WOOD FM2422 (6386-51-001)

Items: 30

County: WOOD
Length: N/A
Highway: FM2422
District: TYLER
Control Number: 6386-51-001
DBE Goal: N/A
Project: RMC - 638651001
Guaranty: N/A
Time: 60 W
Engineer's Estimate: $380,538.50
Date: 06/02/2023 (3 years ago)
Contract Number: N/A
Type: CULVERT REPAIR
Mail/Deliver Bids To: N/A
LANCE POMYKAL
JOSH FULTON
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (9)
E
Engineer's Estimate
$380,538.50
1
$375,135.26
Over/Under Est: -1.42% -$5,403.24
Over/Under Est: -0.54% -$2,041.54
Amt Left: 0.9% $3,361.70
Over/Under Est: 11.91% $45,309.50
Amt Left: 13.52% $50,712.74
Delta: -12.51% -$47,351.04
Over/Under Est: 14.49% $55,121.50
Amt Left: 16.13% $60,524.74
Delta: -2.30% -$9,812.00
Over/Under Est: 26.67% $101,478.50
Amt Left: 28.49% $106,881.74
Delta: -10.64% -$46,357.00
Over/Under Est: 29.27% $111,390.50
Amt Left: 31.13% $116,793.74
Delta: -2.06% -$9,912.00
Over/Under Est: 30.63% $116,558.50
Amt Left: 32.51% $121,961.74
Delta: -1.05% -$5,168.00
Over/Under Est: 31.04% $118,111.50
Amt Left: 32.93% $123,514.74
Delta: -0.31% -$1,553.00
Over/Under Est: 35.66% $135,711.50
Amt Left: 37.62% $141,114.74
Delta: -3.53% -$17,600.00

Bid Items & Bid Tabulations

30 Total 0 of 30
WOOD  |  FM2422  |  TYLER  |  6386-51-001  |  06/02/2023  |  $380,538.50  |  RMC - 638651001  |  CULVERT REPAIR  |  60 W
Item Code
Description
Unit
Quantity
Engineer's Estimate
3LW CIVIL LLC
RED BARON BUILDING COMPANY, LLC
TRUE ROADS CONSTRUCTION, LLC
BECK-REIT & SONS, LTD.
ENCINO LANDSCAPE, INC.
CROSS PLUS CONSTRUCTION, LLC
SJ&J CONSTRUCTION, LLC
SHALOM SERVICES CORPORATION
HIGHWAY 19 CONSTRUCTION LLC
PREPARING ROW(OPT1)
STA 2.000 $1,100.000 $2,500.000 $500.000 $4,000.000 $1,500.000 $5,000.000 $5,500.000 $5,500.000 $4,000.000 $1,000.000
EMBANKMENT (VEHICLE)(ORD COMP)(TY C)
CY 843.000 $25.000 $32.000 $22.000 $26.000 $25.000 $40.000 $44.000 $40.000 $60.000 $50.000
BOND FBR MTRX SEED (PERM)(RURAL)(SAND)
SY 1,700.000 $1.250 $0.750 $2.000 $4.000 $2.000 $2.000 $6.000 $1.500 $2.000 $5.000
VEGETATIVE WATERING
MG 18.700 $75.000 $1.000 $5.000 $50.000 $100.000 $10.000 $110.000 $10.000 $200.000 $100.000
CEM STABIL BKFL
CY 70.000 $200.000 $250.000 $250.000 $400.000 $300.000 $250.000 $275.000 $220.000 $190.000 $300.000
CUT & RESTORING PAV
SY 115.000 $200.000 $185.000 $175.000 $200.000 $250.000 $200.000 $330.000 $150.000 $900.000 $250.000
FLOWABLE BACKFILL
CY 19.000 $225.000 $500.000 $250.000 $575.000 $350.000 $1,000.000 $275.000 $220.000 $650.000 $250.000
RIPRAP (CONC)(5 IN)
CY 6.000 $550.000 $800.000 $500.000 $1,000.000 $1,000.000 $500.000 $220.000 $1,000.000 $700.000 $1,000.000
RIPRAP (STONE PROTECTION)(18 IN)
CY 20.000 $250.000 $186.570 $200.000 $300.000 $444.000 $250.000 $220.000 $250.000 $190.000 $250.000
RIPRAP (STONE PROTECTION)(24 IN)
CY 272.000 $250.000 $151.500 $225.000 $225.000 $355.000 $250.000 $220.000 $250.000 $200.000 $200.000
CONC BOX CULV (4 FT X 2 FT)
LF 128.000 $500.000 $287.450 $600.000 $475.000 $588.000 $500.000 $550.000 $750.000 $400.000 $700.000
CONC BOX CULV (5 FT X 5 FT)(EXTEND)
LF 40.000 $600.000 $780.850 $1,137.170 $500.000 $1,222.000 $800.000 $550.000 $1,000.000 $700.000 $850.000
RC PIPE (CL III)(24 IN)
LF 80.000 $130.000 $134.330 $180.000 $125.000 $400.000 $180.000 $330.000 $120.000 $190.000 $100.000
WINGWALL (FW - 0) (HW=3 FT)
EA 2.000 $10,000.000 $32,500.000 $10,500.000 $10,000.000 $6,000.000 $11,000.000 $7,700.000 $12,000.000 $6,500.000 $7,500.000
WINGWALL (FW - 0) (HW=6 FT)
EA 1.000 $15,000.000 $16,800.000 $15,768.000 $14,000.000 $8,000.000 $12,000.000 $14,300.000 $15,000.000 $9,000.000 $9,500.000
WINGWALL (PW - 2) (HW=3 FT)
EA 2.000 $12,000.000 $1,000.000 $11,216.330 $11,000.000 $6,000.000 $10,000.000 $7,700.000 $13,000.000 $5,000.000 $7,500.000
SET (TY II) (24 IN) (RCP) (4: 1) (C)
EA 4.000 $1,000.000 $1,784.240 $2,500.000 $1,500.000 $3,000.000 $2,000.000 $5,500.000 $1,800.000 $1,500.000 $1,000.000
REMOV STR (WINGWALL)
EA 3.000 $1,650.000 $750.000 $2,000.000 $2,000.000 $500.000 $2,500.000 $1,100.000 $1,200.000 $1,000.000 $1,000.000
REMOV STR (PIPE)
LF 190.000 $35.000 $23.680 $50.000 $60.000 $30.000 $40.000 $1.000 $30.000 $5.000 $50.000
MOBILIZATION (CALLOUT)
EA 10.000 $3,500.000 $1.000 $1.000 $100.000 $1.000 $4,000.000 $3,300.000 $5,000.000 $5,000.000 $10,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 4.000 $2,500.000 $13,750.000 $1,500.000 $12,500.000 $2,500.000 $5,000.000 $5,500.000 $8,000.000 $5,000.000 $5,000.000
ROCK FILTER DAMS (INSTALL) (TY 1)
LF 25.000 $25.000 $45.000 $30.000 $120.000 $50.000 $100.000 $55.000 $8.000 $60.000 $45.000
ROCK FILTER DAMS (REMOVE)
LF 25.000 $10.000 $25.000 $20.000 $30.000 $10.000 $10.000 $6.000 $4.000 $20.000 $10.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 400.000 $2.000 $3.500 $4.500 $8.000 $1.000 $10.000 $17.000 $4.000 $1.000 $5.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 400.000 $1.000 $1.000 $2.000 $1.000 $1.000 $1.000 $1.000 $1.000 $1.000 $1.000
INSTL OM ASSM (OM-2Z)(WFLX)GND
EA 9.000 $34.000 $20.000 $50.000 $75.000 $80.000 $40.000 $165.000 $90.000 $150.000 $45.000
DITCH CLEANING AND RESHAPING (FOOT)
LF 640.000 $5.250 $13.000 $8.000 $18.000 $28.000 $15.000 $28.000 $10.000 $12.000 $10.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 51.000 $120.000 $1.000 $65.000 $75.000 $1.000 $500.000 $275.000 $200.000 $100.000 $150.000
TMA (STATIONARY)
DAY 30.000 $200.000 $1.000 $75.000 $200.000 $1.000 $300.000 $550.000 $150.000 $600.000 $500.000
INST/REMV WKZN SPEED REDUCTION SIGNS
EA 1.000 $300.000 $250.000 $2,500.000 $2,500.000 $100.000 $100.000 $550.000 $500.000 $100.000 $1,000.000
Totals: $380,538.500 $375,135.260 $378,496.960 $425,848.000 $435,660.000 $482,017.000 $491,929.000 $497,097.000 $498,650.000 $516,250.000