WOOD FM 14 (0492-03-036)

Items: 71

County: WOOD
Length: N/A
Highway: FM 14
District: TYLER
Control Number: 0492-03-036
DBE Goal: N/A
Project: STP 2020(615)
Guaranty: N/A
Time: 95 WORKING DAYS
Engineer's Estimate: $4,674,054.40
Date: 03/05/2020 (6 years ago)
Contract Number: N/A
Type: REPAIR & RESURFACE ROADWAY
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (4)
E
Engineer's Estimate
$4,674,054.40
$4,511,805.59
Over/Under Est: -3.47% -$162,248.81
Over/Under Est: 5.93% $277,307.97
Amt Left: 9.74% $439,556.78
$4,955,117.68
Over/Under Est: 6.01% $281,063.28
Amt Left: 9.83% $443,312.09
Delta: -0.08% -$3,755.31
Over/Under Est: 17.26% $806,613.56
Amt Left: 21.47% $968,862.37
Delta: -10.61% -$525,550.28

Bid Items & Bid Tabulations

71 Total 0 of 71
WOOD  |  FM 14  |  TYLER  |  0492-03-036  |  03/05/2020  |  $4,674,054.40  |  STP 2020(615)  |  REPAIR & RESURF ROADWAY  |  95 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
EAST TEXAS BRIDGE, INC.
LONGVIEW BRIDGE AND ROAD, LTD.
WE BUILD, INC.
TEXAS MATERIALS GROUP, INC.
REMOVING CONC (CURB AND GUTTER)
LF 200.000 $20.000 $8.000 $12.000 $14.150 $48.900
REMOVING CONCRETE(MOW STRIP)
LF 418.000 $15.000 $9.000 $12.000 $7.500 $30.680
EMBANKMENT (VEHICLE)(ORD COMP)(TY C)
CY 1,300.000 $30.000 $15.000 $13.500 $30.400 $24.950
BACKFILL (TY A)
STA 65.950 $300.000 $250.000 $200.000 $341.550 $615.400
FURNISHING AND PLACING TOPSOIL (4")
SY 2,444.000 $1.000 $1.250 $3.250 $3.150 $8.750
BOND FBR MTRX SEED (PERM)(RURAL)(SAND)
SY 8,307.000 $0.800 $1.000 $0.820 $0.850 $0.860
VEGETATIVE WATERING
MG 91.380 $10.000 $12.000 $10.000 $587.550 $108.750
FLEXIBLE PAVEMENT STRUCTURE REPAIR(6")
SY 5,000.000 $55.000 $50.000 $57.000 $47.350 $57.750
PLANE ASPH CONC PAV (1.5")
SY 11,953.000 $2.000 $3.500 $2.150 $2.550 $3.700
PLANE ASPH CONC PAV (4")
SY 123,849.000 $4.000 $3.000 $2.150 $1.600 $3.980
RIPRAP (MOW STRIP)(4 IN)
CY 62.000 $500.000 $450.000 $540.000 $384.200 $540.300
CLEANING AND SEALING EXIST JOINTS(CL3)
LF 792.000 $40.000 $25.000 $34.500 $17.500 $22.750
HEADER TYPE EXPANSION JOINT
CF 26.000 $400.000 $700.000 $650.000 $578.200 $739.360
JOINT SEALANT
LF 308.000 $20.000 $20.000 $16.500 $49.000 $15.920
MOBILIZATION
LS 1.000 $425,000.000 $200,000.000 $415,000.000 $486,165.000 $378,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 6.000 $5,000.000 $10,000.000 $3,400.000 $19,257.000 $44,227.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 40.000 $35.000 $45.000 $40.000 $38.900 $48.910
ROCK FILTER DAMS (REMOVE)
LF 40.000 $10.000 $10.000 $11.000 $21.750 $11.380
EARTHWORK (EROSN & SEDMT CONT, IN VEH)
CY 80.000 $25.000 $40.000 $32.000 $27.450 $31.430
BACKHOE WORK (EROSION & SEDMT CONT)
HR 15.000 $100.000 $150.000 $195.000 $152.400 $168.610
TEMP SEDMT CONT FENCE (INSTALL)
LF 2,012.000 $4.000 $3.000 $2.650 $1.700 $3.410
TEMP SEDMT CONT FENCE (REMOVE)
LF 2,012.000 $1.000 $1.000 $1.000 $0.800 $1.140
CONC CURB & GUTTER (TY II)
LF 200.000 $45.000 $40.000 $45.000 $32.100 $73.950
RUMBLE STRIPS (SHOULDER)
LF 13,162.000 $0.200 $0.550 $0.450 $0.550 $1.020
RUMBLE STRIPS (CENTERLINE)
LF 6,589.000 $0.200 $0.550 $0.450 $0.550 $2.020
MTL W-BEAM GD FEN (TIM POST)
LF 525.000 $22.000 $22.000 $22.000 $22.900 $25.020
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 4.000 $1,600.000 $1,600.000 $1,450.000 $1,514.250 $1,734.650
MTL BM GD FEN (LONG SPAN SYSTEM)
EA 2.000 $1,200.000 $1,100.000 $1,100.000 $1,142.850 $1,120.420
MTL BM GD FEN TRANS (ANCHOR PLATE)
EA 4.000 $500.000 $900.000 $880.000 $914.300 $739.360
REMOVE METAL BEAM GUARD FENCE
LF 800.000 $2.750 $2.500 $2.200 $2.300 $5.120
REMOVE TERMINAL ANCHOR SECTION
EA 3.000 $250.000 $250.000 $220.000 $228.600 $170.620
GUARDRAIL END TREATMENT (INSTALL)
EA 6.000 $2,750.000 $2,600.000 $2,750.000 $2,980.300 $2,815.250
GUARDRAIL END TREATMENT (REMOVE)
EA 3.000 $250.000 $250.000 $220.000 $228.600 $284.370
IN SM RD SN SUP&AM TYTWT(1)WS(P)
EA 2.000 $400.000 $1,300.000 $1,250.000 $1,302.000 $1,419.600
REMOVE SM RD SN SUP&AM
EA 1.000 $100.000 $200.000 $335.000 $348.400 $379.920
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
EA 36.000 $30.000 $25.000 $16.500 $17.150 $32.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 26.000 $30.000 $35.000 $27.500 $28.600 $51.250
WK ZN PAV MRK NON-REMOV (W)4"(BRK)
LF 7,300.000 $0.220 $0.160 $0.170 $0.150 $0.170
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
LF 34,554.000 $0.200 $0.130 $0.130 $0.150 $0.140
WK ZN PAV MRK NON-REMOV (W)8"(SLD)
LF 859.000 $0.390 $1.100 $0.550 $1.200 $0.570
WK ZN PAV MRK NON-REMOV (W)24"(SLD)
LF 188.000 $2.750 $3.300 $2.750 $3.550 $2.850
WK ZN PAV MRK NON-REMOV (Y)4"(BRK)
LF 880.000 $0.220 $0.130 $0.130 $0.150 $0.140
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
LF 43,612.000 $0.200 $0.130 $0.130 $0.150 $0.140
WK ZN PAV MRK SHT TERM RMV (W)(4")
LF 6,580.000 $1.100 $1.750 $1.400 $1.450 $1.490
WK ZN PAV MRK SHT TERM RMV (Y)(4")
LF 20,630.000 $1.100 $1.750 $1.400 $1.450 $1.400
REFL PAV MRK TY I (W)4"(DOT)(100MIL)
LF 210.000 $1.000 $2.200 $1.100 $2.350 $1.140
REFL PAV MRK TY I (W)8"(DOT)(100MIL)
LF 70.000 $1.500 $2.750 $1.100 $2.900 $1.140
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 1,129.000 $0.650 $2.500 $0.950 $2.650 $0.960
REFL PAV MRK TY I (W)18"(SLD)(100MIL)
LF 682.000 $4.000 $4.700 $5.500 $5.000 $5.690
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 473.000 $5.000 $6.000 $6.050 $6.200 $6.260
RE PM W/RET REQ TY I (W)4"(BRK)(100MIL)
LF 7,160.000 $0.300 $0.300 $0.550 $0.300 $0.570
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 34,554.000 $0.250 $0.300 $0.500 $0.300 $0.520
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
LF 420.000 $0.300 $0.300 $1.100 $0.300 $1.140
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 42,738.000 $0.280 $0.300 $0.500 $0.300 $0.520
REF PROF PAV MRK TY I(Y)4"(BRK)(100MIL)
LF 460.000 $0.600 $3.300 $5.500 $3.500 $5.690
REF PROF PAV MRK TY I(Y)4"(SLD)(100MIL)
LF 874.000 $0.600 $3.300 $5.500 $3.500 $5.690
PREFAB PAV MRK TY C (W) (ARROW)
EA 2.000 $250.000 $300.000 $220.000 $291.500 $227.500
PREFAB PAV MRK TY C (W) (LNDP ARROW)
EA 2.000 $350.000 $700.000 $440.000 $746.300 $455.000
PREFAB PAV MRK TY C (W) (WORD)
EA 2.000 $250.000 $500.000 $330.000 $489.150 $341.250
PREFAB PAV MRK TY C (W) (RR XING)
EA 4.000 $450.000 $900.000 $770.000 $991.000 $796.250
REFL PAV MRKR TY I-A
EA 128.000 $3.000 $4.000 $3.850 $4.000 $4.000
REFL PAV MRKR TY I-C
EA 550.000 $3.000 $4.000 $3.850 $4.000 $4.000
REFL PAV MRKR TY II-A-A
EA 582.000 $2.800 $4.000 $3.850 $4.000 $4.000
MEMBRANE UNDERSEAL
GAL 33,431.000 $3.000 $3.000 $3.650 $2.550 $3.750
SP MIXES SP-C PG70-22
TON 17,029.000 $105.000 $110.000 $120.000 $117.100 $122.250
SP MIXES SP-D SAC-A PG70-22
TON 11,204.000 $105.000 $110.000 $124.000 $119.000 $118.650
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 28.000 $100.000 $100.000 $100.000 $97.150 $164.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $10,000.000 $15,000.000 $16,000.000 $19,371.000 $3,045.000
PREFORMED CENTERLINE RUMBLE STRIP
LF 130.000 $5.000 $22.000 $16.500 $23.300 $17.050
TMA (STATIONARY)
DAY 87.000 $175.000 $300.000 $125.000 $210.000 $190.250
TMA (MOBILE OPERATION)
DAY 24.000 $175.000 $50.000 $55.000 $975.000 $57.000
Totals: $4,674,054.400 $4,511,805.590 $4,951,362.370 $4,955,117.692 $5,480,667.965