WINKLER FM 874 (1189-01-020)

Items: 64

County: WINKLER
Length: N/A
Highway: FM 874
District: ODESSA
Control Number: 1189-01-020
DBE Goal: N/A
Project: C 1189-1-20
Guaranty: N/A
Time: 279 WORKING DAYS
Engineer's Estimate: $14,859,513.92
Date: 03/04/2022 (4 years ago)
Contract Number: N/A
Type: HIGHWAY IMPROVEMENT
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Documents:
Bidders (3)
E
Engineer's Estimate
$14,859,513.92
Over/Under Est: -0.01% -$766.65
$16,642,778.76
Over/Under Est: 12% $1,783,264.84
Amt Left: 12.01% $1,784,031.49
Over/Under Est: 46.03% $6,839,422.44
Amt Left: 46.03% $6,840,189.09
Delta: -30.38% -$5,056,157.60

Bid Items & Bid Tabulations

64 Total 0 of 64
WINKLER  |  FM 874  |  ODESSA  |  1189-01-020  |  03/04/2022  |  $14,859,513.92  |  C 1189-1-20  |  HWY IMPRV  |  279 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
JONES BROS. DIRT & PAVING CONTRACTORS, INC.
FNF CONSTRUCTION, INC.
KIEWIT INFRASTRUCTURE SOUTH CO.
REMOVING CONC (MEDIANS)
SY 150.000 $9.000 $31.000 $22.000 $37.640
REMOVING STAB BASE AND ASPH PAV(8")
SY 45,376.000 $3.150 $3.750 $3.300 $5.070
EXCAVATION (ROADWAY)
CY 40,379.000 $9.400 $6.700 $9.500 $11.330
EMBANKMENT (FINAL)(ORD COMP)(TY B)
CY 17,211.000 $7.480 $7.400 $8.500 $6.410
BLADING
HR 40.000 $142.150 $350.000 $200.000 $268.080
PROOF ROLLING
HR 100.000 $125.000 $125.000 $150.000 $207.770
FL BS (CMP IN PLC)(TY A GR 4) (8")
SY 90,752.000 $14.640 $9.000 $10.500 $12.370
PRIME COAT (AE-P)
GAL 31,138.000 $3.990 $4.250 $5.000 $4.990
PRIME COAT (MC-30)
GAL 45,376.000 $4.340 $5.100 $4.350 $5.760
FOG SEAL (CSS-1H)
GAL 51,571.000 $3.280 $3.500 $3.500 $3.310
ASPH (AC-20-5TR)
GAL 164,476.000 $3.070 $3.950 $3.450 $4.960
AGGR(TY-B GR-4 SAC-B)
CY 2,117.000 $67.770 $100.000 $122.000 $142.560
AGGR(TY-PB GR-4 SAC-B)
CY 4,233.000 $99.280 $92.000 $123.000 $182.480
ASPH (AC-15P, CHFRS2P OR CRS2P)
GAL 58,486.000 $3.000 $3.900 $4.200 $4.520
TOM-C (AGGREGATE) SAC-A
TON 12,900.000 $102.960 $47.250 $75.750 $90.270
TOM (ASPHALT) PG 70-22
TON 1,025.000 $403.430 $817.000 $955.000 $1,008.400
FLEXIBLE PAVEMENT STRUCTURE REPAIR(3")
SY 5,000.000 $13.190 $35.600 $24.000 $38.850
CURB (TYPE II - A)
LF 92.000 $19.000 $89.250 $90.000 $97.590
CEM STABIL BKFL
CY 6.000 $105.390 $262.500 $425.000 $287.020
DRILL SHAFT (RDWY ILL POLE) (30 IN)
LF 40.000 $210.000 $315.000 $350.000 $344.420
CL K CONC (MISC)
CY 20.000 $800.000 $787.500 $3,000.000 $861.050
RIPRAP (CONC)(4 IN)
CY 2.500 $507.880 $630.000 $2,500.000 $688.840
MOBILIZATION
LS 1.000 $1,125,236.730 $920,000.000 $1,665,000.000 $2,282,725.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 14.000 $16,000.000 $8,600.000 $25,550.000 $23,123.630
BIODEG EROSN CONT LOGS (INSTL) (18")
LF 480.000 $8.000 $21.000 $10.000 $8.500
BIODEG EROSN CONT LOGS (REMOVE)
LF 480.000 $1.750 $7.500 $2.000 $2.300
DRIVEWAYS (CONC)
SY 1,496.000 $81.030 $105.000 $95.000 $114.810
DRIVEWAYS (ACP)
SY 690.000 $63.150 $100.000 $71.000 $125.740
RUMBLE STRIPS (SHOULDER)
LF 93,328.000 $0.120 $0.150 $0.100 $0.080
RUMBLE STRIPS (CENTERLINE)
LF 35,849.000 $0.170 $0.220 $0.150 $0.080
IN RD IL (TY SA) 50T-10 (400W EQ) LED
EA 5.000 $4,214.760 $7,875.000 $8,000.000 $8,610.550
CONDT (PVC) (SCH 40) (2")
LF 857.000 $11.440 $12.600 $13.350 $13.780
CONDT (PVC) (SCH 40) (2") (BORE)
LF 194.000 $23.730 $47.250 $50.000 $51.660
ELEC CONDR (NO.6) BARE
LF 1,150.000 $1.740 $2.360 $2.500 $2.580
ELEC CONDR (NO.6) INSULATED
LF 2,300.000 $2.230 $2.630 $2.750 $2.870
GROUND BOX TY A (122311)W/APRON
EA 5.000 $1,063.960 $1,575.000 $1,670.000 $1,722.110
ELC SRV TY A 240/480 060(NS)SS(E)SP(O)
EA 1.000 $6,396.980 $9,450.000 $10,000.000 $10,332.660
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 63.000 $559.830 $805.350 $800.000 $861.050
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 9.000 $706.650 $908.250 $900.000 $975.860
IN SM RD SN SUP&AM TY10BWG(1)SA(U)
EA 2.000 $950.000 $1,100.400 $1,225.000 $1,262.880
REMOVE SM RD SN SUP&AM
EA 77.000 $88.900 $76.000 $150.000 $114.810
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
LF 383,048.000 $0.140 $0.120 $0.150 $0.130
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
LF 383,048.000 $0.140 $0.120 $0.150 $0.130
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 9,576.000 $1.380 $1.500 $1.000 $2.320
WK ZN PAV MRK SHT TERM (TAB)TY Y
EA 9,576.000 $2.210 $1.500 $1.500 $2.150
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 9,576.000 $1.750 $1.500 $1.500 $0.550
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 11,725.000 $0.860 $1.050 $1.050 $1.150
REFL PAV MRK TY I (Y)12"(SLD)(100MIL)
LF 2,438.000 $3.000 $4.200 $4.050 $4.590
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 118,178.750 $0.850 $0.580 $0.550 $0.630
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
LF 11,220.000 $0.850 $0.610 $0.600 $0.670
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 28,755.000 $0.850 $0.610 $0.600 $0.670
PREFAB PAV MRK TY C (W) (24") (SLD)
LF 62.000 $14.910 $26.250 $30.000 $28.700
PREFAB PAV MRK TY C (W) (ARROW)
EA 12.000 $194.290 $315.000 $350.000 $344.420
PREFAB PAV MRK TY C (W) (LNDP ARROW)
EA 4.000 $613.130 $866.250 $900.000 $947.160
PREFAB PAV MRK TY C (W) (WORD)
EA 12.000 $231.280 $420.000 $420.000 $459.230
SP MIXES SP-B SAC-B PG70-22
TON 66,519.000 $81.600 $84.500 $81.000 $129.570
TACK COAT
GAL 48,386.000 $3.550 $3.000 $3.500 $3.500
BONDING COURSE
GAL 24,193.000 $2.910 $2.200 $3.500 $3.500
CEMENT
TON 618.000 $188.850 $260.000 $248.000 $262.560
ASPHALT BINDER (PG 64-22)
TON 1,702.000 $490.910 $740.000 $790.000 $880.980
FOAMED ASPHALT TREAT (8") (DC)
SY 155,664.000 $3.520 $4.800 $5.000 $3.220
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $17,371.000 $8,250.000 $7,500.000 $25,482.610
TMA (STATIONARY)
DAY 279.000 $300.000 $75.000 $180.000 $295.710
TMA (MOBILE OPERATION)
HR 604.000 $69.270 $20.000 $55.000 $94.960
Totals: $14,859,513.918 $14,858,747.275 $16,642,778.762 $21,698,936.362