| Control Number | County | Highway | Bid Date | Low Bidder | Pay Estimates | % of Contract | Amount | % Complete | Contract Amount |
|---|---|---|---|---|---|---|---|---|---|
| 0465-02-027 | BEXAR | FM 1518 | 10/05/2023 | SER CONSTRUCTION PARTNERS, LLC | 04/26 | 03/26 | 02/26 | 01/26 | 12/25 | 0.01% | $7,430.57 | 54.00% | $74,305,687.35 |
| 1685-01-090 | HARRIS | FM 1960 | 08/03/2023 | SER CONSTRUCTION PARTNERS, LLC | 04/26 | 03/26 | 02/26 | 01/26 | 12/25 | 0.04% | $11,589.27 | 102.00% | $28,973,171.76 |
| 0338-04-065 | MONTGOMERY | SH 105 | 10/07/2022 | SER CONSTRUCTION PARTNERS, LLC | 04/26 | 03/26 | 02/26 | 01/26 | 12/25 | 0.01% | $9,152.47 | 100.00% | $91,524,746.93 |
| 0188-10-021 | FORT BEND | FM 1463 | 08/04/2021 | ZACHRY CONSTRUCTION CORPORATION | 05/26 | 04/26 | 03/26 | 02/26 | 01/26 | 0.03% | $33,891.69 | 101.00% | $112,972,296.07 |
| 0912-71-003 | HARRIS | CS | 04/04/2017 | J.D. ABRAMS, L.P. | 08/25 | 07/25 | 06/25 | 05/25 | 04/25 | 0.63% | $92,798.61 | 99.00% | $14,729,937.61 |