ANDERSON FM 1990 (1928-01-005)
Items: 66
County: ANDERSON
Length: 0.0000 MILES
Highway: FM 1990
District: TYLER
Control Number: 1928-01-005
DBE Goal: 6.0%
Project: STP 2025(993)HES
Guaranty: $48,000.00
Time: 125 WORKING DAYS
Engineer's Estimate: $2,383,206.49
Date: 07/01/2025 (11 months ago)
Contract Number: 7253041
Type: HAZARD ELIMINATION & SAFETY
Project ID: A00193092
Contract Type: Federal
Project Description: SAFETY TREAT FIXED OBJECTS
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
DANNY HENDERSON
EDUARDO CASTANEDA
ANDERSON FM 1990 (1928-01-005)
Project Name: N/A
Project: STP 2025(993)HES
Length: 0.0000 MILES
Project Type: CONSTRUCTION
Limits From: 0.1 MI N OF GUM CR
Limits To: CR 2137
Project Description: SAFETY TREAT FIXED OBJECTS
ANDERSON FM 19 (0559-01-015)
Project Name: FM 19, SH 155- CADDO CRK, 2024 HSIP
Project: STP 2025(993)HES
Length: 0.0000 MILES
Project Type: SAFETY IMPROVEMENT PROJECTS
Limits From: SH 155
Limits To: .125 MI S OF CADDO CR
Project Description: SAFETY TREAT FIXED OBJECTS
ANDERSON FM 861 (1173-01-007)
Project Name: FM 861, BOX CRK-CR 100, 2024 HSIP
Project: STP 2025(993)HES
Length: 0.0000 MILES
Project Type: SAFETY IMPROVEMENT PROJECTS
Limits From: BOX CR
Limits To: CR 100
Project Description: SAFETY TREAT FIXED OBJECTS
Bidders (10)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$2,383,206.49 | |||
| $1,639,418.17 |
-31.21%
-$743,788.32
|
|||
| $1,941,517.68 |
-18.53%
-$441,688.81
|
18.43%
$302,099.51
|
||
| $1,989,245.30 |
-16.53%
-$393,961.19
|
21.34%
$349,827.13
|
-2.46%
-$47,727.62
|
|
| $2,054,544.00 |
-13.79%
-$328,662.49
|
25.32%
$415,125.83
|
-3.28%
-$65,298.70
|
|
| $2,067,898.00 |
-13.23%
-$315,308.49
|
26.14%
$428,479.83
|
-0.65%
-$13,354.00
|
|
| $2,369,900.65 |
-0.56%
-$13,305.84
|
44.56%
$730,482.48
|
-14.60%
-$302,002.65
|
|
| $2,380,503.43 |
-0.11%
-$2,703.06
|
45.2%
$741,085.26
|
-0.45%
-$10,602.78
|
|
| $2,381,996.00 |
-0.05%
-$1,210.49
|
45.3%
$742,577.83
|
-0.06%
-$1,492.57
|
|
| $2,823,203.00 |
18.46%
$439,996.51
|
72.21%
$1,183,784.83
|
-18.52%
-$441,207.00
|
|
| $3,125,834.20 |
31.16%
$742,627.71
|
90.67%
$1,486,416.03
|
-10.72%
-$302,631.20
|
E
Engineer's Estimate
$2,383,206.49
1
Awarded
$1,639,418.17
Over/Under Est:
-31.21%
-$743,788.32
$1,941,517.68
Over/Under Est:
-18.53%
-$441,688.81
Amt Left:
18.43%
$302,099.51
$1,989,245.30
Over/Under Est:
-16.53%
-$393,961.19
Amt Left:
21.34%
$349,827.13
Delta:
-2.46%
-$47,727.62
$2,054,544.00
Over/Under Est:
-13.79%
-$328,662.49
Amt Left:
25.32%
$415,125.83
Delta:
-3.28%
-$65,298.70
$2,067,898.00
Over/Under Est:
-13.23%
-$315,308.49
Amt Left:
26.14%
$428,479.83
Delta:
-0.65%
-$13,354.00
$2,369,900.65
Over/Under Est:
-0.56%
-$13,305.84
Amt Left:
44.56%
$730,482.48
Delta:
-14.60%
-$302,002.65
$2,380,503.43
Over/Under Est:
-0.11%
-$2,703.06
Amt Left:
45.2%
$741,085.26
Delta:
-0.45%
-$10,602.78
$2,381,996.00
Over/Under Est:
-0.05%
-$1,210.49
Amt Left:
45.3%
$742,577.83
Delta:
-0.06%
-$1,492.57
$2,823,203.00
Over/Under Est:
18.46%
$439,996.51
Amt Left:
72.21%
$1,183,784.83
Delta:
-18.52%
-$441,207.00
$3,125,834.20
Over/Under Est:
31.16%
$742,627.71
Amt Left:
90.67%
$1,486,416.03
Delta:
-10.72%
-$302,631.20
| Subcontractor | Percentage | Amount |
|---|---|---|
| CAP RIVER LLC | 5.07% | $83,118.50 |
| DIAMOND ELITE BARRICADES, LLC | 0.84% | $13,771.11 |
| Total: | 5.91% | $96,889.61 |
Bid Items & Bid Tabulations
66
Total
0 of 66
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
| Description | Amount |
|---|---|
| EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) | $1,000.00 |
| SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) | $1,000.00 |
| Total: | $2,000.00 |