WILSON CS (0915-14-048)
Items: 39
County: WILSON
Length: N/A
Highway: CS
District: SAN ANTONIO
Control Number: 0915-14-048
DBE Goal: N/A
Project: STP 2022(749)TAPS
Guaranty: N/A
Time: 55 WORKING DAYS
Engineer's Estimate: $1,328,983.15
Date: 08/02/2023 (2 years ago)
Contract Number: N/A
Type: CONSTRUCT PEDESTRIAN INFRASTRUCTURE
Mail/Deliver Bids To: N/A
WILL LOCKETT
Bidders (7)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$1,328,983.15 | |||
| $1,044,921.00 |
-21.37%
-$284,062.15
|
|||
| $1,049,998.24 |
-20.99%
-$278,984.91
|
0.49%
$5,077.24
|
||
| $1,170,996.00 |
-11.89%
-$157,987.15
|
12.07%
$126,075.00
|
-11.52%
-$120,997.76
|
|
| $1,222,023.31 |
-8.05%
-$106,959.84
|
16.95%
$177,102.31
|
-4.36%
-$51,027.31
|
|
| $1,402,073.00 |
5.5%
$73,089.85
|
34.18%
$357,152.00
|
-14.73%
-$180,049.69
|
|
| $1,427,003.41 |
7.38%
$98,020.26
|
36.57%
$382,082.41
|
-1.78%
-$24,930.41
|
|
| $1,497,948.00 |
12.71%
$168,964.85
|
43.36%
$453,027.00
|
-4.97%
-$70,944.59
|
E
Engineer's Estimate
$1,328,983.15
1
Awarded
$1,044,921.00
Over/Under Est:
-21.37%
-$284,062.15
$1,049,998.24
Over/Under Est:
-20.99%
-$278,984.91
Amt Left:
0.49%
$5,077.24
$1,170,996.00
Over/Under Est:
-11.89%
-$157,987.15
Amt Left:
12.07%
$126,075.00
Delta:
-11.52%
-$120,997.76
$1,222,023.31
Over/Under Est:
-8.05%
-$106,959.84
Amt Left:
16.95%
$177,102.31
Delta:
-4.36%
-$51,027.31
$1,402,073.00
Over/Under Est:
5.5%
$73,089.85
Amt Left:
34.18%
$357,152.00
Delta:
-14.73%
-$180,049.69
$1,427,003.41
Over/Under Est:
7.38%
$98,020.26
Amt Left:
36.57%
$382,082.41
Delta:
-1.78%
-$24,930.41
$1,497,948.00
Over/Under Est:
12.71%
$168,964.85
Amt Left:
43.36%
$453,027.00
Delta:
-4.97%
-$70,944.59
| Subcontractor | Percentage | Amount |
|---|---|---|
| F & W ELECTRICAL CONTRACTORS, INC. | 6.09% | $63,635.69 |
| LONE STAR EROSION CONTROL | 4.27% | $44,618.13 |
| TEXAS GREEN LANDSCAPE LLC | 3.73% | $38,975.55 |
| A3 CONSTRUCTION INC. | 3.68% | $38,453.09 |
| KING GEORGE TRAFFIC SOLUTIONS LLC | 1.27% | $13,270.50 |
| TRP CONSTRUCTION GROUP, LLC | 0.31% | $3,239.26 |
| Total: | 19.35% | $202,192.22 |
Bid Items & Bid Tabulations
39
Total
0 of 39