| Control Number | County | Highway | Bid Date | Low Bidder | Pay Estimates | % of Contract | Amount | % Complete | Contract Amount |
|---|---|---|---|---|---|---|---|---|---|
| 6479-12-001 | FREESTONE | SH0075 | 02/12/2025 | ABESCAPE GROUP LLC | 04/26 | 03/26 | 02/26 | 01/26 | 12/25 | 0.00% | $0.00 | 85.00% | $276,271.00 |
| 6471-03-001 | NAVARRO | SH0031 | 01/08/2025 | SERNA CONTRACTORS, LLC | 02/26 | 12/25 | 11/25 | 10/25 | 09/25 | 0.00% | $0.00 | 90.00% | $631,956.08 |
| 0207-02-031 | RUSK | SH 43 | 09/05/2024 | MADDEN CONTRACTING COMPANY, LLC. | 04/26 | 03/26 | 02/26 | 01/26 | 12/25 | 0.08% | $17,525.28 | 101.00% | $21,906,598.25 |
| 6452-61-001 | SHELBY | US0059 | 02/01/2024 | SERVIN MOWING | 03/25 | 02/25 | 01/25 | 12/24 | 11/24 | 0.00% | $0.00 | 93.00% | $239,608.18 |
| 6453-72-001 | PANOLA | US0059 | 01/10/2024 | SERVIN MOWING | 11/24 | 09/24 | 08/24 | 07/24 | 06/24 | 100.00% | $178,343.88 | 100.00% | $178,343.88 |
| 0450-01-013 | CHEROKEE | SH 204 | 11/01/2023 | MADDEN CONTRACTING COMPANY, LLC. | 04/26 | 03/26 | 02/26 | 01/26 | 12/25 | 0.14% | $23,678.44 | 97.00% | $16,913,171.00 |
| 0191-01-094 | SMITH | US 69 | 02/02/2023 | DREWERY CONSTRUCTION COMPANY, INCORPORATED | 05/26 | 04/26 | 03/26 | 02/26 | 01/26 | 0.10% | $7,851.49 | 96.00% | $7,851,485.13 |