YOUNG FM 1287 (1293-01-024)

Items: 90

County: YOUNG
Length: N/A
Highway: FM 1287
District: WICHITA FALLS
Control Number: 1293-01-024
DBE Goal: 0.0%
Project: STP 2B24(219)HRR
Guaranty: N/A
Time: 386 WORKING DAYS
Engineer's Estimate: $5,747,702.50
Date: 07/10/2024 (1 year ago)
Contract Number: N/A
Type: HAZARD ELIMINATION & SAFETY
Mail/Deliver Bids To: N/A
ZACHARY HUSEN
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (4)
E
Engineer's Estimate
$5,747,702.50
$6,394,017.85
Over/Under Est: 11.24% $646,315.35
$7,327,223.30
Over/Under Est: 27.48% $1,579,520.80
Amt Left: 14.59% $933,205.45
Over/Under Est: 35.2% $2,022,948.13
Amt Left: 21.53% $1,376,632.78
Delta: -6.05% -$443,427.33
$8,142,282.49
Over/Under Est: 41.66% $2,394,579.99
Amt Left: 27.34% $1,748,264.64
Delta: -4.78% -$371,631.86
Subcontractor Percentage Amount
W. S. CONSTRUCTION COMPANY 17.47% $1,132,618.22
HJC FARMS, INC. 1.80% $116,697.93
TRP CONSTRUCTION GROUP, LLC 1.69% $109,566.39
BARRICADES UNLIMITED 0.92% $59,645.61
WOLFE CONSTRUCTION GROUP, INCORPORATED 0.53% $34,361.06
DUSTROL, INC. 0.36% $23,339.59
Total: 22.77% $1,476,228.80

Bid Items & Bid Tabulations

90 Total 0 of 90
YOUNG  |  FM 1287  |  WICHITA FALLS  |  1293-01-024  |  07/10/2024  |  $5,747,702.50  |  STP 2B24(219)HRR  |  HAZARD ELIM & SAFETY  |  386 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
ZACK BURKETT CO.
A. L. HELMCAMP, INC.
EUROVIA ATLANTIC COAST LLC
DUININCK, INC.
EXCAVATION (ROADWAY)
CY 3,995.000 $35.000 $30.810 $53.000 $50.000 $68.000
EXCAVATION (CHANNEL)
CY 98.000 $50.000 $75.000 $100.000 $155.000 $150.000
EMBANKMENT (FINAL)(DENS CONT)(TY B)
CY 3,157.000 $50.000 $61.000 $92.000 $69.000 $68.000
BACKFILL (TY B)
STA 11.000 $195.000 $350.000 $1,000.000 $1,100.000 $590.000
BROADCAST SEED (TEMP) (WARM)
SY 42,394.000 $0.150 $0.160 $0.100 $0.140 $0.170
BROADCAST SEED (TEMP) (COOL)
SY 42,394.000 $0.150 $0.190 $0.120 $0.140 $0.190
DRILL SEEDING (PERM) (RURAL) (SANDY)
SY 84,774.000 $0.150 $0.140 $0.130 $0.180 $0.150
VEGETATIVE WATERING
MG 714.900 $20.000 $50.000 $25.000 $95.000 $42.500
CEMENT
TON 593.000 $280.000 $283.000 $300.000 $280.000 $295.000
CEMENT TREAT (SUBGRADE) (8")
SY 41,536.000 $6.500 $8.000 $7.000 $6.000 $7.350
PRIME COAT (MC-30)
GAL 10,387.000 $10.000 $5.900 $11.000 $7.000 $5.800
EMULS ASPH (PRIME)(MS-2 OR SS-1)
GAL 10,543.000 $3.500 $4.000 $6.000 $4.000 $4.550
FLEXIBLE PAVEMENT STRUCTURE REPAIR(5")
SY 3,644.000 $50.000 $52.000 $95.000 $61.000 $68.500
PLAN & TEXT ASPH CONC PAV(0" TO 2")
SY 1,156.000 $5.000 $5.000 $14.000 $5.000 $15.500
CEM STABIL BKFL
CY 281.000 $75.000 $351.000 $240.000 $285.000 $345.000
CUT & RESTORE ASPH PAVING
SY 251.000 $115.000 $64.350 $72.000 $285.000 $150.000
FLOWABLE BACKFILL
CY 10.000 $225.000 $351.000 $280.000 $650.000 $785.000
TRENCH EXCAVATION PROTECTION
LF 367.000 $2.500 $29.250 $12.000 $1.000 $1.200
TEMPORARY SPL SHORING
SF 398.000 $30.000 $64.350 $56.000 $50.000 $60.500
CL A CONC (PLUG)
EA 2.000 $1,500.000 $2,925.000 $1,700.000 $1,500.000 $1,800.000
CL C CONC (COLLAR)
EA 1.000 $1,000.000 $2,925.000 $2,300.000 $3,000.000 $3,600.000
RIPRAP (STONE PROTECTION)(18 IN)
CY 109.000 $130.000 $200.000 $120.000 $260.000 $255.000
RIPRAP (MOW STRIP)(4 IN)
CY 15.000 $525.000 $877.500 $940.000 $1,010.000 $785.000
CONC BOX CULV (5 FT X 4 FT)
LF 75.000 $350.000 $789.750 $830.000 $450.000 $545.000
RC PIPE (CL III)(24 IN)
LF 140.000 $75.000 $140.400 $94.000 $65.450 $85.000
RC PIPE (CL III)(30 IN)
LF 56.000 $115.000 $169.650 $105.000 $93.530 $115.000
RC PIPE (CL III)(36 IN)
LF 345.000 $145.000 $245.700 $160.000 $136.100 $170.000
RC PIPE (CL III)(48 IN)
LF 168.000 $175.000 $409.500 $270.000 $263.880 $325.000
RC PIPE (CL III)(60 IN)
LF 56.000 $400.000 $643.500 $460.000 $393.640 $495.000
HEADWALL (CH - PW - 0) (DIA= 30 IN)
EA 2.000 $6,500.000 $9,477.000 $6,500.000 $6,000.000 $7,300.000
HEADWALL (CH - PW - 0) (DIA= 36 IN)
EA 8.000 $7,500.000 $11,992.500 $9,400.000 $8,500.000 $10,500.000
HEADWALL (CH - PW - 0) (DIA= 48 IN)
EA 6.000 $9,500.000 $18,720.000 $16,000.000 $15,000.000 $18,000.000
HEADWALL (CH - PW - 0) (DIA= 54 IN)
EA 2.000 $10,000.000 $21,937.500 $21,000.000 $16,500.000 $20,000.000
HEADWALL (CH - PW - 0) (DIA= 60 IN)
EA 2.000 $12,500.000 $25,740.000 $27,000.000 $19,500.000 $23,500.000
WINGWALL (PW - 2) (HW=6 FT)
EA 2.000 $13,500.000 $31,005.000 $28,000.000 $28,000.000 $34,000.000
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 62.000 $1,000.000 $2,047.500 $1,150.000 $1,400.000 $1,700.000
SET (TY II) (24 IN) (RCP) (4: 1) (C)
EA 6.000 $1,500.000 $2,076.750 $1,300.000 $1,435.000 $1,800.000
SET (TY II) (24 IN) (RCP) (6: 1) (P)
EA 24.000 $1,500.000 $2,632.500 $1,300.000 $1,763.000 $2,200.000
SET (TY II) (30 IN) (RCP) (6: 1) (P)
EA 4.000 $2,500.000 $4,680.000 $2,700.000 $3,108.000 $4,200.000
SET (TY II) (48 IN) (RCP) (3: 1) (C)
EA 6.000 $4,500.000 $2,632.500 $5,000.000 $5,500.000 $7,300.000
REMOV & RE - LAY PIPE (54 IN)
LF 6.000 $100.000 $468.000 $170.000 $600.000 $725.000
REMOV STR (SET)
EA 4.000 $1,000.000 $1,170.000 $830.000 $125.000 $150.000
REMOV STR (PIPE)
LF 1,961.000 $25.000 $14.040 $25.000 $10.000 $18.000
MOBILIZATION
LS 1.000 $500,000.000 $400,000.000 $529,000.000 $565,000.000 $800,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 23.000 $5,500.000 $4,810.000 $8,260.000 $30,000.000 $21,500.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 40.000 $60.000 $45.630 $75.000 $50.000 $47.000
ROCK FILTER DAMS (REMOVE)
LF 40.000 $15.000 $20.000 $36.000 $20.000 $18.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 610.000 $2.000 $5.850 $4.600 $4.150 $6.050
TEMP SEDMT CONT FENCE (REMOVE)
LF 610.000 $0.500 $1.170 $2.100 $1.000 $1.200
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 1,275.000 $4.000 $4.680 $4.800 $4.250 $4.850
BIODEG EROSN CONT LOGS (REMOVE)
LF 1,275.000 $1.000 $1.170 $1.700 $1.000 $1.200
DRIVEWAYS (ACP)
SY 550.000 $50.000 $50.000 $70.000 $60.000 $88.000
TURNOUTS (ACP)
SY 511.000 $60.000 $50.000 $71.000 $100.000 $110.000
DRIVEWAYS (BASE)
SY 4,985.000 $25.000 $28.000 $22.000 $35.000 $29.000
RUMBLE STRIPS (SHOULDER) ASPHALT
LF 76,060.000 $0.240 $0.290 $0.290 $0.200 $0.090
RUMBLE STRIPS (CENTERLINE) ASPHALT
LF 38,030.000 $0.300 $0.290 $0.290 $0.250 $0.100
MTL W-BEAM GD FEN (TIM POST)
LF 225.000 $25.000 $35.100 $33.000 $30.000 $36.500
TRANSITION ADJUSTMENT
EA 2.000 $1,850.000 $4,095.000 $1,350.000 $3,500.000 $1,500.000
REMOVE METAL BEAM GUARD FENCE
LF 125.000 $2.500 $11.700 $12.000 $10.000 $12.000
GUARDRAIL END TREATMENT (INSTALL)
EA 2.000 $2,800.000 $5,265.000 $4,200.000 $4,500.000 $4,500.000
GUARDRAIL END TREATMENT (REMOVE)
EA 2.000 $500.000 $585.000 $560.000 $500.000 $605.000
MAILBOX INSTALL-S (TWW-POST) TY 4
EA 39.000 $300.000 $468.000 $450.000 $400.000 $480.000
MAILBOX INSTALL-D (TWW-POST) TY 4
EA 7.000 $350.000 $585.000 $560.000 $500.000 $510.000
MAILBOX INSTALL-M (TWW-POST) TY 4
EA 4.000 $575.000 $1,053.000 $1,000.000 $900.000 $1,100.000
IN SM RD SN SUP&AM TYS80(1)SA(T)
EA 2.000 $575.000 $1,521.000 $1,500.000 $1,300.000 $1,400.000
IN SM RD SN SUP&AM TYS80(1)SA(T-EXAL)
EA 2.000 $1,000.000 $1,755.000 $1,700.000 $1,500.000 $1,400.000
IN SM RD SN SUP&AM TYS80(1)SA(U)
EA 4.000 $900.000 $1,755.000 $1,700.000 $1,500.000 $1,400.000
IN SM RD SN SUP&AM TYTWT(1)WS(P)
EA 38.000 $375.000 $819.000 $780.000 $700.000 $720.000
IN SM RD SN SUP&AM TYTWT(1)WS(T)
EA 5.000 $475.000 $877.500 $830.000 $750.000 $775.000
REMOVE SM RD SN SUP&AM
EA 52.000 $100.000 $117.000 $120.000 $100.000 $120.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 6.000 $50.000 $46.800 $40.000 $40.000 $39.000
INSTL DEL ASSM (D-SW)SZ 1(WFLX)GND(BI)
EA 27.000 $100.000 $175.500 $170.000 $150.000 $57.000
INSTL OM ASSM (OM-2Z)(WFLX)GND(BI)
EA 38.000 $85.000 $175.500 $170.000 $150.000 $63.000
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 4,778.000 $1.000 $1.200 $0.750 $3.000 $1.800
RE PM W/RET REQ TY I (W)6"(SLD)(100MIL)
LF 76,300.000 $0.550 $0.800 $0.600 $0.680 $0.700
RE PM W/RET REQ TY I (Y)6"(BRK)(100MIL)
LF 7,990.000 $0.550 $0.800 $0.650 $0.680 $0.740
RE PM W/RET REQ TY I (Y)6"(SLD)(100MIL)
LF 27,576.000 $0.550 $0.800 $0.600 $0.680 $0.700
PREFAB PAV MRK TY C (W) (24") (SLD)
LF 45.000 $15.000 $17.550 $13.000 $15.000 $14.500
REFL PAV MRKR TY II-A-A
EA 876.000 $2.500 $5.850 $4.300 $5.000 $4.700
TREE REMOVAL (12" - 18" DIA)
EA 12.000 $2,500.000 $1,000.000 $1,000.000 $1,500.000 $1,250.000
TREE TRIMMING AND BRUSH REMOVAL
LF 2,455.000 $3.000 $5.000 $10.000 $20.000 $15.000
D-GR HMA TY-B PG64-22
TON 8,676.000 $100.000 $105.000 $135.000 $130.000 $140.000
D-GR HMA TY-D PG64-22 (LEVEL-UP)
TON 713.000 $200.000 $135.000 $190.000 $165.000 $205.000
D-GR HMA TY-D SAC-B PG70-28
TON 14,971.000 $115.000 $118.000 $144.000 $150.000 $150.000
BONDING COURSE
GAL 10,929.000 $7.000 $5.850 $5.500 $3.000 $4.000
THERMOPLASTIC PIPE(30 IN)(PP)(TYPE III)
LF 56.000 $175.000 $140.400 $100.000 $90.000 $110.000
THERMOPLASTIC PIPE(24 IN)(PP)(TYPE III)
LF 310.000 $100.000 $117.000 $90.000 $62.000 $75.000
THERMOPLASTIC PIPE(18 IN)(PP)(TYPE III)
LF 780.000 $75.000 $105.300 $85.000 $52.000 $63.000
TMA (STATIONARY)
DAY 400.000 $175.000 $275.000 $150.000 $410.000 $305.000
TMA (MOBILE OPERATION)
DAY 6.000 $200.000 $1.000 $400.000 $1,200.000 $1,500.000
Totals: $5,747,702.500 $6,394,017.850 $7,327,223.300 $7,770,650.630 $8,142,282.490