Show Job Controls
Bid Cobra

ARCHER SH 114 (0133-07-026)

Items: 7

County: ARCHER
Length: N/A
Highway: SH 114
District: WICHITA FALLS
Control Number: 0133-07-026
DBE Goal: N/A
Project: STP 1702(138)HES
Guaranty: N/A
Time: 27 WORKING DAYS
Engineer's Estimate: $483,977.48
Date: 04/04/2017 (9 years ago)
Contract Number: N/A
Type: CENTERLINE TEXTURING
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (7)
E
Engineer's Estimate
$483,977.48
1
$273,290.91
Over/Under Est: -43.53% -$210,686.57
$308,527.85
Over/Under Est: -36.25% -$175,449.63
Amt Left: 12.89% $35,236.94
Over/Under Est: -34.63% -$167,585.89
Amt Left: 15.77% $43,100.68
Delta: -2.55% -$7,863.74
Over/Under Est: -33.62% -$162,704.84
Amt Left: 17.56% $47,981.73
Delta: -1.54% -$4,881.05
Over/Under Est: -21.16% -$102,430.24
Amt Left: 39.61% $108,256.33
Delta: -18.76% -$60,274.60
Over/Under Est: -16.71% -$80,869.94
Amt Left: 47.5% $129,816.63
Delta: -5.65% -$21,560.30
Over/Under Est: -15.21% -$73,605.75
Amt Left: 50.16% $137,080.82
Delta: -1.80% -$7,264.19

Bid Items & Bid Tabulations

7 Total 0 of 7
ARCHER  |  SH 114  |  WICHITA FALLS  |  0133-07-026  |  04/04/2017  |  $483,977.48  |  STP 1702(138)HES  |  CENTERLINE TEXTURING  |  27 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
L&L COMPANY
FLAT LINE, INC.
DOUBLE A CONTRACTING, L.P.
TOTAL HIGHWAY MAINTENANCE, LLC
BARRICADES UNLIMITED
TEXAS PANHANDLE CONSTRUCTION, INC.
TRP CONSTRUCTION GROUP, LLC
MOBILIZATION
LS 1.000 $25,000.000 $1.000 $1.000 $10,000.000 $1.000 $1,000.000 $10,000.000 $27,050.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 2.000 $6,000.000 $1.000 $1.000 $2,000.000 $1.000 $1,750.000 $1,000.000 $2,500.000
RUMBLE STRIPS (CENTERLINE)
LF 365,459.000 $0.220 $0.150 $0.145 $0.160 $0.180 $0.260 $0.220 $0.170
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 731,184.000 $0.320 $0.180 $0.220 $0.210 $0.212 $0.240 $0.269 $0.270
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
LF 74,065.000 $0.300 $0.200 $0.220 $0.210 $0.220 $0.240 $0.269 $0.300
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 283,726.000 $0.320 $0.190 $0.220 $0.210 $0.220 $0.240 $0.269 $0.270
REFL PAV MRKR TY II-A-A
EA 7,254.000 $2.700 $2.500 $2.200 $2.100 $3.000 $2.850 $2.450 $2.750
Totals: $483,977.480 $273,290.910 $308,527.855 $316,391.590 $321,272.648 $381,547.240 $403,107.555 $410,371.730