ANDERSON US 287 (0109-02-026)

Items: 44

County: ANDERSON
Length: N/A
Highway: US 287
District: TYLER
Control Number: 0109-02-026
DBE Goal: N/A
Project: STP 2018(809)
Guaranty: N/A
Time: 73 WORKING DAYS
Engineer's Estimate: $4,111,722.55
Date: 05/02/2018 (8 years ago)
Contract Number: N/A
Type: PLNG,ACP,OCST,PFC,PVT MRKG
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (5)
E
Engineer's Estimate
$4,111,722.55
$3,987,345.30
Over/Under Est: -3.02% -$124,377.25
Over/Under Est: 9.82% $403,700.60
Amt Left: 13.24% $528,077.85
Over/Under Est: 11.03% $453,384.96
Amt Left: 14.49% $577,762.21
Delta: -1.10% -$49,684.36
$4,607,866.09
Over/Under Est: 12.07% $496,143.54
Amt Left: 15.56% $620,520.79
Delta: -0.94% -$42,758.58
Over/Under Est: 14.43% $593,432.20
Amt Left: 18% $717,809.45
Delta: -2.11% -$97,288.66

Bid Items & Bid Tabulations

44 Total 0 of 44
ANDERSON  |  US 287  |  TYLER  |  0109-02-026  |  05/02/2018  |  $4,111,722.55  |  STP 2018(809)  |  PLNG,ACP,OCST,PFC,PVT MRKG  |  73 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
BIG CREEK CONSTRUCTION, LTD.
LONGVIEW BRIDGE AND ROAD, LTD.
OLDCASTLE MATERIALS TEXAS, INC.
A. L. HELMCAMP, INC.
EAST TEXAS BRIDGE, INC.
EMBANKMENT (VEHICLE)(ORD COMP)(TY C)
CY 106.000 $30.000 $50.000 $34.000 $50.000 $50.000 $40.000
BACKFILL (TY B)
STA 87.420 $240.000 $150.000 $200.000 $165.000 $165.000 $400.000
BROADCAST SEED (TEMP) (WARM)
SY 451.000 $0.150 $1.500 $1.400 $1.250 $2.000 $1.000
BROADCAST SEED (TEMP) (COOL)
SY 451.000 $0.150 $1.500 $1.400 $1.250 $2.000 $1.000
BOND FBR MTRX SEED (PERM)(RURAL)(SAND)
SY 899.000 $1.200 $2.500 $2.200 $2.000 $5.000 $3.000
VEGETATIVE WATERING
MG 20.000 $20.000 $50.000 $25.000 $45.000 $39.000 $15.000
ASPH (AC-20XP, AC-10-2TR, OR AC-20-5TR)
GAL 56,021.000 $2.750 $3.000 $2.750 $3.509 $3.000 $3.500
AGGR (TY-PD GR-3 OR TY-PL GR-3)
CY 1,270.000 $110.000 $117.000 $118.000 $128.641 $108.000 $145.000
PFC (ASPHALT) PG76-22
TON 433.000 $120.000 $125.000 $140.000 $142.000 $148.000 $135.000
PFC-C (AGGREGATE)(PG76 MIX) SAC-A
TON 6,788.000 $120.000 $125.000 $140.000 $142.000 $148.000 $135.000
SUPERPAVE MIXTURES SP-C PG70-22
TON 21,670.000 $87.000 $90.000 $95.000 $100.000 $104.000 $100.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(3")
SY 5,555.000 $27.000 $22.000 $34.000 $27.000 $24.000 $30.000
PLANE ASPH CONC PAV (0" TO 1 1/2")
SY 1,466.000 $2.500 $4.000 $10.000 $3.100 $2.500 $4.000
PLANE ASPH CONC PAV (5")
SY 78,799.000 $3.000 $3.000 $3.000 $3.100 $3.300 $4.000
RIPRAP (MOW STRIP)(4 IN)
CY 66.000 $525.000 $650.000 $520.000 $485.000 $600.000 $450.000
MOBILIZATION
LS 1.000 $413,000.000 $187,500.000 $440,000.000 $320,705.000 $327,000.000 $350,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 5.000 $5,000.000 $5,000.000 $2,200.000 $14,000.000 $6,100.000 $10,000.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 1,030.000 $3.100 $3.000 $3.250 $2.950 $4.000 $3.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 1,030.000 $1.000 $0.650 $1.100 $1.000 $1.000 $1.000
RUMBLE STRIPS (SHOULDER)
LF 51,400.000 $0.200 $0.200 $0.160 $0.090 $0.170 $0.250
RUMBLE STRIPS (CENTERLINE)
LF 25,175.000 $0.300 $0.200 $0.180 $0.140 $0.170 $0.250
MTL W-BEAM GD FEN (TIM POST)
LF 550.000 $20.000 $30.000 $21.000 $22.000 $20.000 $22.000
REMOVE METAL BEAM GUARD FENCE
LF 350.000 $3.000 $3.000 $5.500 $4.100 $3.000 $4.000
GUARDRAIL END TREATMENT (INSTALL)
EA 8.000 $2,260.000 $2,300.000 $2,775.000 $2,450.000 $2,400.000 $2,500.000
GUARDRAIL END TREATMENT (REMOVE)
EA 8.000 $650.000 $250.000 $440.000 $375.000 $260.000 $250.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2
EA 23.000 $28.000 $25.000 $41.000 $38.000 $25.000 $30.000
WK ZN PAV MRK NON-REMOV (W)4"(BRK)
LF 2,440.000 $0.250 $0.150 $0.160 $0.150 $0.160 $0.200
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
LF 108,800.000 $0.250 $0.150 $0.130 $0.120 $0.130 $0.150
WK ZN PAV MRK NON-REMOV (Y)4"(BRK)
LF 10,600.000 $0.250 $0.150 $0.160 $0.150 $0.160 $0.200
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
LF 51,860.000 $0.200 $0.150 $0.130 $0.120 $0.130 $0.150
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 366.000 $1.000 $1.000 $1.200 $1.000 $1.500 $2.000
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 2,884.000 $0.650 $1.000 $1.200 $1.000 $1.500 $2.000
WK ZN PAV MRK SHT TERM RMV (W)(4")
LF 1,098.000 $0.750 $0.500 $1.400 $1.100 $0.500 $2.000
WK ZN PAV MRK SHT TERM RMV (Y)(4")
LF 16,436.000 $1.000 $0.500 $1.400 $1.200 $0.500 $2.000
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 197.000 $5.400 $6.000 $5.850 $5.300 $5.570 $6.000
RE PM W/RET REQ TY I (W)4"(BRK)(100MIL)
LF 1,220.000 $0.350 $0.460 $0.500 $0.460 $0.480 $0.500
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 54,400.000 $0.350 $0.400 $0.440 $0.400 $0.420 $0.450
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
LF 5,300.000 $0.350 $0.460 $0.500 $0.460 $0.480 $0.500
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 25,930.000 $0.350 $0.420 $0.460 $0.580 $0.440 $0.450
REFL PAV MRKR TY I-C
EA 61.000 $4.000 $3.300 $3.650 $3.300 $3.470 $4.000
REFL PAV MRKR TY II-A-A
EA 3,054.000 $4.000 $3.300 $3.650 $3.300 $3.470 $4.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 14.000 $100.000 $150.000 $100.000 $100.000 $275.000 $200.000
TMA (STATIONARY)
EA 1.000 $8,000.000 $15,000.000 $24,000.000 $14,755.120 $10,000.000 $30,000.000
TMA (STATIONARY)
DAY 30.000 $200.000 $500.000 $200.000 $192.698 $250.000 $300.000
Totals: $4,111,722.550 $3,987,345.300 $4,515,423.150 $4,565,107.519 $4,607,866.090 $4,705,154.750