TxDOT Subcontracts for MILLER SPRINGS MATERIALS, L.L.C.
| Control Number | County | Highway | Bid Date | Low Bidder | Pay Estimates | % of Contract | Amount | % Complete | Contract Amount |
|---|---|---|---|---|---|---|---|---|---|
| 0320-06-008 | BELL | SL 363 | 02/02/2024 | JAMES CONSTRUCTION GROUP, LLC | 04/26 | 03/26 | 02/26 | 01/26 | 12/25 | 0.73% | $401,381.10 | 96.00% | $54,983,712.46 |
| 2502-01-021 | BELL | SL 121 | 08/05/2021 | JAMES CONSTRUCTION GROUP, LLC | 04/26 | 03/26 | 02/26 | 01/26 | 12/25 | 1.83% | $647,765.10 | 101.00% | $35,397,000.08 |
| 0231-04-060 | BELL | IH 14 | 06/04/2020 | JAMES CONSTRUCTION GROUP, L.L.C. | 11/24 | 10/24 | 09/24 | 08/24 | 07/24 | 0.47% | $185,490.78 | 100.00% | $39,466,124.00 |
