Show Job Controls
Bid Cobra

ATASCOSA IH 35 (0017-04-042)

Items: 93

County: ATASCOSA
Length: N/A
Highway: IH 35
District: SAN ANTONIO
Control Number: 0017-04-042
DBE Goal: N/A
Project: NH 2019(646)
Guaranty: N/A
Time: 345 WORKING DAYS
Engineer's Estimate: $14,294,767.15
Date: 03/06/2019 (7 years ago)
Contract Number: N/A
Type: BS RPR, SC, OVLY & PAV MRKS ON MAINLANES
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (6)
E
Engineer's Estimate
$14,294,767.15
$12,910,717.48
Over/Under Est: -9.68% -$1,384,049.67
$13,842,968.54
Over/Under Est: -3.16% -$451,798.61
Amt Left: 7.22% $932,251.06
Over/Under Est: -1.37% -$196,134.68
Amt Left: 9.2% $1,187,914.99
Delta: -1.85% -$255,663.93
Over/Under Est: 0.68% $96,914.95
Amt Left: 11.47% $1,480,964.62
Delta: -2.08% -$293,049.63
Over/Under Est: 3.81% $545,246.46
Amt Left: 14.94% $1,929,296.13
Delta: -3.12% -$448,331.51
Over/Under Est: 9.48% $1,354,482.58
Amt Left: 21.21% $2,738,532.25
Delta: -5.45% -$809,236.12
Subcontractor Percentage Amount
ROADWAY SPECIALTIES, INC. 12.48% $1,611,257.54
RELMCO, INC. 8.01% $1,034,148.47
FLASHER EQUIPMENT COMPANY 5.81% $750,112.69
DEPENDABLE FENCE & WELDING CO. INC. 5.02% $648,118.02
PERFORMANCE EQUIPMENT SERVICE 3.99% $515,137.63
ALL AMERICAN TRUCKING, INC. 1.47% $189,787.55
CHEROKEE SERVICES 1.35% $174,294.69
G 6 CONSTRUCTION, INC. 1.28% $165,257.18
J & P PAVING CO. 0.37% $47,769.65
TRP CONSTRUCTION GROUP, LLC 0.32% $41,314.30
WEST TEXAS ROCK RESOURCES, LLC 0.15% $19,366.08
BUYERS BARRICADES SAN ANTONIO, LLC 0.02% $2,582.14
Total: 40.27% $5,199,145.94

Bid Items & Bid Tabulations

93 Total 0 of 93
ATASCOSA  |  IH 35  |  SAN ANTONIO  |  0017-04-042  |  03/06/2019  |  $14,294,767.15  |  NH 2019(646)  |  BS RPR, SC, OVLY & PAV MRKS ON MAINL...  |  345 WORKING DAYS
Alt
Item Code
Description
Unit
Quantity
Engineer's Estimate
H. L. ZUMWALT CONSTRUCTION, INC.
HUNTER INDUSTRIES, LTD.
ANGEL BROTHERS HOLDINGS CORP.
LONE STAR PAVING COMPANY
ANDERSON COLUMBIA CO., INC.
CLARK CONSTRUCTION OF TEXAS, INC.
REMOVING CONCRETE(MOW STRIP)
LF 463.000 $9.000 $8.000 $4.470 $10.000 $5.500 $10.000 $3.150
BACKFILL (TY B)
STA 785.000 $95.000 $150.000 $94.650 $125.000 $200.000 $100.000 $190.000
COMPOST MANUF TOPSOIL (4")
SY 27,134.000 $1.350 $1.050 $1.820 $1.500 $1.400 $1.890 $0.860
CELL FBR MLCH SEED(PERM)(RURAL)(SANDY)
SY 27,134.000 $0.300 $0.400 $0.350 $0.370 $0.330 $0.350 $0.370
VEGETATIVE WATERING
MG 423.000 $18.000 $13.000 $19.980 $19.000 $30.000 $30.000 $110.000
ASPH(AC-15P,AC-20-5TR,AC-20XP,AC10-2TR)
GAL 227,861.000 $1.270 $0.000 $0.000 $0.000 $0.000 $0.000 $0.000
AGGR (TY-PB GR-4)
CY 6,604.000 $28.640 $0.000 $0.000 $0.000 $0.000 $0.000 $0.000
SUPERPAVE MIXTURES SP-C SAC-A PG76-22
TON 88,926.000 $80.000 $68.000 $83.920 $89.000 $97.250 $84.680 $109.190
FLEXIBLE PAVEMENT STRUCTURE REPAIR(8")
SY 9,313.000 $35.000 $42.000 $37.150 $40.250 $50.000 $45.000 $44.920
PLANE ASPH CONC PAV (1" TO 3")
SY 748,514.000 $2.500 $1.050 $1.280 $1.000 $1.250 $1.260 $1.000
PLANE ASPH CONC PAV (2" TO 6")
SY 11,019.000 $3.750 $1.150 $2.330 $1.500 $4.500 $2.840 $5.000
FLOWABLE BACKFILL
CY 3.000 $140.000 $200.000 $199.000 $180.000 $870.000 $190.000 $800.000
CL C CONC (RAIL FOUNDATION)
CY 41.600 $350.000 $900.000 $866.000 $770.000 $1,310.000 $825.000 $1,245.000
RIPRAP (MOW STRIP)(4 IN)
CY 1,112.000 $450.000 $450.000 $419.000 $490.000 $400.000 $425.000 $425.000
CLEANING EXISTING JOINTS
LF 1,620.000 $10.000 $16.000 $8.500 $11.000 $9.500 $9.500 $8.930
RETROFIT RAIL (TY SSTR)
LF 2,342.300 $150.000 $155.000 $120.000 $139.000 $110.000 $128.000 $125.000
HEADER TYPE EXPANSION JOINT
CF 272.000 $350.000 $520.000 $387.760 $445.000 $425.000 $388.000 $407.150
JOINT SEALANT
LF 1,620.000 $6.750 $12.000 $6.500 $7.000 $7.250 $6.500 $6.830
MOBILIZATION
LS 1.000 $982,000.000 $800,000.000 $1,082,550.270 $1,094,000.000 $215,000.000 $1,260,000.000 $300,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 22.000 $6,000.000 $12,000.000 $4,721.800 $3,300.000 $2,500.000 $5,000.000 $5,000.000
BIODEG EROSN CONT LOGS (INSTL) (8")
LF 23,213.000 $3.750 $3.500 $3.000 $3.000 $3.750 $2.750 $2.890
BIODEG EROSN CONT LOGS (REMOVE)
LF 23,213.000 $1.000 $0.700 $0.700 $0.600 $1.500 $0.600 $0.690
PORT CTB (FUR & INST)(SGL SLOPE)(TY 1)
LF 4,920.000 $12.000 $50.000 $21.000 $20.000 $13.000 $24.000 $13.000
PORT CTB (MOVE)(SGL SLP)(TY 1)
LF 4,530.000 $4.000 $8.000 $10.500 $10.000 $9.500 $14.000 $9.000
PORT CTB (REMOVE)(SGL SLP)(TY 1)
LF 4,920.000 $4.000 $12.000 $16.500 $10.000 $12.500 $16.000 $12.000
RUMBLE STRIPS (SHOULDER)
LF 287,712.000 $0.150 $0.130 $0.190 $0.150 $0.120 $0.090 $0.240
MTL W-BEAM GD FEN (TIM POST)
LF 19,550.000 $25.000 $20.000 $16.600 $21.000 $24.000 $16.600 $17.450
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 45.000 $1,800.000 $1,575.000 $2,060.000 $2,170.000 $1,550.000 $2,200.000 $1,785.000
MTL BEAM GD FEN TRANS (T101)
EA 26.000 $1,225.000 $860.000 $700.000 $960.000 $1,250.000 $700.000 $735.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 47.000 $1,000.000 $1,100.000 $950.000 $1,000.000 $1,100.000 $950.000 $997.500
REMOVE METAL BEAM GUARD FENCE
LF 19,550.000 $3.000 $1.000 $1.000 $1.500 $1.100 $1.000 $1.050
REMOVE TERMINAL ANCHOR SECTION
EA 46.000 $150.000 $110.000 $100.000 $220.000 $135.000 $104.000 $105.000
RM MTL BM GD FENCE TRANS (THRIE-BEAM)
EA 5.000 $250.000 $195.000 $100.000 $220.000 $110.000 $104.000 $105.000
RM MTL BM GD FEN TRANS (T101)
EA 53.000 $165.000 $25.000 $100.000 $110.000 $110.000 $104.000 $105.000
GUARDRAIL END TREATMENT (INSTALL)
EA 45.000 $2,500.000 $2,715.000 $2,200.000 $2,400.000 $3,000.000 $2,300.000 $2,310.000
GUARDRAIL END TREATMENT (REMOVE)
EA 46.000 $250.000 $116.000 $150.000 $200.000 $215.000 $155.000 $157.500
CRASH CUSH ATTEN (INSTL)
EA 8.000 $10,500.000 $7,300.000 $7,300.000 $7,700.000 $8,000.000 $7,590.000 $7,665.000
CRASH CUSH ATTEN (MOVE & RESET)
EA 8.000 $900.000 $970.000 $500.000 $990.000 $1,000.000 $520.000 $525.000
CRASH CUSH ATTEN (REMOVE)
EA 8.000 $660.000 $265.000 $100.000 $550.000 $750.000 $104.000 $105.000
REPLACE EXISTING ALUMINUM SIGNS(TY A)
SF 500.500 $23.000 $30.000 $25.300 $27.800 $27.500 $30.000 $26.570
INSTL OM ASSM (OM-2Y)(WC)GND
EA 46.000 $48.000 $52.000 $43.950 $48.000 $50.000 $51.000 $46.150
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2
EA 232.000 $18.000 $28.000 $15.000 $14.000 $15.000 $27.000 $15.750
INSTL DEL ASSM (D-SY)SZ 1(BRF)GF2
EA 80.000 $16.000 $28.000 $15.000 $14.000 $15.000 $27.000 $15.750
WK ZN PAV MRK REMOV (W)4"(BRK)
LF 55,030.000 $0.450 $0.660 $0.630 $0.690 $0.690 $0.650 $0.470
WK ZN PAV MRK REMOV (W)4"(SLD)
LF 231,957.000 $0.450 $0.600 $0.570 $0.630 $0.620 $0.600 $0.470
WK ZN PAV MRK REMOV (W)(ENTR GORE)
EA 12.000 $2.000 $785.000 $750.000 $825.000 $800.000 $780.000 $525.000
WK ZN PAV MRK REMOV (W)(EXIT GORE)
EA 13.000 $680.000 $785.000 $750.000 $825.000 $800.000 $780.000 $525.000
WK ZN PAV MRK REMOV (Y)4"(SLD)
LF 230,509.000 $0.450 $0.600 $0.570 $0.630 $0.600 $0.600 $0.470
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 44,815.000 $1.000 $1.250 $1.250 $0.850 $0.700 $1.500 $0.690
WK ZN PAV MRK SHT TERM (TAB)TY Y
EA 17,332.000 $0.500 $1.250 $1.250 $0.850 $0.700 $1.500 $0.790
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 378.000 $0.900 $0.740 $0.700 $0.770 $0.750 $0.750 $1.000
REFL PAV MRK TY I (W)12"(SLD)(100MIL)
LF 1,143.000 $3.000 $2.570 $2.440 $2.680 $2.650 $2.500 $2.630
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 2,125.000 $5.500 $5.250 $5.000 $5.500 $5.250 $5.200 $5.250
REFL PAV MRK TY I (W)(ARROW)(100MIL)
EA 3.000 $120.000 $117.000 $111.000 $120.000 $120.000 $115.000 $99.750
REFL PAV MRK TY I(W)(DBL ARROW)(100MIL)
EA 3.000 $235.000 $198.000 $188.000 $200.000 $200.000 $195.000 $131.250
REFL PAV MRK TY I (W)(WORD)(100MIL)
EA 3.000 $150.000 $130.000 $124.000 $135.000 $135.000 $130.000 $131.250
REFL PAV MRK TY I(W)(ENTR GORE)(100MIL)
EA 14.000 $750.000 $900.000 $850.000 $925.000 $900.000 $880.000 $420.000
REFL PAV MRK TY I(W)(EXIT GORE)(100MIL)
EA 14.000 $650.000 $900.000 $850.000 $925.000 $900.000 $880.000 $420.000
REFL PAV MRK TY I (W)(SYMBOL)(100MIL)
EA 6.000 $200.000 $420.000 $400.000 $440.000 $425.000 $415.000 $157.500
REF PAV MRK TY I(W)36"(YLD TRI)(100MIL)
EA 16.000 $35.000 $47.000 $44.000 $48.000 $50.000 $46.000 $26.250
REFL PAV MRK TY I (Y)24"(SLD)(100MIL)
LF 249.000 $6.000 $5.250 $5.000 $5.500 $5.500 $5.200 $5.250
PAVEMENT SEALER 4"
LF 313.000 $0.150 $0.460 $0.440 $0.480 $0.500 $0.500 $0.160
PAVEMENT SEALER 6"
LF 386,921.000 $0.150 $0.180 $0.170 $0.190 $0.180 $0.200 $0.160
PAVEMENT SEALER 8"
LF 378.000 $0.300 $0.530 $0.500 $0.550 $0.550 $0.500 $0.320
PAVEMENT SEALER 12"
LF 1,143.000 $0.400 $1.150 $1.090 $1.200 $1.150 $1.100 $0.530
PAVEMENT SEALER 24"
LF 2,374.000 $2.500 $2.550 $2.440 $2.680 $2.600 $2.500 $1.050
PAVEMENT SEALER (ARROW)
EA 3.000 $45.000 $66.000 $63.000 $65.000 $70.000 $65.000 $57.750
PAVEMENT SEALER (WORD)
EA 3.000 $45.000 $70.000 $67.000 $70.000 $75.000 $70.000 $68.250
PAVEMENT SEALER (DBL ARROW)
EA 3.000 $100.000 $116.000 $109.000 $110.000 $120.000 $114.000 $78.750
PAVEMENT SEALER (ENTR GORE)
EA 14.000 $450.000 $475.000 $450.000 $490.000 $475.000 $470.000 $157.500
PAVEMENT SEALER (EXIT GORE)
EA 14.000 $450.000 $475.000 $450.000 $490.000 $475.000 $470.000 $157.500
PAVEMENT SEALER (SYMBOL)
EA 6.000 $35.000 $126.000 $120.000 $130.000 $130.000 $125.000 $78.750
PAVEMENT SEALER (YLD TRI)
EA 16.000 $16.000 $24.000 $22.000 $24.000 $25.000 $23.000 $10.500
RE PM W/RET REQ TY I (W)4"(BRK)(100MIL)
LF 313.000 $0.450 $0.520 $0.500 $0.550 $0.550 $0.520 $0.320
RE PM W/RET REQ TY I (W)6"(BRK)(100MIL)
LF 40,054.000 $0.600 $0.520 $0.500 $0.550 $0.530 $0.520 $0.370
RE PM W/RET REQ TY I (W)6"(SLD)(100MIL)
LF 174,205.000 $0.500 $0.500 $0.480 $0.530 $0.500 $0.500 $0.370
RE PM W/RET REQ TY I (Y)6"(SLD)(100MIL)
LF 172,662.000 $0.500 $0.500 $0.480 $0.530 $0.500 $0.500 $0.370
REFL PAV MRKR TY I-C
EA 18.000 $3.500 $5.250 $5.000 $5.500 $5.500 $5.200 $3.150
REFL PAV MRKR TY I-R
EA 224.000 $3.400 $5.250 $5.000 $5.500 $5.450 $5.200 $10.500
REFL PAV MRKR TY II-C-R
EA 2,908.000 $3.750 $3.500 $3.330 $3.500 $3.500 $3.500 $4.200
ELIM EXT PAV MRK & MRKS (4")
LF 37,450.000 $0.400 $0.500 $0.470 $0.520 $0.680 $0.500 $0.260
FULL - WIDTH MOWING
CYC 8.000 $2,900.000 $4,000.000 $4,000.000 $1,700.000 $1,750.000 $13,300.000 $3,150.000
CLEANING / SWEEPING (OUTSIDE MAIN LANE)
CYC 22.000 $1,700.000 $3,000.000 $4,000.000 $1,320.000 $1,750.000 $2,180.000 $3,150.000
REPLACE POSTS (TL-3)
EA 165.000 $80.000 $116.000 $90.000 $138.000 $135.000 $94.000 $94.500
CABLE SPLICE / TURNBUCKLE (TL-3)
EA 3.000 $125.000 $475.000 $200.000 $247.000 $250.000 $210.000 $210.000
REPAIR CONCRETE FOUNDATION (TL-3)
EA 3.000 $215.000 $500.000 $500.000 $385.000 $400.000 $2,080.000 $525.000
REPR OR REPLC CABLE BARR TERM SEC(TL-3)
EA 3.000 $475.000 $2,940.000 $500.000 $3,270.000 $3,250.000 $520.000 $525.000
REPLACE CABLE (TL-3)
LF 1,500.000 $1.000 $14.700 $6.000 $2.700 $2.750 $6.000 $6.300
CHECK / RE-TENSION CABLE
EA 11.000 $200.000 $1,155.000 $150.000 $550.000 $545.000 $156.000 $157.500
PORTABLE CHANGEABLE MESSAGE SIGN
EA 4.000 $12,000.000 $15,000.000 $7,036.250 $5,000.000 $15,000.000 $25,300.000 $15,000.000
TMA (STATIONARY)
DAY 571.000 $165.000 $200.000 $200.260 $25.000 $125.000 $210.000 $400.000
TMA (MOBILE OPERATION)
DAY 1,197.000 $130.000 $250.000 $108.250 $25.000 $75.000 $210.000 $400.000
1
MEMBRANE UNDERSEAL
GAL 227,868.000 $2.100 $3.000 $2.520 $2.500 $2.650 $4.000 $2.750
Totals: $14,773,289.180 $12,910,717.480 $13,842,968.540 $14,098,632.470 $14,391,682.100 $14,840,013.610 $15,649,249.735