YOUNG FM 1769 (1711-01-029)

Items: 63

County: YOUNG
Length: N/A
Highway: FM 1769
District: WICHITA FALLS
Control Number: 1711-01-029
DBE Goal: N/A
Project: STP 2017(404)
Guaranty: N/A
Time: 153 WORKING DAYS
Engineer's Estimate: $3,913,381.48
Date: 12/06/2017 (8 years ago)
Contract Number: N/A
Type: REHAB, WIDEN & OVERLAY
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (5)
E
Engineer's Estimate
$3,913,381.48
$3,310,004.48
Over/Under Est: -15.42% -$603,377.00
Over/Under Est: -6.15% -$240,806.83
Amt Left: 10.95% $362,570.17
$3,874,197.54
Over/Under Est: -1% -$39,183.94
Amt Left: 17.05% $564,193.06
Delta: -5.49% -$201,622.89
Over/Under Est: 5.93% $232,186.26
Amt Left: 25.24% $835,563.26
Delta: -7.00% -$271,370.20
$4,669,765.71
Over/Under Est: 19.33% $756,384.23
Amt Left: 41.08% $1,359,761.23
Delta: -12.64% -$524,197.97

Bid Items & Bid Tabulations

63 Total 0 of 63
YOUNG  |  FM 1769  |  WICHITA FALLS  |  1711-01-029  |  12/06/2017  |  $3,913,381.48  |  STP 2017(404)  |  REHAB, WIDEN & OVERLAY  |  153 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
JAGOE-PUBLIC COMPANY
THE LANE CONSTRUCTION CORPORATION
A. L. HELMCAMP, INC.
JAY MILLS CONTRACTING, INCORPORATED
DUININCK, INC.
PREPARING ROW
STA 10.000 $2,500.000 $3,250.000 $1,200.000 $3,000.000 $1,100.000 $3,100.000
EXCAVATION (ROADWAY)
CY 2,114.000 $20.000 $14.500 $39.000 $30.000 $16.000 $52.000
EMBANKMENT (FINAL)(DENS CONT)(TY B)
CY 6,653.000 $15.000 $15.000 $29.000 $18.000 $30.000 $65.500
BROADCAST SEED (TEMP) (WARM)
SY 46,853.000 $0.120 $0.050 $0.050 $0.040 $0.090 $0.050
BROADCAST SEED (TEMP) (COOL)
SY 46,853.000 $0.120 $0.070 $0.060 $0.040 $0.090 $0.060
DRILL SEEDING (PERM) (RURAL) (CLAY)
SY 93,706.000 $0.180 $0.080 $0.070 $0.100 $0.120 $0.080
VEGETATIVE WATERING
MG 794.000 $20.000 $32.000 $32.000 $10.000 $20.000 $27.500
CEMENT
TON 338.000 $160.000 $138.750 $175.000 $160.000 $145.000 $170.000
CEMENT TREAT (SUBGRADE) (8")
SY 37,072.000 $3.000 $2.390 $5.500 $4.700 $3.500 $5.400
PRIME COAT (MC-30)
GAL 11,134.000 $5.000 $3.650 $3.400 $2.800 $4.000 $4.200
D-GR HMA TY-B PG64-22
TON 7,148.000 $60.000 $58.500 $55.000 $69.000 $72.000 $70.000
D-GR HMA TY-D PG70-22
TON 14,426.000 $70.000 $70.250 $73.000 $82.000 $79.800 $82.500
D-GR HMA TY-D PG 70-22 (LEVEL-UP)
TON 7,528.000 $75.000 $73.250 $73.000 $79.000 $80.600 $78.500
FLEXIBLE PAVEMENT STRUCTURE REPAIR(6")
SY 10,308.000 $50.000 $27.000 $27.500 $26.000 $30.800 $35.500
PLAN & TEXT ASPH CONC PAV(0" TO 4")
SY 2,448.000 $4.000 $5.400 $5.500 $3.500 $3.850 $5.550
RIPRAP (MOW STRIP)(4 IN)
CY 39.000 $450.000 $565.000 $685.000 $480.000 $600.000 $485.000
RETROFIT RAIL (TY T131RC)
LF 190.000 $130.000 $180.000 $135.000 $210.000 $206.000 $145.000
CMP (GAL STL 12 IN)
LF 84.000 $100.000 $41.250 $70.000 $38.000 $45.000 $37.500
CMP (GAL STL 18 IN)
LF 86.000 $120.000 $48.500 $84.500 $70.000 $55.000 $70.000
CMP (GAL STL 30 IN)
LF 103.000 $150.000 $54.500 $116.000 $95.000 $70.000 $97.000
SET (TY II) (12 IN) (CMP) (6: 1) (P)
EA 8.000 $1,200.000 $675.000 $850.000 $800.000 $800.000 $805.000
SET (TY II) (18 IN) (CMP) (6: 1) (P)
EA 8.000 $1,400.000 $850.000 $965.000 $1,000.000 $900.000 $1,000.000
SET (TY II) (21 IN) (CMP) (6: 1) (P)
EA 2.000 $1,600.000 $1,000.000 $1,175.000 $1,200.000 $1,050.000 $1,200.000
SET (TY II) (24 IN) (CMP) (6: 1) (P)
EA 4.000 $2,000.000 $1,025.000 $1,200.000 $1,400.000 $1,100.000 $1,400.000
SET (TY II) (30 IN) (CMP) (6: 1) (P)
EA 6.000 $2,500.000 $1,850.000 $1,750.000 $3,200.000 $1,400.000 $3,200.000
REMOV STR (PIPE)
LF 260.000 $20.000 $13.500 $20.000 $11.000 $13.000 $11.000
MOBILIZATION
LS 1.000 $353,922.680 $250,000.000 $165,000.000 $310,000.000 $400,000.000 $360,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 9.000 $6,000.000 $2,800.000 $19,000.000 $8,000.000 $14,000.000 $26,000.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 200.000 $30.000 $26.500 $20.750 $25.000 $40.000 $22.500
ROCK FILTER DAMS (REMOVE)
LF 200.000 $10.000 $21.000 $10.000 $5.000 $15.000 $11.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 4,000.000 $2.500 $2.250 $2.150 $2.600 $2.500 $2.300
TEMP SEDMT CONT FENCE (REMOVE)
LF 4,000.000 $0.800 $0.480 $0.450 $0.200 $1.000 $0.480
BIODEG EROSN CONT LOGS (INSTL) (8")
LF 3,000.000 $3.500 $1.800 $1.700 $3.000 $5.000 $1.800
BIODEG EROSN CONT LOGS (REMOVE)
LF 3,000.000 $0.800 $0.370 $0.350 $0.300 $1.000 $0.380
DRIVEWAYS (CONC)
SY 57.000 $70.000 $64.000 $140.000 $100.000 $86.000 $97.000
DRIVEWAYS (ACP)
SY 1,104.000 $45.000 $11.000 $27.500 $35.000 $33.250 $49.500
TURNOUTS (ACP)
SY 1,329.000 $45.000 $24.500 $40.000 $33.000 $45.000 $37.000
DRIVEWAYS (BASE)
SY 4,133.000 $22.000 $11.250 $14.000 $18.000 $14.000 $21.000
RUMBLE STRIPS (CENTERLINE)
LF 42,080.000 $0.250 $0.110 $0.210 $0.250 $0.500 $0.170
MTL W-BEAM GD FEN (TIM POST)
LF 300.000 $17.000 $19.000 $18.000 $21.000 $30.000 $19.500
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 4.000 $1,500.000 $1,590.000 $1,500.000 $1,800.000 $2,500.000 $1,600.000
REMOVE METAL BEAM GUARD FENCE
LF 400.000 $3.000 $8.500 $8.000 $2.500 $3.000 $8.600
GUARDRAIL END TREATMENT (INSTALL)
EA 4.000 $2,200.000 $2,325.000 $2,200.000 $2,200.000 $2,750.000 $2,400.000
MAILBOX INSTALL-S (TWW-POST) TY 4
EA 19.000 $200.000 $212.000 $225.000 $210.000 $310.000 $240.000
MAILBOX INSTALL-D (TWW-POST) TY 4
EA 3.000 $250.000 $237.000 $270.000 $240.000 $310.000 $290.000
MAILBOX INSTALL-M (TWW-POST) TY 4
EA 2.000 $500.000 $531.000 $590.000 $530.000 $625.000 $635.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 2.000 $600.000 $531.000 $465.000 $530.000 $500.000 $500.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 10.000 $600.000 $531.000 $525.000 $530.000 $550.000 $565.000
RELOCATE SM RD SN SUP&AM TY 10BWG
EA 6.000 $400.000 $450.000 $395.000 $450.000 $400.000 $425.000
RELOCATE SM RD SN SUP&AM TY TWT
EA 15.000 $400.000 $318.000 $235.000 $320.000 $350.000 $255.000
REMOVE SM RD SN SUP&AM
EA 12.000 $100.000 $68.500 $60.000 $100.000 $100.000 $64.500
INSTL DEL ASSM (D-SW)SZ 1(FLX)GND(BI)
EA 32.000 $65.000 $48.000 $110.000 $48.000 $75.000 $120.000
INSTL DEL ASSM (D-SW)SZ (BRF)GF1 (BI)
EA 12.000 $50.000 $16.000 $15.000 $16.000 $50.000 $27.000
INSTL OM ASSM (OM-2Z)(FLX)GND
EA 30.000 $70.000 $48.000 $110.000 $48.000 $70.000 $120.000
WK ZN PAV MRK NON-REMOV (Y)4"(BRK)
LF 18,340.000 $0.200 $0.270 $0.240 $0.240 $0.540 $0.280
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
LF 66,800.000 $0.200 $0.270 $0.210 $0.210 $0.540 $0.280
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 4,427.000 $1.000 $0.750 $1.000 $0.800 $1.240 $1.100
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 84,180.000 $0.400 $0.370 $0.330 $0.330 $0.330 $0.330
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
LF 9,170.000 $0.400 $0.370 $0.400 $0.330 $0.350 $0.330
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 33,400.000 $0.400 $0.370 $0.330 $0.330 $0.330 $0.330
PREFAB PAV MRK TY C (W) (24") (SLD)
LF 54.000 $15.000 $17.000 $11.000 $30.000 $16.500 $27.000
REFL PAV MRKR TY II-A-A
EA 882.000 $4.000 $3.180 $3.500 $3.700 $6.600 $3.500
ELIM EXT PAV MRK & MRKS (4")
LF 42,570.000 $1.000 $0.670 $0.100 $0.300 $0.550 $0.770
Totals: $3,913,381.480 $3,310,004.480 $3,672,574.650 $3,874,197.540 $4,145,567.740 $4,669,765.710