WILSON US0087 (6486-05-001)

Items: 17

County: WILSON
Length: 0.0100 MILES
Highway: US0087
District: SAN ANTONIO
Control Number: 6486-05-001
DBE Goal: 0.0%
Project: BPM - A00216189
Guaranty: $0.00
Time: 16 WORKING DAYS
Engineer's Estimate: $110,128.00
Date: 11/12/2025 (7 months ago) Changed
Contract Number: 11251503
Type: EROSION REPAIR
Project ID: A00216189
Project Description: EROSION REPAIR
Mail/Deliver Bids To: N/A
HENRY FOJTIK
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (6)
E
Engineer's Estimate
$110,128.00
$90,862.00
Over/Under Est: -17.49% -$19,266.00
Over/Under Est: -12.28% -$13,521.00
Amt Left: 6.32% $5,745.00
Over/Under Est: 5.08% $5,591.00
Amt Left: 27.36% $24,857.00
Delta: -19.78% -$19,112.00
Over/Under Est: 7.92% $8,722.00
Amt Left: 30.8% $27,988.00
Delta: -2.71% -$3,131.00
Over/Under Est: 55.59% $61,218.00
Amt Left: 88.58% $80,484.00
Delta: -44.17% -$52,496.00
Over/Under Est: 69.58% $76,624.00
Amt Left: 105.53% $95,890.00
Delta: -8.99% -$15,406.00

Bid Items & Bid Tabulations

17 Total 0 of 17
WILSON  |  US0087  |  SAN ANTONIO  |  6486-05-001  |  11/12/2025  |  $110,128.00  |  BPM - A00216189  |  EROSION REPAIR  |  16 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
DIAMOND R CONTRACTING, LLC
TAYLOR CONTRACTING LLC
BK FIELD OPERATIONS LLC
VINCE CONSTRUCTION LLC
AAD CONTRACTING INC.
ICOS MANAGEMENT, LLC
REMOV CONC (RIPRAP)
SY 532.000 $9.040 $20.000 $25.000 $60.000 $10.000 $25.000 $25.000
EMBANK (FNL)(OC)(TY B)
CY 25.000 $50.000 $50.000 $150.000 $1.000 $40.000 $55.000 $200.000
COMPOST MANUF TOPSOIL (4")
SY 250.000 $3.000 $1.000 $2.000 $1.000 $5.000 $8.000 $20.000
BROADCAST SEED (PERM_RURAL_CLAY)
SY 250.000 $1.000 $1.000 $1.000 $1.000 $1.000 $2.000 $1.000
SOIL RET BLKT(SL_MOD_CLAY_SHORT)
SY 250.000 $6.620 $1.000 $2.500 $3.000 $2.000 $3.500 $5.000
CONC STR REPAIR (VERTICAL & OVERHEAD)
SF 40.000 $128.210 $120.000 $250.000 $90.000 $150.000 $175.000 $250.000
RIPRAP (CONC)(5 IN)
CY 134.000 $450.130 $400.000 $350.000 $500.000 $550.000 $600.000 $640.000
TYPE A JOINT
LF 66.000 $55.750 $50.000 $10.000 $60.000 $70.000 $100.000 $100.000
MOBILIZATION
LS 1.000 $10,000.000 $5,000.000 $2,500.000 $5,000.000 $7,500.000 $25,000.000 $40,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 2.000 $3,500.000 $2,500.000 $1.000 $1.000 $2,500.000 $7,000.000 $1.000
TMA (STATIONARY)
DAY 18.000 $110.460 $1.000 $1.000 $1.000 $150.000 $350.000 $250.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 112.000 $22.020 $1.000 $10.000 $1.000 $30.000 $12.000 $40.000
CONSTRUCTION EXITS (REMOVE)
SY 112.000 $2.040 $1.000 $1.000 $1.000 $5.000 $1.000 $20.000
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 90.000 $4.510 $1.000 $2.000 $1.000 $10.000 $4.000 $12.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 90.000 $0.550 $1.000 $1.000 $1.000 $1.000 $1.000 $1.000
DRIFTWOOD REMOVAL
LS 1.000 $3,000.000 $5,000.000 $10,000.000 $1,000.000 $5,000.000 $10,000.000 $5,000.000
CNC CRACK REPAIR (DISCRETE)(GRAVITY)
LF 22.000 $325.000 $50.000 $300.000 $70.000 $50.000 $95.000 $100.000
Totals: $110,128.000 $90,862.000 $96,607.000 $115,719.000 $118,850.000 $171,346.000 $186,752.000