ZAVALA LA PALOMA (0922-48-004)

Items: 72

County: ZAVALA
Length: 0.0060 MILES
Highway: LA PALOMA
District: LAREDO
Control Number: 0922-48-004
DBE Goal: 0.0%
Project: BR 2B23(188)
Guaranty: $15,000.00
Time: 134 WORKING DAYS
Engineer's Estimate: $1,631,536.66
Date: 04/07/2026 (2 months ago) Changed
Contract Number: 4263230
Type: BRIDGE REPLACEMENT
Project ID: A00186521
Contract Type: Federal
Project Description: REPLACEMENT OF OFF-SYSTEM BRIDGE LA PALOMA RD AT GALLINA SLOUGH CREEK
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
GERARDO M GONZALEZ
ANGEL MARTINEZ
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (5)
E
Engineer's Estimate
$1,631,536.66
$1,523,015.88
Over/Under Est: -6.65% -$108,520.78
Over/Under Est: -2.44% -$39,880.17
Amt Left: 4.51% $68,640.61
Over/Under Est: 11.85% $193,398.96
Amt Left: 19.82% $301,919.74
Delta: -14.66% -$233,279.13
Over/Under Est: 13.83% $225,630.01
Amt Left: 21.94% $334,150.79
Delta: -1.77% -$32,231.05
$2,491,324.58
Over/Under Est: 52.7% $859,787.92
Amt Left: 63.58% $968,308.70
Delta: -34.15% -$634,157.91

Bid Items & Bid Tabulations

72 Total 0 of 72
ZAVALA  |  LA PALOMA  |  LAREDO  |  0922-48-004  |  04/07/2026  |  $1,631,536.66  |  BR 2B23(188)  |  BRIDGE REPL  |  134 WORKING DAYS
Alt
Item Code
Description
Unit
Quantity
Engineer's Estimate
ACEE CONSTRUCTION LLC.
PRESIDIO CONTRACTING, LLC
J. CARROLL WEAVER, INC.
ACME BRIDGE COMPANY, INC.
CK NEWBERRY, LLC
PREPARING ROW
STA 7.000 $3,500.000 $2,250.000 $9,615.000 $1,761.130 $3,310.000 $5,000.000
TREE PROTECTION (INSTALL)
EA 6.000 $450.000 $315.250 $705.000 $1,110.000 $1,060.000 $1,000.000
TREE PROTECTION (REMOVE)
EA 6.000 $120.000 $150.350 $215.000 $888.000 $318.000 $500.000
REMOV CONC (FLUME)
SY 266.000 $75.000 $39.900 $25.250 $19.730 $20.900 $35.000
EXCAV (ROADWAY)
CY 341.996 $35.000 $25.000 $58.150 $41.920 $44.000 $125.000
EXCAV (CHANNEL)
CY 310.400 $30.000 $25.000 $59.600 $34.640 $39.700 $100.000
EMBANK (FNL)(OC)(TY A)
CY 484.403 $45.000 $35.000 $26.600 $14.640 $60.000 $60.000
BACKFILL (TY B)
STA 4.000 $150.000 $264.600 $1,500.000 $1,218.640 $332.000 $2,000.000
BLADING
HR 24.000 $100.000 $55.000 $65.000 $101.550 $100.000 $200.000
DRILL SEED (PERM_RURAL_CLAY)
AC 0.850 $1,500.000 $5,061.000 $5,230.000 $5,350.200 $5,114.480 $6,000.000
DRILL SEED (TEMP_WARM)
AC 0.850 $1,500.000 $4,368.000 $4,515.000 $4,617.600 $4,414.150 $6,000.000
PROOF ROLLING
HR 16.000 $120.000 $38.500 $25.000 $76.170 $107.000 $100.000
FL BS (CMP IN PLC)(TYA GR1-2)(FNAL POS)
CY 337.000 $160.000 $125.000 $125.600 $115.420 $127.000 $200.000
PRIME COAT (MC-30)
GAL 404.370 $18.000 $21.150 $13.000 $11.310 $12.300 $20.000
D-GR HMA TY-C SAC-A PG76-22
TON 222.300 $160.000 $250.000 $310.000 $366.750 $298.000 $300.000
CEM STABIL BKFL
CY 28.000 $250.000 $145.000 $300.000 $330.250 $436.000 $400.000
FLOWABLE BACKFILL
CY 25.000 $350.000 $145.000 $345.000 $428.200 $405.000 $500.000
TEMPORARY SPL SHORING
SF 600.000 $80.000 $18.000 $7.000 $20.410 $1.050 $30.000
APPROACH SLAB
CY 38.500 $665.000 $1,195.800 $932.000 $943.260 $1,090.000 $1,500.000
RIPRAP (CONC)(4 IN)
CY 20.000 $300.000 $580.000 $670.000 $760.260 $873.000 $800.000
RIPRAP (MOW STRIP)(4 IN)
CY 46.000 $650.000 $580.000 $690.000 $832.490 $921.000 $900.000
RIPRAP (STONE PROTECTION)(12 IN)
CY 98.000 $210.000 $210.000 $250.000 $200.830 $500.000 $325.000
REMOV STR (PIPE)
LF 216.000 $100.000 $17.350 $72.000 $24.300 $15.700 $100.000
REMOV STR (BRIDGE 0 - 99 FT LENGTH)
EA 1.000 $25,000.000 $12,500.000 $25,750.000 $73,514.570 $10,000.000 $75,000.000
REMOVE STR (GABION)
LF 80.000 $20.000 $11.750 $60.000 $65.620 $34.000 $100.000
MOBILIZATION
LS 1.000 $125,230.000 $152,000.000 $154,785.000 $173,033.850 $168,000.000 $225,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 8.000 $10,000.000 $3,950.000 $4,135.000 $2,775.000 $2,000.000 $10,000.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 4.000 $10,000.000 $12,500.000 $6,500.000 $6,105.000 $18,000.000 $10,000.000
ROCK FILTER DAMS (INSTALL) (TY 4)
LF 200.000 $50.000 $67.200 $69.450 $67.000 $67.900 $25.000
ROCK FILTER DAMS (REMOVE)
LF 200.000 $12.000 $16.500 $17.000 $11.100 $16.700 $12.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 233.000 $30.000 $30.800 $32.000 $22.200 $31.100 $30.000
CONSTRUCTION EXITS (REMOVE)
SY 233.000 $10.000 $10.350 $10.000 $8.880 $10.400 $12.000
BACKHOE WORK (EROSION & SEDMT CONT)
HR 40.000 $75.000 $40.000 $125.000 $60.930 $167.000 $100.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 800.000 $3.500 $6.300 $6.500 $7.640 $6.400 $12.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 800.000 $1.500 $2.100 $2.150 $4.260 $2.100 $6.000
CONSTRUCTING DETOURS (TY1)
SY 715.000 $150.000 $55.000 $54.750 $120.310 $114.000 $100.000
CONSTRUCTING DETOURS (TY2)
SY 949.000 $150.000 $70.000 $44.250 $95.320 $138.000 $80.000
ONE-WAY TRAF CONT (FLAGGER CONT)
HR 80.000 $100.000 $147.000 $75.000 $63.330 $100.000 $60.000
ONE-WAY TRAF CONT (PORT TRAF SIG)
MO 5.000 $5,000.000 $7,644.000 $5,140.000 $4,059.110 $4,190.000 $10,000.000
PORT CTB (FUR & INST)(LOW PROF)(TY 1)
LF 360.000 $35.000 $33.600 $31.400 $30.290 $37.100 $60.000
PORT CTB (FUR & INST)(LOW PROF)(TY 2)
LF 160.000 $40.000 $31.650 $31.400 $30.290 $30.600 $110.000
PORT CTB (REMOVE)(LOW PROF)(TY 1)
LF 360.000 $20.000 $25.300 $17.550 $30.290 $37.000 $60.000
PORT CTB (REMOVE)(LOW PROF)(TY 2)
LF 160.000 $25.000 $21.950 $17.550 $30.290 $31.600 $100.000
CONC CURB (TY III)
LF 36.000 $100.000 $13.500 $265.000 $84.440 $96.500 $200.000
MTL W-BEAM GD FEN (TIM POST)
LF 314.000 $35.000 $29.950 $31.000 $33.380 $31.800 $60.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 2.000 $1,500.000 $1,725.150 $1,780.000 $2,740.270 $1,700.000 $1,500.000
GUARDRAIL END TREATMENT (INSTALL)
EA 6.000 $3,500.000 $3,888.150 $4,020.000 $5,037.210 $3,710.000 $4,000.000
WIRE FENCE (TY C)
LF 520.000 $15.000 $58.800 $30.000 $27.750 $15.900 $40.000
WIRE FENCE (WATER GAP)
LF 40.000 $50.000 $269.500 $105.000 $333.000 $37.100 $120.000
WIRE FENCE (REMOVE)
LF 560.000 $10.000 $7.850 $5.000 $11.100 $5.300 $20.000
REMOVE SM RD SN SUP&AM (SIGN ONLY)
EA 4.000 $100.000 $98.000 $100.000 $194.250 $106.000 $600.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 38.000 $50.000 $117.600 $27.000 $84.360 $31.800 $75.000
INSTL OM ASSM (OM-2Z)(WFLX)(WAP)
EA 6.000 $150.000 $352.800 $163.000 $138.750 $79.600 $75.000
WK ZN PAV MRK REMOV (Y)6"(SLD)
LF 6,000.000 $2.000 $1.950 $0.900 $0.720 $0.450 $2.000
WK ZN PAV MRK SHT TERM (TAB)TY Y
EA 150.000 $2.000 $2.650 $5.300 $2.220 $1.850 $1.000
TY I HIGH PERF PM (Y)6"(SLD)(100MIL)
LF 2,000.000 $2.000 $4.750 $2.150 $2.220 $2.050 $3.000
REFL PAV MRKR TY II-A-A
EA 50.000 $5.000 $15.700 $27.500 $8.880 $26.500 $30.000
PRECAST C-SPAN CULVERTS
LF 34.000 $4,000.000 $3,350.000 $5,400.000 $6,262.710 $8,000.000 $8,750.000
1
LRA PAV TY-I GR-A
TON 96.000 $160.000 $210.000 $475.000 $157.790 $459.000 $225.000
1
DRILL SHAFT (24 IN)
LF 742.000 $240.000 $285.000 $301.100 $428.820 $295.000 $500.000
1
CL C CONC (ABUT)
CY 105.600 $1,250.000 $1,461.850 $1,060.000 $998.120 $1,090.000 $2,250.000
1
REINF CONC SLAB (SLAB BEAM)
SF 1,040.000 $35.000 $27.950 $26.850 $54.900 $41.600 $60.000
1
PRESTR CONC SLAB BEAM (5SB15)
LF 197.500 $325.000 $429.050 $322.000 $361.130 $439.000 $325.000
1
RAIL (TY T631)
LF 140.000 $110.000 $102.550 $110.000 $181.410 $130.000 $250.000
1
ARMOR JOINT (SEALED)
LF 44.000 $100.000 $208.050 $200.000 $105.450 $264.000 $250.000
1A
ASPH (AC-15P)
GAL 0.000 $274.400 $0.000 $0.000 $0.000 $0.000 $0.000
1A
LRA PAV TY-I GR-A
TON 0.000 $160.000 $0.000 $0.000 $0.000 $0.000 $0.000
1A
DRILL SHAFT (24 IN)
LF 0.000 $240.000 $0.000 $0.000 $0.000 $0.000 $0.000
1A
DRILL SHAFT (30 IN)
LF 0.000 $394.000 $0.000 $0.000 $0.000 $0.000 $0.000
1A
CL C CONC (ABUT)
CY 0.000 $1,250.000 $0.000 $0.000 $0.000 $0.000 $0.000
1A
PRESTR CONC DECK SLAB BEAM (6DS20)
LF 0.000 $318.000 $0.000 $0.000 $0.000 $0.000 $0.000
1A
RAIL (TY T631)
LF 0.000 $110.000 $0.000 $0.000 $0.000 $0.000 $0.000
Totals: $1,631,536.655 $1,523,015.866 $1,591,656.487 $1,824,935.615 $1,857,166.670 $2,491,324.580
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) $1,000.00
LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (PART) $50,000.00
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) $28,500.00
Total: $79,500.00