WILSON US 181 (0100-03-086)

Items: 30

County: WILSON
Length: N/A
Highway: US 181
District: SAN ANTONIO
Control Number: 0100-03-086
DBE Goal: N/A
Project: STP 2023(386)HES
Guaranty: N/A
Time: 192 WORKING DAYS
Engineer's Estimate: $5,075,877.91
Date: 12/02/2022 (3 years ago)
Contract Number: N/A
Type: HAZARD ELIMINATION & SAFETY
Mail/Deliver Bids To: N/A
TIMOTHY PARKER1
MARCO GALINDO
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (7)
E
Engineer's Estimate
$5,075,877.91
$4,783,311.04
Over/Under Est: -5.76% -$292,566.87
Over/Under Est: -4.03% -$204,797.39
Amt Left: 1.83% $87,769.48
$5,034,886.93
Over/Under Est: -0.81% -$40,990.98
Amt Left: 5.26% $251,575.89
Delta: -3.36% -$163,806.41
Over/Under Est: 2.87% $145,865.37
Amt Left: 9.17% $438,432.24
Delta: -3.71% -$186,856.35
Over/Under Est: 5.48% $278,201.03
Amt Left: 11.93% $570,767.90
Delta: -2.53% -$132,335.66
$5,698,730.46
Over/Under Est: 12.27% $622,852.55
Amt Left: 19.14% $915,419.42
Delta: -6.44% -$344,651.52
$6,043,767.60
Over/Under Est: 19.07% $967,889.69
Amt Left: 26.35% $1,260,456.56
Delta: -6.05% -$345,037.14

Bid Items & Bid Tabulations

30 Total 0 of 30
WILSON  |  US 181  |  SAN ANTONIO  |  0100-03-086  |  12/02/2022  |  $5,075,877.91  |  STP 2023(386)HES  |  HAZARD ELIM & SAFETY  |  192 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
MASSANA CONSTRUCTION INC.
SCR CIVIL CONSTRUCTION, LLC
DAN WILLIAMS COMPANY
ROADWAY SPECIALTIES, INC.
GRATIOT CONSTRUCTION, LTD.
ALTUS CONSTRUCTION LLC
FNH CONSTRUCTION, LLC
REMOVING CONC (RIPRAP)
SY 783.000 $10.000 $12.000 $22.000 $16.000 $44.000 $17.000 $11.580 $100.000
RMV TRT & UNTRT BASE & ASPH PV(12"-30")
SY 8,904.000 $10.000 $28.000 $40.000 $12.750 $18.000 $30.000 $29.000 $40.000
EXCAVATION (ROADWAY)
CY 525.000 $12.000 $46.000 $33.000 $30.000 $44.000 $40.000 $52.060 $30.000
EMBANKMENT (VEHICLE)(ORD COMP)(TY B)
CY 2,550.000 $22.000 $35.000 $23.800 $15.000 $51.000 $55.000 $36.260 $40.000
BLADING
HR 30.000 $150.000 $200.000 $179.000 $140.000 $200.000 $100.000 $440.430 $200.000
DRILL SEEDING (PERM) (RURAL) (CLAY)
SY 178,396.000 $0.280 $0.180 $0.370 $0.230 $0.450 $0.260 $0.330 $0.300
DRILL SEED (TEMP)(WARM OR COOL)
SY 178,396.000 $0.180 $0.120 $0.280 $0.200 $0.380 $0.190 $0.240 $0.300
VEGETATIVE WATERING
MG 2,782.600 $20.000 $71.850 $48.000 $8.000 $54.490 $50.000 $2.520 $50.000
SOIL RETENTION BLANKETS (CL 1) (TY A)
SY 178,396.000 $1.000 $0.900 $1.070 $1.300 $1.310 $1.640 $1.570 $3.000
RIPRAP (CL A) (MOW STRIP) (3 IN)
CY 2,634.000 $520.000 $395.000 $547.000 $430.000 $385.000 $585.000 $477.240 $500.000
REMOV STR (SET)
EA 14.000 $640.000 $1,000.000 $400.000 $700.000 $550.000 $500.000 $1,315.440 $2,500.000
REMOV STR (PIPE)
LF 669.000 $25.000 $45.000 $30.000 $25.000 $40.000 $13.000 $29.170 $50.000
MOBILIZATION
LS 1.000 $461,443.450 $226,703.730 $161,000.000 $500,000.000 $695,214.850 $850,000.000 $553,678.250 $287,500.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 12.000 $9,000.000 $12,000.000 $3,300.000 $25,000.000 $1,934.470 $1.000 $25,167.190 $8,500.000
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 4,910.000 $4.000 $4.000 $7.500 $6.000 $9.170 $5.500 $9.120 $18.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 4,910.000 $1.500 $1.000 $1.700 $2.000 $16.620 $0.750 $2.200 $9.000
CABLE BARRIER SYSTEM (TL-3)
LF 88,022.000 $19.000 $15.000 $15.960 $16.500 $15.550 $12.750 $18.410 $12.000
CABLE BARRIER TERMINAL SECTION (TL-3)
EA 134.000 $3,600.000 $5,500.000 $2,105.000 $4,000.000 $3,313.540 $2,750.000 $3,517.960 $5,000.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 18.000 $600.000 $550.000 $1,000.000 $850.000 $539.910 $1,000.000 $778.570 $1,500.000
REMOVE SM RD SN SUP&AM
EA 60.000 $115.000 $125.000 $125.000 $125.000 $150.000 $1.000 $182.940 $650.000
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 286.000 $1.000 $4.000 $1.700 $3.250 $2.040 $1.500 $1.890 $6.000
REFL PAV MRK TY II (W) 8" (SLD)
LF 286.000 $0.600 $0.500 $1.150 $3.250 $1.360 $1.000 $1.260 $6.000
REFL PAV MRK TY II (Y) 6" (SLD)
LF 13,517.000 $0.300 $0.600 $0.450 $1.000 $0.540 $0.400 $0.500 $6.000
REF PROF PAV MRK TY I(W)6"(SLD)(100MIL)
LF 200,096.000 $0.750 $0.800 $1.110 $0.950 $1.360 $1.000 $1.260 $2.000
REF PROF PAV MRK TY I(Y)6"(SLD)(100MIL)
LF 213,143.000 $1.000 $0.900 $1.110 $0.950 $1.360 $1.000 $1.260 $2.000
REFL PAV MRKR TY II-C-R
EA 14.000 $4.600 $7.500 $12.000 $5.000 $13.620 $10.000 $12.580 $5.000
ELIM EXT PAV MRK & MRKS (4")
LF 13,274.000 $0.500 $0.600 $0.600 $1.000 $0.680 $0.500 $0.630 $1.000
ELIM EXT PAV MRK & MRKS (8")
LF 7,306.000 $1.200 $1.200 $0.840 $2.000 $1.020 $0.750 $0.940 $2.000
TMA (STATIONARY)
DAY 176.000 $220.000 $275.000 $350.000 $300.000 $50.000 $1.000 $176.170 $250.000
TMA (MOBILE OPERATION)
DAY 39.000 $250.000 $260.000 $200.000 $550.000 $350.000 $500.000 $302.010 $550.000
Totals: $5,075,877.910 $4,783,311.040 $4,871,080.520 $5,034,886.930 $5,221,743.284 $5,354,078.940 $5,698,730.462 $6,043,767.600