WINKLER SH 115 (0354-04-040)

Items: 57

County: WINKLER
Length: N/A
Highway: SH 115
District: ODESSA
Control Number: 0354-04-040
DBE Goal: N/A
Project: C 354-4-40
Guaranty: N/A
Time: 112 WORKING DAYS
Engineer's Estimate: $9,249,915.43
Date: 10/06/2022 (3 years ago)
Contract Number: N/A
Type: ROADWAY REHABILITATION
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (4)
E
Engineer's Estimate
$9,249,915.43
1
$8,225,180.16
Over/Under Est: -11.08% -$1,024,735.27
$8,425,329.10
Over/Under Est: -8.91% -$824,586.33
Amt Left: 2.43% $200,148.94
Over/Under Est: -5.64% -$521,316.16
Amt Left: 6.12% $503,419.11
Delta: -3.60% -$303,270.17
$10,980,012.23
Over/Under Est: 18.7% $1,730,096.80
Amt Left: 33.49% $2,754,832.07
Delta: -25.79% -$2,251,412.96

Bid Items & Bid Tabulations

57 Total 0 of 57
WINKLER  |  SH 115  |  ODESSA  |  0354-04-040  |  10/06/2022  |  $9,249,915.43  |  C 354-4-40  |  ROADWAY REHAB  |  112 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
RK HALL, LLC
FNF CONSTRUCTION, INC.
JONES BROS. DIRT & PAVING CONTRACTORS, INC.
GILVIN-TERRILL, LTD.
EXCAVATION (ROADWAY)
CY 5,000.000 $20.000 $9.610 $15.300 $21.000 $21.000
SUBGRADE WIDENING (ORD COMP)
STA 33.000 $2,000.000 $780.690 $2,200.000 $1,350.000 $4,500.000
EMBANKMENT (FINAL)(ORD COMP)(TY B)
CY 5,000.000 $16.500 $13.360 $13.500 $21.000 $21.000
BLADING
HR 20.000 $450.000 $173.900 $200.000 $450.000 $300.000
PROOF ROLLING
HR 20.000 $200.000 $151.880 $115.000 $175.000 $400.000
FL BS (CMP IN PLC)(TY A GR 4) (8")
SY 5,531.000 $25.000 $22.160 $13.000 $27.750 $45.000
PRIME COAT (AE-P)
GAL 17,121.000 $4.500 $5.210 $3.750 $4.500 $5.000
FOG SEAL (CSS-1H)
GAL 35,685.000 $4.250 $4.750 $6.000 $4.050 $6.000
ASPH (AC-20-5TR)
GAL 32,531.000 $6.000 $5.380 $6.000 $4.700 $5.500
AGGR(TY-PB GR-4 SAC-A)
CY 722.000 $140.000 $244.080 $240.000 $167.000 $200.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(3")
SY 3,000.000 $50.000 $58.410 $45.000 $46.000 $70.000
DRILL SHAFT (RDWY ILL POLE) (30 IN)
LF 112.000 $350.000 $551.250 $660.000 $577.500 $340.000
RIPRAP (CONC)(4 IN)
CY 7.000 $600.000 $5,344.930 $2,415.000 $5,500.000 $1,000.000
MOBILIZATION
LS 1.000 $837,628.680 $650,297.830 $834,000.000 $900,000.000 $1,000,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 6.000 $25,000.000 $26,559.300 $65,000.000 $20,000.000 $75,000.000
BIODEG EROSN CONT LOGS (INSTL) (18")
LF 216.000 $10.000 $18.590 $12.500 $25.000 $10.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 216.000 $3.000 $10.000 $5.100 $10.000 $5.000
DRIVEWAYS (ACP)
SY 679.000 $130.000 $56.610 $25.000 $110.000 $160.000
RUMBLE STRIPS (SHOULDER)
LF 34,242.000 $0.250 $0.160 $0.250 $0.170 $0.450
RUMBLE STRIPS (CENTERLINE)
LF 16,280.000 $0.300 $0.260 $0.250 $0.280 $0.450
IN RD IL (TY SA) 50T-10 (400W EQ) LED
EA 14.000 $8,000.000 $8,400.000 $10,017.000 $8,800.000 $6,975.000
CONDT (HDPE) (2")
LF 3,376.000 $12.000 $12.600 $15.000 $13.200 $25.000
ELEC CONDR (NO.6) BARE
LF 3,645.000 $3.000 $2.630 $3.150 $2.750 $2.750
ELEC CONDR (NO.6) INSULATED
LF 7,290.000 $3.000 $2.890 $3.450 $3.030 $3.350
GROUND BOX TY A (122311)W/APRON
EA 1.000 $2,500.000 $1,837.500 $2,191.000 $1,925.000 $1,676.000
ELC SRV TY A 240/480 060(NS)SS(E)SP(O)
EA 1.000 $10,000.000 $13,125.000 $15,650.000 $13,750.000 $7,800.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 26.000 $1,200.000 $862.050 $1,190.000 $903.100 $825.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 15.000 $1,200.000 $1,025.850 $1,350.000 $1,074.700 $1,000.000
IN SM RD SN SUP&AM TY10BWG(1)SA(U)
EA 2.000 $1,900.000 $1,253.700 $1,610.000 $1,313.400 $1,375.000
REMOVE SM RD SN SUP&AM
EA 28.000 $275.000 $153.910 $150.000 $150.000 $168.000
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
LF 97,680.000 $0.300 $0.150 $0.200 $0.150 $0.140
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
LF 97,680.000 $0.300 $0.150 $0.200 $0.150 $0.140
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 2,444.000 $1.750 $4.240 $0.700 $2.280 $1.000
WK ZN PAV MRK SHT TERM (TAB)TY Y
EA 2,444.000 $2.650 $4.240 $0.700 $2.280 $1.000
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 2,444.000 $2.100 $4.240 $0.700 $2.280 $1.000
REFL PAV MRK TY I (W)8"(BRK)(100MIL)
LF 890.000 $2.500 $1.120 $1.350 $1.180 $1.070
REFL PAV MRK TY I (W)8"(DOT)(100MIL)
LF 1,410.000 $2.500 $1.120 $1.350 $1.180 $1.070
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 4,768.000 $2.000 $1.120 $1.350 $1.180 $1.070
REFL PAV MRK TY I (Y)12"(SLD)(100MIL)
LF 2,710.000 $4.500 $4.730 $5.650 $4.950 $4.500
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 34,161.000 $0.750 $0.540 $0.650 $0.560 $0.510
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
LF 2,112.000 $1.000 $0.540 $0.650 $0.560 $0.510
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 27,269.000 $1.750 $0.540 $0.650 $0.560 $0.510
PREFAB PAV MRK TY C (W) (24") (SLD)
LF 42.000 $30.000 $20.210 $24.000 $21.180 $19.250
PREFAB PAV MRK TY C (W) (ARROW)
EA 14.000 $390.000 $262.500 $315.000 $275.000 $250.000
PREFAB PAV MRK TY C (W) (LNDP ARROW)
EA 9.000 $630.000 $682.500 $820.000 $715.000 $650.000
PREFAB PAV MRK TY C (W) (WORD)
EA 8.000 $400.000 $367.500 $440.000 $385.000 $350.000
REFL PAV MRKR TY I-C
EA 925.000 $5.500 $4.200 $5.000 $4.400 $4.000
REFL PAV MRKR TY II-A-A
EA 971.000 $5.250 $4.200 $5.000 $4.400 $4.000
SP MIXES SP-B SAC-B PG70-22
TON 19,775.000 $129.570 $124.750 $105.000 $116.000 $160.000
STONE-MTRX-ASPH SMA-D SAC-A PG76-22
TON 9,421.000 $160.000 $156.100 $200.000 $157.000 $170.000
BONDING COURSE
GAL 8,564.000 $5.000 $5.270 $6.500 $4.500 $7.500
CEMENT
TON 343.000 $400.000 $300.000 $265.000 $345.000 $250.000
ASPHALT BINDER (PG 64-22)
TON 937.000 $1,300.000 $1,037.000 $877.000 $1,140.700 $850.000
FOAMED ASPHALT TREAT (8") (DC)
SY 85,587.000 $10.000 $6.000 $5.000 $9.200 $17.500
PORTABLE CHANGEABLE MESSAGE SIGN
EA 8.000 $25,000.000 $13,356.030 $11,000.000 $19,250.000 $19,200.000
TMA (STATIONARY)
DAY 240.000 $95.000 $391.020 $195.000 $137.500 $450.000
TMA (MOBILE OPERATION)
DAY 105.000 $300.000 $460.270 $655.000 $935.000 $450.000
Totals: $9,249,915.430 $8,225,180.160 $8,425,329.100 $8,728,599.270 $10,980,012.230