
|
465.000
|
$29.200
|
$26.500
|
$30.650
|
$32.360
|
|
|
|
DOWNSTREAM ANCHOR TERMINAL SECTION
|
EA
|
2.000
|
$1,552.370
|
$1,350.000
|
$1,835.000
|
$1,662.950
|
|
|
|
REMOVE METAL BEAM GUARD FENCE
|
LF
|
500.000
|
$4.500
|
$2.000
|
$2.550
|
$4.610
|
|
|
|
REMOVE DOWNSTREAM ANCHOR TERMINAL
|
EA
|
4.000
|
$212.000
|
$200.000
|
$229.000
|
$220.980
|
|
|
|
GUARDRAIL END TREATMENT (INSTALL)
|
EA
|
2.000
|
$3,271.000
|
$3,000.000
|
$3,720.000
|
$3,978.450
|
|
|
|
MAILBOX INSTALL-S (TWG-POST) TY 1
|
EA
|
1.000
|
$267.260
|
$275.000
|
$280.000
|
$313.890
|
|
|
|
MAILBOX INSTALL-D (TWG-POST) TY 1
|
EA
|
2.000
|
$280.000
|
$305.000
|
$311.000
|
$346.890
|
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
|
EA
|
24.000
|
$561.960
|
$568.000
|
$580.000
|
$636.190
|
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
|
EA
|
27.000
|
$667.130
|
$697.000
|
$712.000
|
$778.090
|
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(T-2EXT)
|
EA
|
2.000
|
$960.820
|
$779.000
|
$795.000
|
$868.290
|
|
|
|
IN SM RD SN SUP&AM TYFRP(1)UA(P)
|
EA
|
6.000
|
$700.000
|
$625.000
|
$638.000
|
$698.890
|
|
|
|
IN SM RD SN SUP&AM TYS80(1)SA(P)
|
EA
|
2.000
|
$750.000
|
$765.000
|
$780.000
|
$852.890
|
|
|
|
IN SM RD SN SUP&AM TYS80(1)SA(T)
|
EA
|
9.000
|
$885.010
|
$905.000
|
$924.000
|
$1,006.890
|
|
|
|
IN SM RD SN SUP&AM TYS80(1)SA(U)
|
EA
|
6.000
|
$1,077.000
|
$1,065.000
|
$1,085.000
|
$1,182.890
|
|
|
|
IN SM RD SN SUP&AM TYS80(1)SA(U-1EXT)
|
EA
|
4.000
|
$1,187.100
|
$1,215.000
|
$1,240.000
|
$1,347.890
|
|
|
|
IN SM RD SN SUP&AM TYS80(1)SA(U-WC)
|
EA
|
4.000
|
$1,289.490
|
$1,422.000
|
$1,450.000
|
$1,575.590
|
|
|
|
IN SM RD SN SUP&AM TYS80(2)SA(P-EXAL)
|
EA
|
1.000
|
$1,830.950
|
$1,894.000
|
$1,935.000
|
$2,094.790
|
|
|
|
IN BRIDGE MNT CLEARANCE SGN ASSM(TY S)
|
EA
|
2.000
|
$2,400.000
|
$2,591.480
|
$2,520.000
|
$2,828.710
|
|
|
|
REMOVE SM RD SN SUP&AM
|
EA
|
81.000
|
$128.420
|
$118.000
|
$120.000
|
$141.050
|
|
|
|
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
|
EA
|
8.000
|
$32.000
|
$30.000
|
$31.000
|
$44.390
|
|
|
|
INSTL DEL ASSM (D-SY)SZ 1(YFLX)GND(BR)
|
EA
|
6.000
|
$116.000
|
$92.000
|
$94.000
|
$112.590
|
|
|
|
INSTL OM ASSM (OM-2Z)(WFLX)GND(BI)
|
EA
|
50.000
|
$180.750
|
$92.000
|
$94.000
|
$112.590
|
|
|
|
INSTL OM ASSM (OM-3L)(WFLX)GND)GND
|
EA
|
1.000
|
$450.000
|
$402.000
|
$410.000
|
$453.590
|
|
|
|
INSTL OM ASSM (OM-3R)(WFLX)GND)GND
|
EA
|
1.000
|
$450.000
|
$402.000
|
$410.000
|
$453.590
|
|
|
|
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
|
LF
|
127,535.000
|
$0.420
|
$0.450
|
$0.390
|
$0.430
|
|
|
|
WK ZN PAV MRK NON-REMOV (W)24"(SLD)
|
LF
|
152.000
|
$4.000
|
$12.000
|
$6.130
|
$7.350
|
|
|
|
WK ZN PAV MRK NON-REMOV (Y)4"(BRK)
|
LF
|
860.000
|
$0.350
|
$0.450
|
$0.440
|
$0.610
|
|
|
|
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
|
LF
|
80,068.000
|
$0.410
|
$0.450
|
$0.390
|
$0.430
|
|
|
|
WK ZN PAV MRK REMOV (REFL) TY II-A-A
|
EA
|
940.000
|
$4.530
|
$2.500
|
$5.100
|
$5.740
|
|
|
|
WK ZN PAV MRK REMOV (TRAF BTN) TY W
|
LF
|
6,800.000
|
$1.170
|
$1.250
|
$0.510
|
$0.720
|
|
|
|
WK ZN PAV MRK REMOV (W)24"(SLD)
|
LF
|
672.000
|
$7.400
|
$6.000
|
$7.150
|
$7.870
|
|
|
|
WK ZN PAV MRK REMOV (Y)4"(BRK)
|
LF
|
500.000
|
$0.880
|
$0.450
|
$0.510
|
$0.780
|
|
|
|
WK ZN PAV MRK REMOV (Y)4"(SLD)
|
LF
|
41,885.000
|
$0.640
|
$0.450
|
$0.510
|
$0.560
|
|
|
|
WK ZN PAV MRK SHT TERM (TAB)TY W
|
EA
|
6,047.000
|
$2.000
|
$1.660
|
$1.100
|
$1.240
|
|
|
|
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
|
EA
|
8,042.000
|
$1.430
|
$1.660
|
$1.100
|
$1.210
|
|
|
|
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
|
LF
|
148.000
|
$7.300
|
$12.000
|
$10.200
|
$11.770
|
|
|
|
PAVEMENT SEALER 4"
|
LF
|
59,396.000
|
$0.220
|
$0.250
|
$0.200
|
$0.220
|
|
|
|
PAVEMENT SEALER 6"
|
LF
|
80,910.000
|
$0.230
|
$0.350
|
$0.310
|
$0.340
|
|
|
|
PAVEMENT SEALER 24"
|
LF
|
148.000
|
$2.920
|
$1.000
|
$1.630
|
$2.530
|
|
|
|
RE PM W/RET REQ TY I (W)6"(SLD)(100MIL)
|
LF
|
80,910.000
|
$0.560
|
$0.750
|
$0.690
|
$0.340
|
|
|
|
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
|
LF
|
5,000.000
|
$1.500
|
$0.550
|
$0.510
|
$0.570
|
|
|
|
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
|
LF
|
54,396.000
|
$0.540
|
$0.550
|
$0.460
|
$0.510
|
|
|
|
REFL PAV MRKR TY II-A-A
|
EA
|
945.000
|
$5.910
|
$2.500
|
$7.150
|
$7.940
|
|
|
|
ELIM EXT PAV MRK & MRKS (4")
|
LF
|
7,260.000
|
$0.640
|
$0.350
|
$0.540
|
$3.850
|
|
|
|
FULL - WIDTH MOWING
|
CYC
|
3.000
|
$15,000.000
|
$8,500.000
|
$10,500.000
|
$3,611.140
|
|
|
|
LITTER REMOVAL
|
CYC
|
3.000
|
$2,000.000
|
$2,397.470
|
$3,300.000
|
$5,531.930
|
|
|
|
DITCH CLEANING AND RESHAPING (FOOT)
|
LF
|
80,990.000
|
$2.000
|
$2.340
|
$1.900
|
$1.360
|
|
|
|
D-GR HMA TY-B PG64-22
|
TON
|
45,181.000
|
$95.000
|
$84.060
|
$98.250
|
$102.000
|
|
|
|
D-GR HMA TY-D PG70-22
|
TON
|
1,691.000
|
$85.000
|
$95.400
|
$156.000
|
$120.000
|
|
|
|
TACK COAT
|
GAL
|
6,427.000
|
$3.700
|
$4.230
|
$3.450
|
$6.420
|
|
|
|
SP MIXES SP-C SAC-B PG70-22
|
TON
|
16,010.000
|
$87.800
|
$99.810
|
$121.000
|
$125.000
|
|
|
|
TACK COAT
|
GAL
|
14,556.000
|
$5.820
|
$4.290
|
$3.500
|
$6.260
|
|
|
|
CEMENT
|
TON
|
492.000
|
$350.750
|
$253.800
|
$0.000
|
$241.520
|
|
|
|
EMULSION
|
GAL
|
422,396.000
|
$1.900
|
$3.780
|
$0.000
|
$3.760
|
|
|
|
EMUL TRTMNT(MX EXST MTRL & NEW BASE) 8"
|
SY
|
127,643.000
|
$4.000
|
$3.280
|
$0.000
|
$2.870
|
|
|
|
PORTABLE CHANGEABLE MESSAGE SIGN
|
EA
|
2.000
|
$9,438.000
|
$10,200.340
|
$12,000.000
|
$39,179.530
|
|
|
|
PREFORMED IN-LANE(TRANS) RUMBLE STRIP
|
LF
|
1,440.000
|
$25.000
|
$9.000
|
$25.500
|
$27.660
|
|
|
|
TMA (STATIONARY)
|
DAY
|
26.000
|
$295.690
|
$357.010
|
$150.000
|
$578.240
|
|
|
|
TMA (MOBILE OPERATION)
|
DAY
|
52.000
|
$150.000
|
$1,020.030
|
$300.000
|
$737.540
|
|
1
|
|
CEMENT
|
TON
|
471.000
|
$388.050
|
$0.000
|
$260.000
|
$0.000
|
|
1
|
|
ASPHALT BINDER (PG 64-22)
|
TON
|
1,219.000
|
$650.000
|
$0.000
|
$814.000
|
$0.000
|
|
1
|
|
FOAMED ASPHALT TREAT (8") (DC)
|
SY
|
127,643.000
|
$4.000
|
$0.000
|
$5.440
|
$0.000
|
|
Totals: |
$15,543,813.520
|
$14,508,838.600
|
$15,483,190.330
|
$16,201,709.500
|