Items: 36

County: ANGELINA
Length: N/A
Highway: VA
District: LUFKIN
Control Number: 0911-38-071
DBE Goal: N/A
Project: STP 2019(183)
Guaranty: N/A
Time: 79 WORKING DAYS
Engineer's Estimate: $207,604.75
Date: 11/07/2018 (7 years ago)
Contract Number: N/A
Type: LANDSCAPING_IN VARIOUS LOCATIONS
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (3)
E
Engineer's Estimate
$207,604.75
Over/Under Est: 14.93% $30,990.70
Over/Under Est: 130.79% $271,517.43
Amt Left: 100.81% $240,526.73
Over/Under Est: 133.61% $277,381.65
Amt Left: 103.27% $246,390.95
Delta: -1.22% -$5,864.22

Bid Items & Bid Tabulations

36 Total 0 of 36
ANGELINA  |  VA  |  LUFKIN  |  0911-38-071  |  11/07/2018  |  $207,604.75  |  STP 2019(183)  |  LANDSCAPING_IN VARIOUS LOCATIONS  |  79 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
GREEN SOURCE ENVIRONMENTAL SOLUTIONS, INC.
COX CONCRETE CONTRACTORS, INCORPORATED
CLASSIC IRRIGATION & LANDSCAPE LLC
PREPARING ROW
AC 0.170 $30,000.000 $10,000.000 $82,080.000 $1,000.000
EMBANKMENT (FINAL)(ORD COMP)(TY A)
CY 55.000 $30.000 $50.000 $92.000 $2.500
BLOCK SODDING
SY 749.000 $4.500 $6.000 $7.160 $7.000
VEGETATIVE WATERING
MG 7.400 $10.000 $10.000 $174.000 $1.000
IRRIGATION SYSTEM
LS 6.000 $1,600.000 $6,000.000 $1,954.000 $1,200.000
PLANT MATERIAL (4" CNTR)
EA 60.000 $1.750 $3.000 $4.000 $3.000
PLANT MATERIAL (1-GAL)
EA 288.000 $12.000 $10.000 $16.420 $10.000
PLANT MATERIAL (3-GAL)
EA 131.000 $35.000 $18.000 $32.830 $30.000
PLANT MATERIAL (15-GAL)
EA 20.000 $175.000 $130.000 $102.600 $150.000
MULCH
SY 427.000 $9.000 $10.000 $7.410 $55.000
PLANT BED PREPARATION
SY 427.000 $17.250 $1.200 $9.610 $10.000
PLANT MATERIAL (45 GAL) (TREE)
EA 12.000 $500.000 $300.000 $684.010 $416.000
CL C CONC (FOOTING)
CY 16.800 $910.000 $250.000 $1,230.100 $540.000
MOBILIZATION
LS 1.000 $21,000.000 $23,000.000 $13,564.000 $16,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 5.000 $2,500.000 $1,669.210 $3,048.000 $2,500.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 70.000 $3.000 $2.000 $14.100 $2.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 70.000 $1.000 $1.000 $7.000 $1.500
LANDSCAPE PAVERS
SY 94.000 $95.000 $43.500 $336.800 $43.000
CONDT (HDPE) (2") BORE
LF 245.000 $35.000 $20.000 $144.230 $20.000
GROUND BOX TY A (122311)
EA 2.000 $750.000 $650.000 $1,130.000 $500.000
LANDSCAPE AMENITY (TY 1)
EA 1.000 $15,000.000 $10,000.000 $72,265.000 $25,000.000
LANDSCAPE AMENITY (TY 2)
EA 1.000 $3,500.000 $10,000.000 $9,947.000 $40,000.000
LANDSCAPE AMENITY (TY 3)
EA 1.000 $8,000.000 $10,000.000 $15,371.000 $25,000.000
LANDSCAPE AMENITY (TY 4)
EA 1.000 $8,000.000 $10,000.000 $15,034.000 $25,000.000
LANDSCAPE AMENITY (TY 5)
EA 1.000 $11,000.000 $10,000.000 $52,981.000 $10,000.000
LANDSCAPE AMENITY (TY 6)
EA 1.000 $600.000 $10,000.000 $9,970.000 $25,000.000
LANDSCAPE AMENITY (TY 7)
EA 1.000 $15,500.000 $10,000.000 $38,013.000 $25,000.000
LANDSCAPE AMENITY (TY 8)
EA 2.000 $3,800.000 $9,000.000 $5,064.000 $15,000.000
LANDSCAPE AMENITY (TY 9)
EA 2.000 $3,800.000 $9,000.000 $4,771.000 $15,000.000
LANDSCAPE AMENITY (TY 10)
EA 6.000 $500.000 $500.000 $1,290.000 $6,000.000
LANDSCAPE AMENITY (TY 11)
EA 17.000 $250.000 $500.000 $1,241.600 $2,600.000
LANDSCAPE AMENITY (TY 12)
EA 17.000 $225.000 $500.000 $1,241.600 $2,900.000
LANDSCAPE AMENITY (TY 13)
EA 4.000 $300.000 $500.000 $596.000 $3,600.000
TREE PROTECTION
EA 1.000 $200.000 $200.000 $1,759.000 $1,000.000
LOOSE AGGR FOR GROUNDCOVER (TYPE I)
CY 4.330 $250.000 $400.000 $352.000 $250.000
LOOSE AGGR FOR GROUNDCOVER (TYPE II)
CY 3.000 $175.000 $400.000 $1,954.000 $250.000
Totals: $207,604.750 $238,595.450 $479,122.180 $484,986.400