Show Job Controls
Bid Cobra

WOOD US0080 (6493-93-001)

Items: 32

County: WOOD
Length: 0.0100 MILES
Highway: US0080
District: TYLER
Control Number: 6493-93-001
DBE Goal: 0.0%
Project: RMC - A00218435
Guaranty: $6,000.00
Time: 730 CALENDAR DAYS
Engineer's Estimate: $318,875.00
Date: 05/12/2026 (30 days ago)
Contract Number: 5261001
Type: METAL BEAM GUARD FENCE REPAIR
Project ID: A00218435
Project Description: FOR THE PURPOSE OF REPAIRING GUARDRAIL.
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: MAINTENANCE CONTRACT OFFICE
2709 W FRONT ST, TYLER, TX 75702
LANCE POMYKAL
MANUEL Y ENRIQUEZ
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (1)
E
Engineer's Estimate
$318,875.00
1
$330,480.00
Over/Under Est: 3.64% $11,605.00

Bid Items & Bid Tabulations

32 Total 0 of 32
WOOD  |  US0080  |  TYLER  |  6493-93-001  |  05/12/2026  |  $318,875.00  |  RMC - A00218435  |  METAL BEAM GUARD FENCE REPAIR  |  730 CALENDAR DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
CATOCON, INC.
CONC STR REPAIR(DECK REP(PART DEPTH))
SF 30.000 $150.000 $100.000
CONC STR REPAIR(DECK REP (FULL DEPTH))
SF 30.000 $200.000 $100.000
CONC STR REPAIR (VERTICAL & OVERHEAD)
SF 30.000 $250.000 $100.000
CONC STR REPAIR (STANDARD)
SF 30.000 $200.000 $100.000
RIPRAP (MOW STRIP)(4 IN)
CY 10.000 $700.000 $500.000
MOBILIZATION (CALLOUT)
EA 25.000 $1,000.000 $1.000
TMA (STATIONARY)
DAY 50.000 $300.000 $40.000
MTL W-BEAM GD FEN (TIM POST)
LF 400.000 $30.000 $40.000
MTL W-BEAM GD FEN ADJUSTMENT
LF 200.000 $5.000 $5.000
TRANSITION ADJUSTMENT
EA 5.000 $875.000 $1.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 5.000 $1,600.000 $1,500.000
REMOVE METAL BEAM GUARD FENCE
LF 700.000 $4.000 $2.000
REPLACE RAIL ELEMENT (W-BEAM)
LF 2,500.000 $25.000 $40.000
REPLACE RAIL ELEMENT (THRIE-BEAM)
LF 25.000 $35.000 $40.000
REPL RAIL ELMNT(THRIE-BM TRANS TO W-BM)
EA 10.000 $100.000 $400.000
REPLACE TIMBER POST W/O CONC FND
EA 100.000 $60.000 $50.000
REPLACE TIMBER POST W/ CONC FND
EA 25.000 $85.000 $100.000
REPLACE STEEL POST W/ CONC FND
EA 25.000 $90.000 $100.000
REALIGN POSTS
EA 110.000 $20.000 $20.000
REPLACE TERMINAL ANCHOR POSTS
EA 5.000 $50.000 $50.000
REM OBSOLETE GET & REPL W/ SGT
EA 25.000 $4,000.000 $5,000.000
REPL SINGLE GDRAIL TERM IMPACT HEAD
EA 8.000 $1,000.000 $1,300.000
REPLACE SINGLE GDRAIL TERMINAL RAIL
LF 300.000 $40.000 $40.000
REPLACE SINGLE GDRAIL TERMINAL POST
EA 20.000 $120.000 $200.000
REPLACE BLOCKOUT
EA 100.000 $35.000 $35.000
REPAIR STEEL POST WITH BASE PLATE
EA 10.000 $100.000 $250.000
RESET SGT IMPACT HEAD
EA 12.000 $200.000 $100.000
REPLACE SGT OBJECT MARKER
EA 5.000 $40.000 $100.000
REPLACE SGT CABLE ANCHOR
EA 5.000 $80.000 $100.000
REPLACE SGT CABLE ASSEMBLY
EA 5.000 $80.000 $100.000
REPLACE SGT STRUT
EA 5.000 $190.000 $100.000
REPAIR (STEEL POST W/CHANNEL IRON RAIL)
LF 75.000 $150.000 $100.000
Totals: $318,875.000 $330,480.000