WOOD SL 564 (3240-01-019)
Items: 75
County: WOOD
Length: N/A
Highway: SL 564
District: TYLER
Control Number: 3240-01-019
DBE Goal: N/A
Project: STP 2019(323)
Guaranty: N/A
Time: 101 WORKING DAYS
Engineer's Estimate: $5,870,279.89
Date: 01/09/2019 (7 years ago)
Contract Number: N/A
Type: PLANING,PVMT RPR,ACP,OCST,PFS,MBGF,PV MK
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Bidders (4)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$5,870,279.89 | |||
| $5,773,806.79 |
-1.64%
-$96,473.10
|
|||
| $5,844,679.33 |
-0.44%
-$25,600.56
|
1.23%
$70,872.54
|
||
| $5,865,375.76 |
-0.08%
-$4,904.13
|
1.59%
$91,568.97
|
-0.35%
-$20,696.43
|
|
| $6,250,538.20 |
6.48%
$380,258.31
|
8.26%
$476,731.41
|
-6.57%
-$385,162.44
|
E
Engineer's Estimate
$5,870,279.89
1
Awarded
$5,773,806.79
Over/Under Est:
-1.64%
-$96,473.10
$5,844,679.33
Over/Under Est:
-0.44%
-$25,600.56
Amt Left:
1.23%
$70,872.54
$5,865,375.76
Over/Under Est:
-0.08%
-$4,904.13
Amt Left:
1.59%
$91,568.97
Delta:
-0.35%
-$20,696.43
$6,250,538.20
Over/Under Est:
6.48%
$380,258.31
Amt Left:
8.26%
$476,731.41
Delta:
-6.57%
-$385,162.44
Bid Items & Bid Tabulations
75
Total
0 of 75