Show Job Controls
Bid Cobra

ANDERSON US 175 (0198-03-026)

Items: 201

County: ANDERSON
Length: N/A
Highway: US 175
District: TYLER
Control Number: 0198-03-026
DBE Goal: N/A
Project: C 198-3-26
Guaranty: N/A
Time: 510 WORKING DAYS
Engineer's Estimate: $48,036,548.55
Date: 06/30/2022 (3 years ago)
Contract Number: N/A
Type: WIDEN ROAD - ADD LANES
Mail/Deliver Bids To: N/A
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (4)
E
Engineer's Estimate
$48,036,548.55
$55,487,305.16
Over/Under Est: 15.51% $7,450,756.61
$62,792,646.11
Over/Under Est: 30.72% $14,756,097.56
Amt Left: 13.17% $7,305,340.95
$63,868,868.68
Over/Under Est: 32.96% $15,832,320.13
Amt Left: 15.11% $8,381,563.52
Delta: -1.71% -$1,076,222.57
Over/Under Est: 35.13% $16,872,955.53
Amt Left: 16.98% $9,422,198.92
Delta: -1.63% -$1,040,635.40
Subcontractor Percentage Amount
J & M CONTRACTING, COMPANY 6.85% $3,850,443.68
J. H. ODEN CONTRACTING COMPANY 3.07% $1,725,673.30
ANCORTEX, INC. 1.31% $736,362.22
STRIPING TECHNOLOGY, L.P. 0.44% $247,327.77
TORO BRAVO CONSTRUCTION, LLC 0.31% $174,253.66
DUSTIN ALLEN, INC. 0.19% $106,800.63
SOUTHWEST ENVIRONMENT SERVICES LLC 0.18% $101,179.54
FLEX SUPPLY, LLC 0.13% $73,074.11
WHM CONSTRUCTION, INC. 0.08% $44,968.69
A&J REBAR LLC 0.06% $33,726.51
A-CORE CONCRETE CUTTING OF TEXAS, INC. 0.04% $22,484.34
1 PRIORITY ENVIRONMENTAL SERVICES, LLC 0.04% $22,484.34
SCOTT DERR PAINTING CO, LLC 0.03% $16,863.26
STRIPE-A-ZONE, LLC 0.03% $16,863.26
NEXT CONSTRUCTION SOLUTIONS LLC 0.00% $0.00
Total: 12.76% $7,172,505.31

Bid Items & Bid Tabulations

201 Total 0 of 201
ANDERSON  |  US 175  |  TYLER  |  0198-03-026  |  06/30/2022  |  $48,036,548.55  |  C 198-3-26  |  WIDEN ROAD - ADD LANES  |  510 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
BIG CREEK CONSTRUCTION, LTD.
A. L. HELMCAMP, INC.
EAST TEXAS BRIDGE, INC.
LONGVIEW BRIDGE AND ROAD, LTD.
PREPARING ROW
STA 287.200 $1,600.000 $5,000.000 $10,600.000 $10,400.000 $10,000.000
REMOVING CONC (RIPRAP)
SY 923.000 $12.000 $15.000 $22.000 $10.000 $15.000
REMOVING CONC (DRIVEWAYS)
SY 790.000 $17.000 $25.000 $32.000 $12.000 $20.000
REMOVING CONC (CURB AND GUTTER)
LF 2,197.000 $8.500 $10.000 $14.000 $7.000 $10.000
REMOVING CONC (FLUME)
SY 19.000 $45.000 $75.000 $30.000 $55.000 $40.000
REMOVING STAB BASE & ASPH PAV (8"-14")
SY 125,792.000 $3.500 $5.000 $7.000 $7.500 $5.500
EXCAVATION (ROADWAY)
CY 433,689.000 $8.000 $8.000 $8.000 $7.750 $10.000
EMBANKMENT (FINAL)(DENS CONT)(TY C)
CY 265,951.000 $8.500 $6.000 $5.000 $9.000 $14.000
BLADING
HR 150.000 $100.000 $150.000 $128.000 $150.000 $155.000
FURNISHING AND PLACING TOPSOIL (4")
SY 469,157.000 $1.400 $1.000 $0.700 $1.000 $1.600
EROSION CONTROL COMPOST (2")
SY 464,601.000 $0.750 $2.000 $0.500 $1.550 $1.650
BLOCK SODDING
SY 4,556.000 $4.500 $7.000 $5.300 $5.500 $5.500
BROADCAST SEED (PERM) (RURAL) (SANDY)
SY 464,601.000 $0.150 $0.100 $0.080 $0.150 $0.150
BOND FBR MTRX SEED (PERM)(RURAL)(SAND)
SY 464,601.000 $0.800 $0.700 $0.710 $0.700 $0.720
BONDED FBR MTRX SEED (TEMP)(WARM)
SY 234,581.000 $0.800 $0.680 $0.710 $0.670 $0.690
BONDED FBR MTRX SEED (TEMP)(COOL)
SY 234,581.000 $0.800 $0.680 $0.710 $0.650 $0.690
VEGETATIVE WATERING
MG 22,520.000 $8.000 $8.000 $5.000 $7.000 $22.000
SOIL RETENTION BLANKETS (CL 1) (TY D)
SY 10,000.000 $2.750 $1.500 $1.100 $1.000 $0.830
WILDFLOWER SEEDING
AC 24.000 $1,500.000 $1,200.000 $1,200.000 $1,000.000 $990.000
FL BS (CMP IN PLACE)(TY A GR 1-2)(12")
SY 150,108.000 $23.000 $25.000 $33.500 $34.000 $33.500
LIME (HYDRATED LIME (SLURRY))
TON 2,181.000 $176.000 $300.000 $200.000 $320.000 $350.000
LIME TRT (SUBGRADE)(8")
SY 121,143.000 $3.500 $1.500 $2.000 $3.500 $2.150
CEMENT
TON 2,181.000 $195.000 $250.000 $240.000 $240.000 $270.000
CEMENT TREAT (SUBGRADE) (8")
SY 121,143.000 $2.500 $2.500 $3.600 $2.500 $2.100
PRIME COAT (MC-30)
GAL 45,608.000 $4.700 $5.000 $5.000 $5.500 $5.750
ASPH (AC-20XP, AC-10-2TR, OR AC-20-5TR)
GAL 188,775.000 $3.500 $5.000 $4.700 $3.550 $5.750
AGGR (TY-PD GR-3 OR TY-PL GR-3)
CY 4,496.000 $120.000 $120.000 $145.000 $120.000 $149.500
FLEXIBLE PAVEMENT STRUCTURE REPAIR(6")
SY 1,300.000 $55.000 $60.000 $86.000 $70.000 $90.000
CEM STABIL BKFL
CY 752.000 $100.000 $175.000 $280.000 $250.000 $240.000
CUT & RESTORING PAV
SY 794.000 $90.000 $80.000 $100.000 $125.000 $185.000
FLOWABLE BACKFILL
CY 3,374.000 $120.000 $185.000 $260.000 $250.000 $220.000
TRENCH EXCAVATION PROTECTION
LF 2,999.000 $5.000 $10.000 $12.000 $5.000 $10.500
TEMPORARY SPL SHORING
SF 8,519.000 $20.000 $35.000 $70.000 $38.000 $50.000
FOUNDATON LOADTEST(D4945)(DRILLD SHAFT)
EA 4.000 $20,000.000 $60,000.000 $50,000.000 $20,000.000 $22,000.000
DRILL SHAFT (18 IN)
LF 382.000 $100.000 $185.000 $200.000 $200.000 $205.000
DRILL SHAFT (36 IN)
LF 3,788.000 $225.000 $310.000 $300.000 $285.000 $345.000
CL C CONC (ABUT)(HPC)
CY 133.600 $1,000.000 $1,200.000 $1,100.000 $1,200.000 $1,100.000
CL C CONC (CAP)(HPC)
CY 410.400 $1,000.000 $1,200.000 $1,300.000 $1,200.000 $1,130.000
CL C CONC (COLUMN)(HPC)
CY 179.200 $1,000.000 $1,200.000 $1,300.000 $1,400.000 $1,260.000
CL C CONC (COLLAR)
EA 2.000 $1,000.000 $1,500.000 $2,000.000 $1,500.000 $1,350.000
CL C CONC (MISC)
CY 24.000 $1,000.000 $1,500.000 $800.000 $1,200.000 $830.000
CL E CONC (SEAL SLAB)
CY 119.000 $650.000 $725.000 $550.000 $300.000 $610.000
REINF CONC SLAB
SF 130,000.000 $18.000 $20.000 $26.000 $26.000 $24.500
APPROACH SLAB
CY 122.000 $500.000 $900.000 $750.000 $750.000 $850.000
PRESTR CONC GIRDER (TX54)
LF 16,185.000 $165.000 $220.000 $235.000 $220.000 $220.000
RIPRAP (CONC)(5 IN)
CY 165.000 $550.000 $600.000 $640.000 $650.000 $650.000
RIPRAP (STONE COMMON)(DRY)(12 IN)
CY 16.000 $100.000 $425.000 $190.000 $190.000 $210.000
RIPRAP (STONE COMMON)(DRY)(18 IN)
CY 392.000 $200.000 $145.000 $190.000 $190.000 $180.000
RIPRAP (STONE PROTECTION)(24 IN)
CY 1,862.000 $150.000 $155.000 $150.000 $190.000 $180.000
RIPRAP (STONE PROTECTION)(30 IN)
CY 99.000 $180.000 $190.000 $190.000 $190.000 $185.000
RIPRAP (MOW STRIP)(4 IN)
CY 168.000 $495.000 $575.000 $580.000 $650.000 $675.000
RAIL (TY SSTR)
LF 6,644.000 $50.000 $75.000 $75.000 $115.000 $60.000
SEALED EXPANSION JOINT (4 IN) (SEJ - M)
LF 468.000 $150.000 $190.000 $185.000 $180.000 $215.000
CONC BOX CULV (3 FT X 3 FT)
LF 38.000 $200.000 $270.000 $310.000 $600.000 $370.000
CONC BOX CULV (6 FT X 3 FT)
LF 228.000 $450.000 $515.000 $450.000 $800.000 $570.000
CONC BOX CULV (7 FT X 5 FT)
LF 96.000 $530.000 $650.000 $730.000 $950.000 $750.000
CONC BOX CULV (3 FT X 3 FT)(EXTEND)
LF 82.000 $600.000 $525.000 $360.000 $800.000 $395.000
CONC BOX CULV (10 FT X 5 FT)(EXTEND)
LF 85.000 $1,600.000 $2,000.000 $1,300.000 $1,200.000 $995.000
CONC BOX CULV (10 FT X 8 FT)(EXTEND)
LF 150.000 $1,800.000 $2,100.000 $1,300.000 $1,500.000 $1,925.000
CONC BOX CULV (10 FT X 10 FT)(EXTEND)
LF 54.000 $2,000.000 $2,200.000 $1,600.000 $1,600.000 $1,300.000
RC PIPE (CL III)(18 IN)
LF 7,751.000 $65.000 $60.000 $66.000 $55.000 $50.000
RC PIPE (CL III)(24 IN)
LF 851.000 $80.000 $80.000 $82.000 $75.000 $70.000
RC PIPE (CL III)(30 IN)
LF 592.000 $120.000 $110.000 $101.000 $100.000 $95.000
RC PIPE (CL III)(36 IN)
LF 659.000 $150.000 $145.000 $135.000 $140.000 $135.000
RC PIPE (CL III)(42 IN)
LF 193.000 $180.000 $225.000 $180.000 $200.000 $175.000
RC PIPE (CL III)(48 IN)
LF 429.000 $250.000 $235.000 $230.000 $285.000 $220.000
MANH (COMPL)(PRM)(48IN)
EA 1.000 $5,500.000 $4,800.000 $5,700.000 $6,000.000 $7,880.000
INLET (COMPL)(PCO)(3FT)(NONE)
EA 16.000 $5,000.000 $7,600.000 $6,100.000 $6,000.000 $7,650.000
INLET (COMPL)(PCO)(3FT)(RIGHT)
EA 1.000 $5,500.000 $9,900.000 $6,600.000 $6,000.000 $8,575.000
INLET (COMPL)(PCO)(3FT)(BOTH)
EA 7.000 $5,750.000 $12,200.000 $7,000.000 $6,000.000 $9,500.000
INLET (COMPL)(PSL)(SL)(5FTX5FT)
EA 2.000 $9,100.000 $9,200.000 $6,600.000 $11,000.000 $9,500.000
INLET (COMPL)(PSL)(SL)(6FTX6FT)
EA 1.000 $9,500.000 $14,000.000 $11,000.000 $16,000.000 $15,935.000
INLET (COMPL)(PSL)(SL)(8FTX8FT)
EA 3.000 $10,000.000 $16,000.000 $20,000.000 $20,000.000 $20,620.000
INLET (COMPL)(PSL)(FG)(3FTX3FT-3FTX3FT)
EA 6.000 $5,000.000 $6,700.000 $4,100.000 $7,000.000 $4,310.000
INLET (COMPL)(PSL)(FG)(4FTX4FT-4FTX4FT)
EA 1.000 $6,800.000 $15,000.000 $10,000.000 $16,000.000 $16,725.000
INLET (COMPL)(PSL)(FG)(5FTX5FT-4FTX4FT)
EA 2.000 $11,700.000 $13,500.000 $6,500.000 $12,000.000 $13,260.000
INLET (COMPL)(PSL)(FG)(6FTX6FT-3FTX3FT)
EA 2.000 $7,800.000 $14,000.000 $7,500.000 $12,000.000 $13,100.000
INLET (COMPL)(PSL)(FG)(8FTX8FT-3FTX3FT)
EA 1.000 $12,000.000 $19,000.000 $25,000.000 $21,000.000 $21,810.000
WINGWALL (FW - 0) (HW=4 FT)
EA 1.000 $8,800.000 $16,000.000 $18,000.000 $15,000.000 $6,545.000
WINGWALL (FW - S) (HW=10 FT)
EA 1.000 $37,000.000 $42,000.000 $46,000.000 $30,000.000 $28,650.000
WINGWALL (PW - 1) (HW=10 FT)
EA 3.000 $46,300.000 $87,000.000 $90,000.000 $65,000.000 $52,960.000
WINGWALL (PW - 1) (HW=12 FT)
EA 2.000 $50,000.000 $129,000.000 $100,000.000 $95,000.000 $79,200.000
WINGWALL (PW - 1) (HW=5 FT)
EA 2.000 $16,800.000 $24,000.000 $20,000.000 $20,000.000 $17,100.000
WINGWALL (PW - 1) (HW=6 FT)
EA 2.000 $21,200.000 $25,000.000 $22,000.000 $15,000.000 $17,590.000
WINGWALL (SW - 0) (HW=7 FT)
EA 1.000 $25,000.000 $26,000.000 $22,000.000 $18,000.000 $17,590.000
HEADWALL (CH - PW - 0)(DIA=36 IN)(MOD)
EA 1.000 $7,400.000 $95,000.000 $85,000.000 $67,000.000 $66,890.000
SET (TY I)(S= 6 FT)(HW= 3 FT)(6:1) (C)
EA 1.000 $7,500.000 $9,200.000 $9,100.000 $10,000.000 $10,100.000
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 108.000 $1,000.000 $900.000 $750.000 $700.000 $686.000
SET (TY II) (24 IN) (RCP) (4: 1) (C)
EA 5.000 $1,400.000 $2,300.000 $900.000 $900.000 $1,121.000
SET (TY II) (24 IN) (RCP) (6: 1) (C)
EA 6.000 $2,000.000 $2,600.000 $1,100.000 $1,100.000 $1,232.000
SET (TY II) (30 IN) (RCP) (6: 1) (C)
EA 12.000 $3,000.000 $3,200.000 $2,100.000 $2,000.000 $2,057.000
SET (TY II) (36 IN) (RCP) (4: 1) (C)
EA 3.000 $3,500.000 $4,100.000 $3,600.000 $2,500.000 $4,015.000
SET (TY II) (36 IN) (RCP) (6: 1) (C)
EA 5.000 $4,000.000 $5,000.000 $2,700.000 $3,300.000 $5,145.000
SET (TY II) (42 IN) (RCP) (4: 1) (C)
EA 1.000 $6,050.000 $7,200.000 $5,900.000 $6,000.000 $5,920.000
SET (TY II) (48 IN) (RCP) (4: 1) (C)
EA 2.000 $7,000.000 $7,500.000 $6,700.000 $7,000.000 $6,840.000
SET (TY II) (48 IN) (RCP) (6: 1) (C)
EA 2.000 $10,700.000 $9,800.000 $8,200.000 $10,000.000 $8,675.000
REMOV STR (BOX CULVERT)
EA 2.000 $4,000.000 $7,500.000 $2,500.000 $8,000.000 $8,000.000
REMOV STR (INLET)
EA 2.000 $590.000 $500.000 $1,000.000 $4,500.000 $725.000
REMOV STR (BRIDGE 500 - 999 FT LENGTH)
EA 1.000 $285,000.000 $349,000.000 $670,000.000 $275,000.000 $550,000.000
REMOV STR (PIPE)
EA 67.000 $400.000 $450.000 $660.000 $1,000.000 $1,515.000
REMOVING ROCK RIPRAP
LF 92.000 $1,900.000 $75.000 $30.000 $40.000 $50.000
MOBILIZATION
LS 1.000 $4,367,000.000 $5,400,000.000 $6,100,000.000 $5,600,000.000 $4,500,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 30.000 $8,000.000 $7,500.000 $15,000.000 $15,000.000 $5,200.000
ROCK FILTER DAMS (INSTALL) (TY 1)
LF 815.000 $30.000 $35.000 $31.000 $33.000 $31.900
ROCK FILTER DAMS (INSTALL) (TY 3)
LF 1,500.000 $50.000 $60.000 $42.000 $48.000 $49.500
ROCK FILTER DAMS (REMOVE)
LF 2,315.000 $10.000 $7.000 $11.000 $8.000 $12.100
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 3,500.000 $30.000 $20.000 $15.000 $25.000 $28.600
CONSTRUCTION EXITS (REMOVE)
SY 3,500.000 $10.000 $5.000 $3.000 $8.000 $9.900
EXCAV (EROSN & SEDMT CONT, IN VEH)
CY 5,000.000 $15.000 $20.000 $14.000 $10.000 $15.000
EMBANK (EROSN & SEDMT CONT, IN VEH)
CY 5,000.000 $15.000 $20.000 $21.000 $10.000 $17.000
BACKHOE WORK (EROSION & SEDMT CONT)
HR 1,500.000 $70.000 $80.000 $66.000 $30.000 $71.250
FRNT END LOADER WORK (ERSN & SEDM CONT)
HR 1,200.000 $105.000 $80.000 $100.000 $30.000 $71.250
BULLDOZER WORK (EROSION & SEDMT CONT)
HR 1,200.000 $70.000 $80.000 $110.000 $30.000 $54.200
TEMP SEDMT CONT FENCE (INSTALL)
LF 21,290.000 $2.850 $3.500 $2.500 $3.500 $3.600
TEMP SEDMT CONT FENCE (REMOVE)
LF 21,290.000 $0.700 $0.500 $0.900 $0.650 $0.330
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 590.000 $6.000 $7.000 $4.300 $8.000 $5.500
BIODEG EROSN CONT LOGS (REMOVE)
LF 590.000 $1.500 $1.000 $1.100 $1.000 $1.100
TRACKHOE WORK (EROSION & SEDMT CONT)
HR 1,400.000 $70.000 $80.000 $85.000 $60.000 $176.650
CONSTRUCTING DETOURS
SY 6,176.000 $58.000 $130.000 $105.000 $127.000 $195.000
PORT CTB (FUR & INST)(LOW PROF)(TY 2)
LF 280.000 $75.000 $85.000 $85.000 $75.000 $95.000
PORT CTB (DES SOURCE)(F-SHAPE)(TY 1)
LF 7,500.000 $22.000 $12.000 $25.000 $16.000 $6.150
PORT CTB (DES SOURCE)(LOW PROF)(TY 1)
LF 1,100.000 $14.000 $22.000 $35.000 $15.000 $5.000
PORT CTB (MOVE)(F-SHAPE)(TY 1)
LF 9,960.000 $10.000 $7.000 $16.000 $7.000 $4.000
PORT CTB (MOVE)(LOW PROF)(TY 1)
LF 440.000 $8.000 $19.000 $30.000 $7.000 $3.000
PORT CTB (MOVE)(LOW PROF)(TY 2)
LF 160.000 $8.000 $19.000 $30.000 $7.000 $3.000
PORT CTB (STKPL)(F-SHAPE)(TY 1)
LF 7,500.000 $12.000 $10.000 $22.000 $9.000 $6.150
PORT CTB (STKPL)(LOW PROF)(TY 1)
LF 1,100.000 $10.000 $16.000 $26.000 $9.000 $5.000
PORT CTB (STKPL)(LOW PROF)(TY 2)
LF 280.000 $10.000 $16.000 $26.000 $9.000 $5.000
CONC CURB & GUTTER (TY II)
LF 6,043.000 $28.000 $24.000 $42.000 $50.000 $40.000
DRIVEWAYS (ACP)
SY 7,189.000 $40.000 $40.000 $42.000 $50.000 $56.000
DRIVEWAYS (CONC) (HES)
SY 831.000 $105.000 $95.000 $140.000 $150.000 $128.000
RUMBLE STRIPS (SHOULDER)
LF 71,254.000 $0.200 $0.300 $0.240 $0.350 $0.250
MTL W-BEAM GD FEN (TIM POST)
LF 2,475.000 $28.000 $30.000 $24.000 $25.000 $24.500
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 8.000 $2,000.000 $2,200.000 $1,800.000 $2,100.000 $1,892.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 5.000 $1,600.000 $1,500.000 $1,400.000 $1,400.000 $1,397.000
REMOVE METAL BEAM GUARD FENCE
LF 875.000 $2.200 $3.000 $2.200 $3.000 $2.200
GUARDRAIL END TREATMENT (INSTALL)
EA 9.000 $4,000.000 $3,500.000 $3,200.000 $3,300.000 $3,327.500
GUARDRAIL END TREATMENT (REMOVE)
EA 4.000 $270.000 $250.000 $220.000 $250.000 $220.000
CRASH CUSH ATTEN (MOVE & RESET)
EA 38.000 $1,200.000 $2,500.000 $1,000.000 $3,000.000 $3,025.000
CRASH CUSH ATTEN (REMOVE)
EA 18.000 $870.000 $1,250.000 $700.000 $1,500.000 $1,320.000
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
EA 18.000 $11,800.000 $9,000.000 $8,800.000 $11,000.000 $11,000.000
PIPE UNDERDRAINS (TY 8) (6")
LF 1,000.000 $20.000 $42.000 $46.000 $48.000 $47.500
MAILBOX INSTALL-S (TWG-POST) TY 2
EA 14.000 $270.000 $300.000 $270.000 $325.000 $317.900
MAILBOX INSTALL-D (TWG-POST) TY 2
EA 1.000 $310.000 $500.000 $425.000 $340.000 $355.300
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 75.000 $560.000 $750.000 $710.000 $750.000 $772.200
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 16.000 $680.000 $900.000 $850.000 $900.000 $942.700
IN SM RD SN SUP&AM TY10BWG(1)SA(U)
EA 2.000 $800.000 $1,200.000 $1,000.000 $1,100.000 $1,096.700
IN SM RD SN SUP&AM TYS80(1)SA(P-BM)
EA 3.000 $875.000 $1,100.000 $1,000.000 $1,100.000 $1,051.600
IN SM RD SN SUP&AM TYS80(1)SA(T-2EXT)
EA 2.000 $1,000.000 $1,500.000 $1,400.000 $1,500.000 $1,500.000
IN SM RD SN SUP&AM TYS80(2)SA(P-EXAL)
EA 2.000 $1,500.000 $2,500.000 $2,000.000 $2,300.000 $2,285.800
IN SM RD SN SUP&AM (RAIL MOUNT)
EA 1.000 $3,000.000 $10,000.000 $1,600.000 $8,000.000 $7,298.500
REMOVE SM RD SN SUP&AM
EA 67.000 $90.000 $125.000 $30.000 $105.000 $103.400
INSTL DEL ASSM (D-SW)SZ (BRF)CTB
EA 40.000 $20.000 $40.000 $20.000 $35.000 $26.400
INSTL DEL ASSM (D-SY)SZ (BRF)CTB
EA 40.000 $20.000 $30.000 $20.000 $35.000 $26.400
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2
EA 28.000 $30.000 $40.000 $45.000 $55.000 $37.400
INSTL DEL ASSM (D-SY)SZ 1(BRF)GF2
EA 14.000 $30.000 $40.000 $45.000 $55.000 $37.400
INSTL OM ASSM (OM-2Z)(WFLX)GND
EA 54.000 $80.000 $90.000 $110.000 $85.000 $85.800
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
LF 54,027.000 $0.200 $0.550 $0.530 $0.550 $0.550
WK ZN PAV MRK NON-REMOV (W)24"(SLD)
LF 160.000 $4.000 $6.000 $4.240 $5.000 $4.400
WK ZN PAV MRK NON-REMOV (Y)4"(BRK)
LF 3,108.000 $0.250 $0.550 $0.530 $0.550 $0.550
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
LF 56,654.000 $0.200 $0.550 $0.530 $0.550 $0.550
WK ZN PAV MRK NON-REMOV (Y)24"(SLD)
LF 1,476.000 $3.750 $3.000 $2.650 $2.700 $2.750
WK ZN PAV MRK REMOV (REFL) TY I-C
EA 2,115.000 $3.750 $4.000 $3.500 $3.600 $3.630
WK ZN PAV MRK REMOV (REFL) TY II-A-A
EA 2,472.000 $4.000 $4.000 $3.500 $3.600 $3.630
WK ZN PAV MRK REMOV (TRAF BTN) TY W
EA 6,337.000 $3.000 $4.000 $3.180 $3.300 $3.300
WK ZN PAV MRK REMOV (TRAF BTN) TY Y
EA 7,424.000 $3.000 $4.000 $3.180 $3.300 $3.300
WK ZN PAV MRK REMOV (W)4"(SLD)
LF 3,300.000 $0.600 $1.500 $1.060 $1.100 $1.100
WK ZN PAV MRK REMOV (Y)4"(SLD)
LF 3,300.000 $1.000 $1.500 $1.060 $1.100 $1.100
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 1,212.000 $1.000 $1.500 $2.000 $2.000 $2.000
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 920.000 $1.000 $1.500 $2.000 $2.000 $2.000
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 7,278.000 $0.900 $1.250 $1.060 $1.100 $1.100
REFL PAV MRK TY I (W)12"(SLD)(100MIL)
LF 160.000 $3.000 $4.500 $4.240 $5.000 $4.400
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 262.000 $6.000 $7.000 $6.360 $7.000 $6.600
REF PAV MRK TY I(W)18"(YLD TRI)(100MIL)
EA 104.000 $35.000 $40.000 $37.100 $40.000 $38.500
REFL PAV MRK TY I (Y)24"(SLD)(100MIL)
LF 1,220.000 $5.500 $6.000 $5.830 $6.000 $6.050
PAVEMENT SEALER 4"
LF 7,520.000 $0.100 $0.550 $0.530 $0.550 $0.550
RE PM W/RET REQ TY I (W)4"(BRK)(100MIL)
LF 12,440.000 $0.400 $0.550 $0.530 $0.550 $0.550
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 48,113.000 $0.400 $0.550 $0.530 $0.550 $0.550
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
LF 3,440.000 $0.400 $0.550 $0.530 $0.550 $0.550
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 57,168.000 $0.400 $0.550 $0.530 $0.550 $0.550
PREFAB PAV MRK TY C (W) (ARROW)
EA 45.000 $200.000 $250.000 $212.000 $220.000 $220.000
PREFAB PAV MRK TY C (W) (WORD)
EA 21.000 $270.000 $300.000 $259.700 $260.000 $269.500
REFL PAV MRKR TY I-C
EA 191.000 $4.000 $5.000 $3.920 $4.000 $4.070
REFL PAV MRKR TY II-A-A
EA 661.000 $3.500 $5.000 $3.920 $4.000 $4.070
REFL PAV MRKR TY II-C-R
EA 767.000 $3.500 $5.000 $3.920 $4.000 $4.070
ELIM EXT PAV MRK & MRKS (4")
LF 30,884.000 $0.500 $0.500 $0.420 $0.440 $0.440
PAV SURF PREP FOR MRK (4")
LF 7,520.000 $0.050 $0.400 $0.530 $0.550 $0.550
SP MIXES SP-B PG64-22
TON 35,995.000 $95.000 $102.000 $130.000 $133.000 $123.400
SP MIXES SP-C PG64-22
TON 65,829.000 $90.000 $107.000 $130.000 $137.000 $126.790
SP MIXES SP-C SAC-A PG70-22
TON 8,717.000 $110.000 $122.000 $143.000 $145.000 $134.550
SP MIXES SP-D PG64-22 (LEVEL-UP)
TON 7,686.000 $120.000 $117.000 $143.000 $138.000 $128.820
PFC-C (PG76 MIX) SAC-A
TON 11,042.000 $180.000 $160.000 $160.000 $175.000 $173.250
TACK COAT
GAL 14,724.000 $4.000 $4.500 $4.500 $4.000 $4.500
TIP TESTING(DRILL SHAFT)
EA 6.000 $4,500.000 $4,000.000 $7,500.000 $5,000.000 $3,500.000
ASBESTOS ABATEMENT (OTHER)
SF 400.000 $88.000 $60.000 $58.000 $50.000 $140.000
INSTALL FTB
LF 1,800.000 $45.000 $60.000 $37.000 $65.000 $55.000
REMOVE FTB
LF 1,800.000 $5.000 $15.000 $15.000 $15.000 $13.200
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 400.000 $72.000 $150.000 $100.000 $100.000 $132.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 4.000 $12,000.000 $10,000.000 $15,000.000 $40,000.000 $25,000.000
TMA (STATIONARY)
DAY 945.000 $160.000 $200.000 $80.000 $100.000 $250.000
TMA (MOBILE OPERATION)
DAY 80.000 $160.000 $500.000 $100.000 $100.000 $250.000
Totals: $48,036,548.550 $55,487,305.160 $62,792,646.110 $63,868,868.680 $64,909,504.080