YOUNG FM 701 (0570-03-019)

Items: 73

County: YOUNG
Length: N/A
Highway: FM 701
District: WICHITA FALLS
Control Number: 0570-03-019
DBE Goal: N/A
Project: BR 2023(333)
Guaranty: N/A
Time: 336 WORKING DAYS
Engineer's Estimate: $6,563,411.13
Date: 01/06/2023 (3 years ago)
Contract Number: N/A
Type: BRIDGE REPLACEMENT
Mail/Deliver Bids To: N/A
ZACHARY HUSEN
ANTHONY BOUCHER
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (5)
E
Engineer's Estimate
$6,563,411.13
$7,845,445.00
Over/Under Est: 19.53% $1,282,033.87
Over/Under Est: 28.35% $1,860,818.27
Amt Left: 7.38% $578,784.40
Over/Under Est: 37.08% $2,433,752.02
Amt Left: 14.68% $1,151,718.15
Delta: -6.80% -$572,933.75
$9,737,977.60
Over/Under Est: 48.37% $3,174,566.47
Amt Left: 24.12% $1,892,532.60
Delta: -8.23% -$740,814.45
$11,161,121.31
Over/Under Est: 70.05% $4,597,710.18
Amt Left: 42.26% $3,315,676.31
Delta: -14.61% -$1,423,143.71
Subcontractor Percentage Amount
PEACHTREE CONSTRUCTION, LTD. 7.80% $615,466.41
WYLIE DRILLING & DRAINAGE, INC. 6.26% $493,951.25
ODUM SERVICES, LLC 1.30% $102,577.74
S & S BRIDGE PAINTING, INC. 0.77% $60,757.58
WOLFE CONSTRUCTION GROUP, INCORPORATED 0.63% $49,710.75
HERMANOS STEEL, LLC 0.54% $42,609.21
KING GEORGE TRAFFIC SOLUTIONS LLC 0.32% $25,249.90
TORO BRAVO CONSTRUCTION, LLC 0.21% $16,570.25
PENHALL COMPANY 0.13% $10,257.77
FC TRAFFIC CONTROL, INC. 0.03% $2,367.18
Total: 17.99% $1,419,518.04

Bid Items & Bid Tabulations

73 Total 0 of 73
YOUNG  |  FM 701  |  WICHITA FALLS  |  0570-03-019  |  01/06/2023  |  $6,563,411.13  |  BR 2023(333)  |  BRIDGE REPL  |  336 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
INDUS ROAD & BRIDGE, INC.
HODGES AND SON CONSTRUCTION COMPANY, INC.
COPPELL CONSTRUCTION CO., INC.
EARTH BUILDERS, L.P.
ALTUS CONSTRUCTION LLC
PREPARING ROW
STA 37.000 $4,000.000 $8,072.020 $4,000.000 $3,000.000 $6,000.000 $13,246.220
REMOVING CONC (RIPRAP)
SY 2,905.000 $15.000 $25.000 $10.000 $10.000 $15.000 $10.970
EXCAVATION (ROADWAY)
CY 1,595.000 $10.900 $22.000 $20.000 $33.000 $30.000 $11.110
EXCAVATION (CHANNEL)
CY 469.000 $16.000 $36.000 $20.000 $50.000 $30.000 $25.200
EMBANKMENT (FINAL)(DENS CONT)(TY B)
CY 4,193.000 $12.000 $40.000 $25.000 $44.000 $30.000 $12.330
DRILL SEEDING (PERM) (RURAL) (SANDY)
AC 1.352 $530.000 $5,000.000 $2,000.000 $1,465.000 $1,600.000 $1,149.300
DRILL SEEDING (TEMP)(WARM OR COOL)
AC 1.352 $430.000 $5,000.000 $2,000.000 $1,410.000 $1,600.000 $751.060
VEGETATIVE WATERING
MG 54.000 $27.000 $255.000 $1.000 $40.000 $100.000 $132.460
SOIL RETENTION BLANKETS (CL 1) (TY A)
SY 6,031.000 $1.750 $1.500 $3.000 $2.100 $3.000 $1.250
CEMENT
TON 108.000 $170.000 $300.000 $300.000 $285.000 $280.000 $264.050
CEMENT TREAT (SUBGRADE) (8")
SY 9,836.000 $3.000 $5.000 $10.000 $10.000 $10.000 $3.140
PRIME COAT (MC-30)
GAL 2,460.000 $5.500 $8.000 $10.000 $7.000 $7.000 $9.270
CEM STABIL BKFL
CY 590.000 $162.000 $200.000 $250.000 $273.000 $240.000 $149.470
TEMPORARY SPL SHORING
SF 1,125.000 $23.000 $40.000 $45.000 $70.000 $25.000 $29.220
DRILL SHAFT (18 IN)
LF 392.000 $140.000 $155.000 $145.000 $86.000 $120.000 $357.780
DRILL SHAFT (36 IN)
LF 1,224.000 $250.000 $280.000 $275.000 $287.000 $280.000 $517.040
DRILL SHAFT (48 IN)
LF 465.000 $400.000 $500.000 $500.000 $532.000 $490.000 $991.020
CL C CONC (ABUT)(HPC)
CY 199.600 $1,250.000 $800.000 $1,000.000 $1,450.000 $1,800.000 $1,433.780
CL C CONC (CAP)(HPC)
CY 105.500 $1,500.000 $1,300.000 $1,000.000 $1,550.000 $2,000.000 $2,339.160
CL C CONC (COLUMN)(HPC)
CY 154.000 $1,200.000 $1,100.000 $1,200.000 $1,300.000 $2,000.000 $1,372.530
CL C CONC (HEADWALL)
CY 44.000 $1,000.000 $1,000.000 $1,600.000 $1,550.000 $1,500.000 $1,252.700
REINF CONC SLAB (HPC)
SF 36,040.000 $22.000 $24.000 $25.000 $32.250 $32.000 $45.460
BRIDGE SIDEWALK (HPC)
SF 3,249.000 $11.750 $12.000 $15.000 $17.500 $18.000 $13.640
APPROACH SLAB (HPC)
CY 203.300 $675.000 $700.000 $1,000.000 $700.000 $850.000 $3,597.800
PRESTR CONC GIRDER (TX54)
LF 4,309.660 $190.000 $265.000 $340.000 $420.000 $280.000 $323.800
PENETRATING CONCRETE SURFACE TREATMENT
SY 226.400 $9.000 $30.000 $40.000 $25.000 $30.000 $33.120
RIPRAP (STONE COMMON)(DRY)(8 IN)
CY 821.000 $93.490 $174.000 $145.000 $142.000 $110.000 $107.290
RIPRAP (STONE PROTECTION)(18 IN)
CY 2,943.000 $147.000 $122.000 $145.000 $135.000 $135.000 $202.950
RIPRAP (MOW STRIP)(4 IN)
CY 134.000 $525.000 $500.000 $600.000 $975.000 $550.000 $563.930
STR STEEL (MISCELLANEOUS BRIDGE)
LB 168.000 $15.000 $30.000 $100.000 $24.000 $18.000 $17.880
RAIL (TY T223)(HPC)
LF 1,733.000 $155.000 $165.000 $150.000 $200.000 $150.000 $174.890
RAIL (TY C223)(HPC)
LF 397.000 $200.000 $220.000 $150.000 $250.000 $180.000 $238.430
SEALED EXPANSION JOINT (4 IN) (SEJ - M)
LF 234.000 $175.000 $190.000 $170.000 $235.000 $220.000 $199.940
GABIONS (3' X 3')(GALV)
CY 20.000 $265.000 $365.000 $300.000 $400.000 $300.000 $365.720
RC PIPE (CL III)(24 IN)
LF 45.000 $92.000 $155.000 $100.000 $160.000 $125.000 $132.340
HEADWALL (CH - PW - 0) (DIA= 42 IN)
EA 1.000 $9,000.000 $10,500.000 $70,000.000 $10,500.000 $6,000.000 $12,364.560
SET (TY II) (24 IN) (RCP) (4: 1) (C)
EA 1.000 $1,700.000 $2,500.000 $5,000.000 $3,200.000 $1,200.000 $2,318.090
SET (TY II) (24 IN) (RCP) (6: 1) (P)
EA 2.000 $1,400.000 $3,000.000 $5,000.000 $3,450.000 $1,500.000 $3,001.590
REMOV STR (BRIDGE 100 - 499 FT LENGTH)
EA 3.000 $150,000.000 $84,000.000 $300,000.000 $220,000.000 $600,000.000 $249,348.960
REMOV STR (RAILROAD CROSSING)
EA 1.000 $5,000.000 $10,000.000 $2,000.000 $14,500.000 $1,500.000 $11,921.590
MOBILIZATION
LS 1.000 $593,698.000 $780,000.000 $700,000.000 $842,000.000 $1,000,000.000 $1,072,943.430
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 19.000 $7,200.000 $12,000.000 $5,000.000 $2,200.000 $3,000.000 $15,895.460
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 80.000 $35.000 $46.000 $1.000 $35.000 $50.000 $40.260
ROCK FILTER DAMS (REMOVE)
LF 80.000 $11.500 $17.000 $1.000 $20.000 $10.000 $13.260
TEMP SEDMT CONT FENCE (INSTALL)
LF 6,769.000 $2.800 $5.000 $1.000 $3.400 $3.700 $4.070
TEMP SEDMT CONT FENCE (REMOVE)
LF 6,769.000 $0.800 $1.000 $1.000 $1.250 $1.300 $0.970
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 160.000 $5.000 $7.000 $5.000 $8.500 $9.500 $6.030
BIODEG EROSN CONT LOGS (REMOVE)
LF 160.000 $1.000 $1.000 $1.000 $1.250 $1.250 $1.800
DRIVEWAYS (BASE)
SY 414.000 $20.000 $150.000 $65.000 $45.000 $25.000 $27.780
MTL W-BEAM GD FEN (TIM POST)
LF 1,826.000 $28.000 $32.000 $25.000 $22.000 $30.000 $31.950
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 8.000 $1,900.000 $2,400.000 $1,600.000 $2,000.000 $1,800.000 $2,681.210
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 2.000 $1,300.000 $2,100.000 $1,500.000 $1,450.000 $1,500.000 $1,738.860
MTL BM GD FEN TRANS (NON - SYM)
EA 3.000 $1,200.000 $1,200.000 $1,000.000 $950.000 $900.000 $1,238.680
REMOVE METAL BEAM GUARD FENCE
LF 775.000 $2.600 $5.000 $1.000 $2.500 $5.000 $2.890
REMOVE TERMINAL ANCHOR SECTION
EA 12.000 $275.000 $200.000 $400.000 $150.000 $400.000 $285.080
GUARDRAIL END TREATMENT (INSTALL)
EA 9.000 $3,250.000 $3,700.000 $3,000.000 $2,950.000 $3,000.000 $4,015.860
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
EA 1.000 $9,375.000 $9,300.100 $12,000.000 $10,375.000 $11,000.000 $11,544.010
WIRE FENCE (TY C)
LF 155.000 $18.000 $30.000 $20.000 $20.000 $18.000 $19.660
IN SM RD SN SUP&AM TYTWT(1)UA(P)
EA 9.000 $525.000 $776.000 $850.000 $725.000 $650.000 $761.660
IN SM RD SN SUP&AM TYTWT(1)UA(T)
EA 4.000 $580.000 $900.000 $850.000 $750.000 $800.000 $960.350
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
EA 24.000 $30.000 $29.000 $20.000 $15.000 $25.000 $33.120
REMOVE DELIN & OBJECT MARKER ASSMS
EA 12.000 $28.000 $38.000 $20.000 $20.000 $5.000 $196.870
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2
EA 34.000 $39.000 $89.000 $40.000 $40.000 $55.000 $99.350
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 7,572.000 $0.300 $1.000 $1.250 $1.000 $1.300 $1.180
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 7,572.000 $0.310 $1.000 $1.250 $1.000 $1.300 $1.180
REFL PAV MRKR TY II-A-A
EA 96.000 $3.200 $8.000 $15.000 $5.000 $12.000 $7.950
PAV SURF PREP FOR MRK (4")
LF 4,324.000 $0.100 $0.740 $1.500 $1.000 $1.300 $0.730
D-GR HMA TY-B PG64-22
TON 3,246.000 $100.000 $180.000 $150.000 $128.000 $135.000 $169.550
D-GR HMA TY-D SAC-B PG64-22
TON 1,083.000 $300.000 $180.000 $160.000 $143.000 $145.000 $189.420
INSTALL BRIDGE IDENTIFICATION NUMBERS
EA 6.000 $350.000 $500.000 $500.000 $500.000 $500.000 $876.000
INSTALL FTB
LF 735.000 $100.000 $80.000 $60.000 $125.000 $80.000 $76.170
REMOVE FTB
LF 735.000 $16.000 $20.000 $20.000 $12.000 $5.000 $33.770
PORTABLE CHANGEABLE MESSAGE SIGN
EA 4.000 $10,000.000 $45,000.000 $50,000.000 $12,500.000 $20,000.000 $8,610.040
Totals: $6,563,411.130 $7,845,445.000 $8,424,229.400 $8,997,163.150 $9,737,977.600 $11,161,121.341