| Control Number | County | Highway | Bid Date | Low Bidder | Pay Estimates | % of Contract | Amount | % Complete | Contract Amount |
|---|---|---|---|---|---|---|---|---|---|
| 0353-02-037 | DENTON | SH 114 | 04/04/2023 | MARIO SINACOLA & SONS EXCAVATING, INC. | 05/26 | 04/26 | 03/26 | 02/26 | 01/26 | 0.32% | $320,043.95 | 98.00% | $100,013,734.81 |
| 0047-04-031 | COLLIN | SH 5 | 12/02/2022 | HARPER BROTHERS CONSTRUCTION LLC | 05/26 | 04/26 | 03/26 | 02/26 | 01/26 | 0.21% | $82,470.21 | 27.00% | $39,271,527.03 |
| 0549-03-024 | COLLIN | SH 121 | 10/01/2020 | MARIO SINACOLA & SONS EXCAVATING, INC. | 12/24 | 11/24 | 10/24 | 09/24 | 08/24 | 0.68% | $621,428.78 | 100.00% | $91,386,585.26 |