WISE US 81 (0013-07-087)

Items: 38

County: WISE
Length: N/A
Highway: US 81
District: FORT WORTH
Control Number: 0013-07-087
DBE Goal: N/A
Project: STP 2B23(146)TP
Guaranty: N/A
Time: 169 WORKING DAYS
Engineer's Estimate: $3,012,606.41
Date: 08/02/2023 (2 years ago)
Contract Number: N/A
Type: CONSTRUCT REST AREA
Mail/Deliver Bids To: N/A
EDREAN CHENG
OSCAR R CHAVEZ
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (6)
E
Engineer's Estimate
$3,012,606.41
$2,289,336.40
Over/Under Est: -24.01% -$723,270.01
$2,364,861.80
Over/Under Est: -21.5% -$647,744.61
Amt Left: 3.3% $75,525.40
Over/Under Est: -14.12% -$425,311.26
Amt Left: 13.02% $297,958.75
Delta: -9.41% -$222,433.35
Over/Under Est: -9.69% -$292,067.81
Amt Left: 18.84% $431,202.20
Delta: -5.15% -$133,243.45
Over/Under Est: -7.07% -$213,140.97
Amt Left: 22.28% $510,129.04
Delta: -2.90% -$78,926.84
$3,167,942.00
Over/Under Est: 5.16% $155,335.59
Amt Left: 38.38% $878,605.60
Delta: -13.16% -$368,476.56
Subcontractor Percentage Amount
JAGOE-PUBLIC COMPANY 12.77% $351,146.14
BEAN ELECTRICAL, LLC 8.42% $231,530.97
TEX OP CONSTRUCTION, LP 2.58% $70,944.17
TEXAS SWPPP SERVICES 1.64% $45,096.29
BREDA COMPANY, INC. 0.74% $20,348.33
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. 0.74% $20,348.33
TRAFFIC HIGHWAY MAINTENANCE, LLC 0.56% $15,398.73
ACT SAW CUTTING & REMOVAL 0.34% $9,349.23
Total: 27.79% $764,162.19

Bid Items & Bid Tabulations

38 Total 0 of 38
WISE  |  US 81  |  FORT WORTH  |  0013-07-087  |  08/02/2023  |  $3,012,606.41  |  STP 2B23(146)TP  |  CONSTRUCT REST AREA  |  169 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
ED BELL CONSTRUCTION COMPANY
JAGOE-PUBLIC COMPANY
RAGLE CONSTRUCTION, INC.
SILVER CREEK CONSTRUCTION, INC.
SEMA CONSTRUCTION, INC.
TEXAS-REYES GROUP LTD.
PREPARING ROW
STA 32.000 $100.000 $4,200.000 $120.000 $8,500.000 $750.000 $11,397.590 $676.000
REMOVING CONC (PAV)
SY 4,100.000 $50.000 $17.500 $11.250 $40.000 $45.000 $13.840 $28.000
REMOVING CONC (SIDEWALKS)
SY 70.000 $40.000 $24.000 $16.500 $25.000 $30.000 $12.140 $115.000
REMOVING CONC (CURB AND GUTTER)
LF 3,340.000 $15.000 $11.500 $2.600 $10.000 $35.000 $2.280 $12.000
REMOVING STAB BASE & ASPH PAV (7"-12")
SY 8,870.000 $12.500 $10.000 $11.000 $6.500 $25.000 $6.280 $9.500
EXCAVATION (ROADWAY)
CY 1,100.000 $20.000 $35.000 $75.000 $100.000 $70.000 $20.190 $41.000
EXCAVATION (SPECIAL)
CY 50.000 $24.000 $65.000 $75.000 $90.000 $150.000 $33.450 $60.000
EMBANKMENT (FINAL)(ORD COMP)(TY D)
CY 50.000 $24.000 $28.000 $100.000 $90.000 $85.000 $55.860 $116.000
BACKFILL (TY B)
STA 32.000 $275.000 $310.000 $310.000 $900.000 $250.000 $1,353.310 $452.000
FL BS (CMP IN PLACE)(TY A GR 1-2)(8")
SY 3,160.000 $130.000 $25.000 $23.500 $13.300 $25.000 $14.790 $39.000
LIME (HYDRATED LIME (SLURRY))
TON 252.700 $330.000 $325.000 $310.000 $305.000 $470.000 $305.000 $498.000
LIME TRT (EXST MATL) (6")
SY 3,260.000 $7.000 $4.750 $4.000 $3.600 $12.500 $8.990 $12.000
LIME TRT (EXST MATL)(8")
SY 10,190.000 $9.000 $5.000 $4.500 $4.400 $12.500 $7.190 $8.500
PRIME COAT (MULTI OPTION)
GAL 3,759.300 $6.000 $3.000 $2.000 $6.000 $6.000 $7.720 $7.500
CONC PVMT (CONT REINF - CRCP) (8")
SY 9,400.000 $100.000 $90.000 $110.000 $93.000 $85.000 $115.000 $135.000
MOBILIZATION
LS 1.000 $273,873.310 $213,000.000 $230,000.000 $260,000.000 $220,000.000 $279,946.540 $289,811.650
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 9.000 $7,000.000 $4,200.000 $1,100.000 $5,350.000 $6,000.000 $2,107.660 $540.000
ROCK FILTER DAMS (INSTALL) (TY 4)
LF 200.000 $70.000 $90.000 $54.000 $39.000 $75.000 $49.920 $44.000
ROCK FILTER DAMS (REMOVE)
LF 200.000 $10.000 $45.000 $27.500 $20.000 $20.000 $24.000 $22.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 4,000.000 $5.000 $2.750 $5.500 $4.000 $5.000 $5.120 $4.500
TEMP SEDMT CONT FENCE (REMOVE)
LF 4,000.000 $1.000 $0.500 $1.400 $1.000 $1.500 $1.000 $1.000
BIODEG EROSN CONT LOGS (INSTL) (8")
LF 1,000.000 $8.000 $3.500 $5.500 $4.000 $7.000 $5.120 $4.500
BIODEG EROSN CONT LOGS (REMOVE)
LF 1,000.000 $2.000 $1.500 $1.400 $1.000 $1.000 $1.000 $1.000
CONC CURB (MONO) (TY II)
LF 1,650.000 $80.000 $5.000 $3.800 $3.900 $5.000 $9.110 $18.000
CONC CURB & GUTTER (TY II)
LF 1,690.000 $50.000 $40.000 $41.750 $24.800 $28.000 $33.770 $46.000
DRIVEWAYS (ACP)
SY 65.000 $60.000 $80.000 $48.500 $197.300 $300.000 $80.290 $291.000
CONC SIDEWALKS (4")
SY 620.000 $50.000 $80.000 $100.000 $56.900 $100.000 $75.470 $89.000
CURB RAMPS (TY 2)
EA 4.000 $2,000.000 $2,500.000 $4,300.000 $1,564.200 $3,000.000 $2,292.780 $4,350.000
CURB RAMPS (TY 7)
EA 1.000 $2,000.000 $2,500.000 $4,000.000 $2,083.500 $3,000.000 $2,802.290 $4,240.000
RELOCATE SM RD SN SUP&AM TY 10BWG
EA 3.000 $300.000 $1,250.000 $760.000 $550.000 $700.000 $580.780 $908.000
REFL PAV MRK TY I (W)12"(SLD)(090MIL)
LF 633.000 $1.000 $11.000 $7.200 $5.250 $6.000 $5.540 $13.000
RE PM W/RET REQ TY I (W)6"(SLD)(090MIL)
LF 594.000 $0.950 $7.000 $3.400 $2.500 $3.000 $2.640 $8.000
PRE PM TY B (ACC PRK)(BLU)(SYMBOL ONLY)
EA 1.000 $500.000 $1,350.000 $1,000.000 $750.000 $750.000 $791.970 $1,380.000
LANDSCAPE AMENITY (TRASH/RECYCLE BIN)
EA 8.000 $1,500.000 $2,000.000 $1,500.000 $1,295.000 $1,000.000 $1,987.080 $2,000.000
D-GR HMA TY-B PG64-22
TON 2,756.800 $120.000 $100.000 $110.000 $107.000 $117.000 $112.710 $185.000
D-GR HMA TY-C SAC-A PG70-28
TON 283.800 $110.000 $200.000 $190.000 $154.000 $164.000 $194.020 $250.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 1.000 $5,000.000 $11,000.000 $12,400.000 $25,000.000 $10,000.000 $16,123.440 $322.000
TMA (STATIONARY)
DAY 25.000 $250.000 $75.000 $320.000 $290.800 $500.000 $865.890 $233.000
Totals: $3,012,606.410 $2,289,336.400 $2,364,861.800 $2,587,295.150 $2,720,538.600 $2,799,465.460 $3,167,942.000