WINKLER SH 115 (0354-01-056)

Items: 24

County: WINKLER
Length: 0.0000 MILES
Highway: SH 115
District: ODESSA
Control Number: 0354-01-056
DBE Goal: 0.0%
Project: F 2B24(423)
Guaranty: $46,000.00
Time: 90 WORKING DAYS
Engineer's Estimate: $2,856,103.29
Date: 02/06/2025 (1 year ago)
Contract Number: 2253024
Type: HIGHWAY IMPROVEMENT
Project ID: A00199805
Contract Type: Federal
Project Description: ROADWAY REHABILITATION
Mail/Deliver Bids To: N/A
ODA-PRELETTINGQUESTIONS
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (7)
E
Engineer's Estimate
$2,856,103.29
Over/Under Est: -6.9% -$197,154.94
$2,972,490.25
Over/Under Est: 4.08% $116,386.96
Amt Left: 11.79% $313,541.90
$3,463,131.59
Over/Under Est: 21.25% $607,028.30
Amt Left: 30.24% $804,183.24
Delta: -16.51% -$490,641.34
$3,524,873.50
Over/Under Est: 23.42% $668,770.21
Amt Left: 32.57% $865,925.15
Delta: -1.78% -$61,741.91
$3,565,284.00
Over/Under Est: 24.83% $709,180.71
Amt Left: 34.09% $906,335.65
Delta: -1.15% -$40,410.50
$3,859,621.97
Over/Under Est: 35.14% $1,003,518.68
Amt Left: 45.16% $1,200,673.62
Delta: -8.26% -$294,337.97
Over/Under Est: 46.53% $1,328,886.71
Amt Left: 57.39% $1,526,041.65
Delta: -8.43% -$325,368.03
Subcontractor Percentage Amount
TEX OP CONSTRUCTION, LP 2.57% $68,334.97
CONTRACTORS SERVICE, LTD. 1.04% $27,653.06
DK CONTRACTING, LLC 0.84% $22,335.17
TRP CONSTRUCTION GROUP, LLC 0.44% $11,699.37
R.E.B.D. TRUCKING LLC 0.02% $531.79
Total: 4.91% $130,554.36

Bid Items & Bid Tabulations

24 Total 0 of 24
WINKLER  |  SH 115  |  ODESSA  |  0354-01-056  |  02/06/2025  |  $2,856,103.29  |  F 2B24(423)  |  HWY IMPRV  |  90 WORKING DAYS
Alt
Item Code
Description
Unit
Quantity
Engineer's Estimate
JONES BROS. DIRT & PAVING CONTRACTORS, INC.
A. L. HELMCAMP, INC.
LAKEY, INC.
CK NEWBERRY, LLC
FNF CONSTRUCTION, INC.
REECE ALBERT, INC.
GREY SKY CONSTRUCTION LLC
RMV (2"-6") TRT/UNTRT BASE & ASPH PAV
SY 31,746.000 $5.420 $6.780 $10.500 $10.000 $10.000 $10.000 $6.230 $15.000
BLADING
HR 10.000 $825.000 $393.080 $300.000 $270.000 $200.000 $400.000 $476.040 $150.000
PROOF ROLLING
HR 10.000 $163.870 $154.990 $215.000 $100.000 $100.000 $150.000 $185.560 $150.000
PRIME COAT (AE-P)
GAL 6,350.000 $8.530 $4.660 $4.700 $6.130 $6.000 $8.000 $6.350 $6.000
SP MIXES SP-B PG70-22
TON 10,478.000 $137.500 $125.460 $130.000 $118.000 $160.000 $126.000 $168.840 $180.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(6")
SY 3,399.000 $55.610 $71.860 $70.000 $55.000 $110.000 $105.000 $136.580 $60.000
MOBILIZATION
LS 1.000 $292,248.630 $110,000.000 $216,000.000 $600,000.000 $325,000.000 $356,650.000 $177,066.980 $450,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 5.000 $10,846.000 $10,000.000 $7,000.000 $37,000.000 $10,000.000 $96,500.000 $13,418.140 $10,000.000
TMA (STATIONARY)
DAY 90.000 $266.880 $148.500 $300.000 $460.000 $350.000 $185.000 $418.680 $250.000
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 100.000 $6.810 $20.720 $16.000 $6.630 $12.000 $14.000 $11.970 $18.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 100.000 $3.450 $15.720 $9.000 $3.000 $4.000 $3.250 $5.820 $9.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 16.000 $1,124.000 $950.400 $1,520.000 $915.000 $1,000.000 $1,000.000 $943.000 $1,500.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 8.000 $839.000 $1,160.500 $1,775.000 $950.000 $1,100.000 $1,250.000 $1,151.460 $1,500.000
REMOVE SM RD SN SUP&AM
EA 2.000 $138.000 $281.320 $162.000 $115.000 $100.000 $750.000 $119.670 $500.000
WK ZN PAV MRK SHT TERM (TAB)TY Y
EA 648.000 $1.830 $1.590 $0.900 $1.690 $2.000 $2.000 $2.240 $6.000
RE PM TY II (W) 6" (SLD)
LF 12,391.000 $0.860 $0.390 $0.370 $0.190 $0.350 $0.500 $0.380 $3.000
RE PM TY II (W) 24" (SLD)
LF 191.000 $39.100 $5.500 $5.250 $4.000 $5.000 $7.000 $5.460 $20.000
RE PM TY II (Y) 6" (BRK)
LF 1,207.000 $0.170 $0.390 $0.370 $0.200 $0.350 $0.500 $0.380 $3.000
RE PM TY II (Y) 6" (SLD)
LF 5,512.000 $0.180 $0.390 $0.370 $0.190 $0.350 $0.500 $0.380 $3.000
PREFAB PM TY C (W)(RR XING)
EA 2.000 $678.310 $1,320.000 $1,260.000 $597.500 $1,200.000 $1,250.000 $1,309.720 $2,500.000
REFL PAV MRKR TY II-A-A
EA 162.000 $4.310 $11.000 $11.000 $5.500 $10.000 $12.000 $10.910 $6.000
BONDING COURSE
GAL 3,176.000 $7.410 $4.950 $4.600 $6.000 $4.000 $9.000 $2.920 $10.000
1
STONE-MTRX-ASPH SMAR-F SAC-A
TON 3,651.000 $150.000 $169.290 $0.000 $0.000 $0.000 $160.000 $287.590 $0.000
1A
STONE-MTRX-ASPH SMA-D PG76-22
TON 3,651.000 $150.000 $0.000 $180.000 $220.000 $180.000 $0.000 $0.000 $250.000
Totals: $3,403,753.290 $2,658,948.350 $2,972,490.250 $3,463,131.590 $3,524,873.500 $3,565,284.000 $3,859,621.970 $4,184,990.000