Show Job Controls
Bid Cobra

ANGELINA FM 3124 (2662-03-003)

Items: 82

County: ANGELINA
Length: N/A
Highway: FM 3124
District: LUFKIN
Control Number: 2662-03-003
DBE Goal: 550.0%
Project: STP 2B24(159)HES
Guaranty: N/A
Time: 120 WORKING DAYS
Engineer's Estimate: $3,405,139.15
Date: 06/06/2024 (2 years ago)
Contract Number: N/A
Type: HAZARD ELIMINATION & SAFETY
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (2)
E
Engineer's Estimate
$3,405,139.15
$3,926,436.54
Over/Under Est: 15.31% $521,297.39
Over/Under Est: 25.59% $871,446.40
Amt Left: 8.92% $350,149.01
Subcontractor Percentage Amount
TEXAS MATERIALS GROUP, INC. 33.59% $1,324,207.25
A R BROTHERS CONSTRUCTION SERVICES, INC. 8.17% $322,083.16
INTERSTATE BARRICADES & MARKINGS, INC. 1.78% $70,172.34
DREWERY BROS. TREE SERVICE, INC. 1.68% $66,230.07
SOUTHWEST ENVIRONMENT SERVICES LLC 1.33% $52,432.14
CAP RIVER LLC 0.96% $37,845.76
THIRD COAST SERVICES LLC 0.74% $29,172.77
DUSTIN ALLEN, INC. 0.45% $17,740.20
PANOLA SIGN & BARRICADE, INC. 0.43% $16,951.75
DUSTROL, INC. 0.30% $11,826.80
WEST TEXAS ROCK RESOURCES, LLC 0.15% $5,913.40
Total: 49.58% $1,954,575.64

Bid Items & Bid Tabulations

82 Total 0 of 82
ANGELINA  |  FM 3124  |  LUFKIN  |  2662-03-003  |  06/06/2024  |  $3,405,139.15  |  STP 2B24(159)HES  |  HAZARD ELIM & SAFETY  |  120 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
PINTO CONSTRUCTION CO., INC.
DREWERY CONSTRUCTION COMPANY, INCORPORATED
PREPARING ROW
STA 122.000 $1,500.000 $678.760 $870.000
REMOVING CONC (RIPRAP)
SY 80.000 $40.000 $44.000 $55.000
SUBGRADE WIDENING (ORD COMP)
STA 122.000 $460.000 $442.030 $975.000
EMBANKMENT (VEHICLE)(ORD COMP)(TY B)
CY 6,960.000 $20.000 $24.210 $28.000
BLADING
STA 122.000 $250.000 $136.540 $255.000
SPEC EXCAV WORK (HYD EXCAVATOR)
HR 51.000 $215.000 $165.000 $250.000
BLOCK SODDING
SY 3,120.000 $6.500 $6.070 $6.450
BROADCAST SEED (TEMP) (WARM)
SY 13,485.000 $0.150 $0.180 $0.140
BROADCAST SEED (TEMP) (COOL)
SY 13,485.000 $0.150 $0.180 $0.140
BOND FBR MTRX SEED (PERM)(RURAL)(SAND)
SY 26,970.000 $0.700 $0.820 $0.600
VEGETATIVE WATERING
MG 1,142.000 $5.000 $0.010 $41.000
SOIL RETENTION BLANKETS (CL 1) (TY A)
SY 20.000 $2.000 $11.000 $3.900
CEM TRT (PLNT MX)(CL N)(TY A)(GR3)(12")
SY 10,788.000 $80.000 $91.660 $103.500
EMULS ASPH (EROSN CONT)(SS-1)
GAL 1,619.000 $8.000 $7.040 $6.500
ASPH (RC-250)
TON 12.000 $1,700.000 $2,579.170 $1,525.000
AGGR (TY E OR L, PE OR PL GR 4)
CY 260.000 $225.000 $182.930 $205.000
AGGR (TY E OR L GR 5)
CY 78.000 $225.000 $389.750 $355.000
ASPH (AC-15P OR CRS-2P)
TON 63.000 $900.000 $1,002.140 $1,030.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(12")
SY 400.000 $155.000 $241.410 $285.000
PLANE ASPH CONC PAV(0" TO 2")
SY 290.000 $6.000 $55.000 $24.000
CEM STABIL BKFL
CY 10.000 $800.000 $440.000 $278.000
TEMPORARY SPL SHORING
SF 148.000 $70.000 $60.500 $61.000
DRILL SHAFT (RDWY ILL POLE) (30 IN)
LF 8.000 $300.000 $521.400 $335.000
CL C CONC (COLLAR)
EA 7.000 $1,000.000 $1,650.000 $2,000.000
RIPRAP (CONC)(4 IN)
CY 8.000 $700.000 $990.000 $1,100.000
RIPRAP (STONE COMMON)(DRY)(18 IN)
CY 46.000 $300.000 $324.500 $234.000
RIPRAP (STONE COMMON)(DRY)(24 IN)
CY 190.000 $250.000 $324.500 $245.000
RC PIPE (CL III)(18 IN)
LF 345.000 $80.000 $121.000 $55.000
RC PIPE (CL III)(24 IN)
LF 32.000 $120.000 $165.000 $106.000
RC PIPE (CL III)(30 IN)
LF 20.000 $140.000 $187.000 $145.000
RC PIPE (CL III)(36 IN)
LF 4.000 $170.000 $275.000 $205.000
HEADWALL (CH - FW - 0) (DIA= 54 IN)
EA 1.000 $12,000.000 $20,900.000 $28,000.000
HEADWALL (CH - PW - 0) (DIA= 30 IN)
EA 1.000 $8,000.000 $14,850.000 $17,000.000
HEADWALL (CH - PW - 0) (DIA= 36 IN)
EA 1.000 $10,000.000 $17,050.000 $20,000.000
HEADWALL (CH - PW - 0) (DIA= 48 IN)
EA 1.000 $16,000.000 $20,350.000 $21,000.000
SET (TY II) (18 IN) (RCP) (4: 1) (C)
EA 4.000 $900.000 $1,045.000 $800.000
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 20.000 $1,000.000 $1,155.000 $940.000
SET (TY II) (24 IN) (RCP) (4: 1) (C)
EA 6.000 $1,400.000 $1,430.000 $1,400.000
SET (TY II) (30 IN) (RCP) (4: 1) (C)
EA 3.000 $2,000.000 $3,850.000 $2,900.000
SET (TY II) (36 IN) (RCP) (4: 1) (C)
EA 1.000 $4,500.000 $5,500.000 $4,800.000
CLEAN EXIST CULVERTS
EA 6.000 $2,500.000 $3,300.000 $2,000.000
REMOVE STR (CONC)
EA 2.000 $3,000.000 $3,850.000 $1,100.000
MOBILIZATION
LS 1.000 $320,000.000 $390,000.000 $325,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 11.000 $3,500.000 $2,000.000 $15,000.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 372.000 $45.000 $56.650 $58.000
ROCK FILTER DAMS (REMOVE)
LF 372.000 $15.000 $14.850 $15.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 250.000 $10.000 $5.000 $33.000
CONSTRUCTION EXITS (REMOVE)
SY 250.000 $5.000 $1.000 $12.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 444.000 $5.000 $6.710 $6.800
TEMP SEDMT CONT FENCE (REMOVE)
LF 444.000 $1.500 $1.650 $1.650
DRIVEWAYS (ACP)
SY 1,244.000 $75.000 $72.190 $78.000
TURNOUTS (SURF TREAT)
SY 138.000 $90.000 $146.510 $122.000
RUMBLE STRIPS (CENTERLINE)
LF 12,125.000 $0.200 $1.000 $0.310
MTL W-BEAM GD FEN (TIM POST)
LF 255.000 $27.000 $52.380 $31.000
REMOVE METAL BEAM GUARD FENCE
LF 275.000 $4.000 $12.000 $11.500
GUARDRAIL END TREATMENT (INSTALL)
EA 2.000 $3,500.000 $3,465.000 $3,350.000
GUARDRAIL END TREATMENT (REMOVE)
EA 2.000 $285.000 $385.000 $400.000
WIRE FENCE (TY A)
LF 10.000 $20.000 $100.000 $85.000
MAILBOX INSTALL-S (WC-POST) TY 3
EA 6.000 $225.000 $281.600 $230.000
IN RD IL (TY SA) 40T-8 (250W EQ) LED
EA 1.000 $4,500.000 $7,866.100 $9,000.000
CONDT (PVC) (SCH 80) (2") (BORE)
LF 170.000 $20.000 $28.050 $13.500
ELEC CONDR (NO.8) BARE
LF 170.000 $2.000 $3.170 $4.500
ELEC CONDR (NO.8) INSULATED
LF 80.000 $2.000 $3.470 $4.500
GROUND BOX TY A (122311)W/APRON
EA 3.000 $1,200.000 $1,623.600 $700.000
ELC SRV TY D 120/240 060(NS)SS(E)SP(O)
EA 1.000 $6,500.000 $9,478.700 $9,500.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 4.000 $725.000 $910.800 $840.000
IN SM RD SN SUP&AM TYTWT(1)WS(P)
EA 11.000 $450.000 $544.500 $540.000
IN SM RD SN SUP&AM TYTWT(1)WS(T)
EA 2.000 $550.000 $657.800 $630.000
REMOVE SM RD SN SUP&AM
EA 17.000 $100.000 $128.700 $165.000
INSTL OM ASSM (OM-2Z)(WFLX)SRF(BI)
EA 26.000 $100.000 $160.600 $117.000
WK ZN PAV MRK NON-REMOV (Y)6"(SLD)
LF 48,546.000 $0.400 $0.330 $0.450
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 3,642.000 $1.000 $2.000 $2.100
REF PROF PAV MRK TY I(W)6"(SLD)(090MIL)
LF 24,177.000 $1.000 $1.650 $1.400
RE PM W/RET REQ TY I (Y)6"(BRK)(090MIL)
LF 1,590.000 $0.750 $1.090 $0.750
RE PM W/RET REQ TY I (Y)6"(SLD)(090MIL)
LF 16,419.000 $0.750 $1.090 $0.750
PREFAB PAV MRK TY C (W) (24") (SLD)
LF 35.000 $16.000 $13.200 $16.000
REFL PAV MRKR TY II-A-A
EA 224.000 $5.500 $5.500 $9.000
SP MIXES SP-C SAC-A PG70-22
TON 5,866.000 $160.000 $195.690 $202.000
BONDING COURSE
GAL 1,761.000 $5.500 $6.600 $7.750
PORTABLE CHANGEABLE MESSAGE SIGN
EA 1.000 $20,000.000 $30,000.000 $20,000.000
TMA (STATIONARY)
DAY 120.000 $200.000 $250.000 $290.000
TMA (MOBILE OPERATION)
DAY 10.000 $200.000 $50.000 $55.000
Totals: $3,405,139.150 $3,926,436.540 $4,276,585.550