WILLIAMSON COUNTY ROAD 143 (0914-05-203)
Items: 68
County: WILLIAMSON
Length: 0.0000 MILES
Highway: COUNTY ROAD 143
District: AUSTIN
Control Number: 0914-05-203
DBE Goal: 6.0%
Project: BR 2020(732)
Guaranty: $40,000.00
Time: 104 WORKING DAYS
Engineer's Estimate: $2,022,833.86
Date: 08/08/2025 (10 months ago) Changed
Contract Number: 6253022
Type: HIGHWAY IMPROVEMENT
Project ID: A00129321
Contract Type: Federal
Project Description: REPLACE BRIDGE AND APPROACHES
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
KYLE RUSSELL
JEREMY MIKES
WILLIAMSON COUNTY ROAD 143 (0914-05-203)
Project Name: N/A
Project: BR 2020(732)
Length: 0.0000 MILES
Project Type: CONSTRUCTION
Limits From: 570' W OF DRY BERRY CREEK ON CR 143
Limits To: 440' E OF DRY BERRY CREEK ON CR 143
Project Description: REPLACE BRIDGE AND APPROACHES
WILLIAMSON COUNTY ROAD 143 (0914-05-219)
Project Name: CR 143 FROM W & E OF DRY BERRY CREEK
Project: CC 914-5-219
Length: 0.0000 MILES
Project Type: REHABILITATION OF EXISTING ROAD
Limits From: 3,200' EAST OF CR 234
Limits To: 4,614' EAST OF CR 234
Project Description: ROAD RE-ALIGNMENT ON EITHER SIDE OF DRY BERRY CREEK AND ADDITIONAL BRIDGE TO MEET 60 MPH DESIGN SPEED. LIMITS ARE 3,200’ EAST OF CR 234 TO 3,882’ EAST OF CR 234 AND 4,082’ EAST OF CR 234 TO 4,614’ EAST OF CR 234
Informational
Bidders (11)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$2,022,833.86 | |||
| $1,585,425.45 |
-21.62%
-$437,408.41
|
|||
| $1,689,966.00 |
-16.46%
-$332,867.86
|
6.59%
$104,540.55
|
||
| $1,812,701.70 |
-10.39%
-$210,132.16
|
14.34%
$227,276.25
|
-7.26%
-$122,735.70
|
|
| $1,838,555.85 |
-9.11%
-$184,278.01
|
15.97%
$253,130.40
|
-1.43%
-$25,854.15
|
|
| $1,897,999.99 |
-6.17%
-$124,833.87
|
19.72%
$312,574.54
|
-3.23%
-$59,444.14
|
|
| $1,974,942.28 |
-2.37%
-$47,891.58
|
24.57%
$389,516.83
|
-4.05%
-$76,942.29
|
|
| $2,092,092.00 |
3.42%
$69,258.14
|
31.96%
$506,666.55
|
-5.93%
-$117,149.72
|
|
| $2,125,307.05 |
5.07%
$102,473.19
|
34.05%
$539,881.60
|
-1.59%
-$33,215.05
|
|
| $2,173,884.25 |
7.47%
$151,050.39
|
37.12%
$588,458.80
|
-2.29%
-$48,577.20
|
|
| $2,179,121.64 |
7.73%
$156,287.78
|
37.45%
$593,696.19
|
-0.24%
-$5,237.39
|
|
| $2,519,156.35 |
24.54%
$496,322.49
|
58.89%
$933,730.90
|
-15.60%
-$340,034.71
|
E
Engineer's Estimate
$2,022,833.86
1
Awarded
$1,585,425.45
Over/Under Est:
-21.62%
-$437,408.41
$1,689,966.00
Over/Under Est:
-16.46%
-$332,867.86
Amt Left:
6.59%
$104,540.55
$1,812,701.70
Over/Under Est:
-10.39%
-$210,132.16
Amt Left:
14.34%
$227,276.25
Delta:
-7.26%
-$122,735.70
$1,838,555.85
Over/Under Est:
-9.11%
-$184,278.01
Amt Left:
15.97%
$253,130.40
Delta:
-1.43%
-$25,854.15
$1,897,999.99
Over/Under Est:
-6.17%
-$124,833.87
Amt Left:
19.72%
$312,574.54
Delta:
-3.23%
-$59,444.14
$1,974,942.28
Over/Under Est:
-2.37%
-$47,891.58
Amt Left:
24.57%
$389,516.83
Delta:
-4.05%
-$76,942.29
$2,092,092.00
Over/Under Est:
3.42%
$69,258.14
Amt Left:
31.96%
$506,666.55
Delta:
-5.93%
-$117,149.72
$2,125,307.05
Over/Under Est:
5.07%
$102,473.19
Amt Left:
34.05%
$539,881.60
Delta:
-1.59%
-$33,215.05
$2,173,884.25
Over/Under Est:
7.47%
$151,050.39
Amt Left:
37.12%
$588,458.80
Delta:
-2.29%
-$48,577.20
$2,179,121.64
Over/Under Est:
7.73%
$156,287.78
Amt Left:
37.45%
$593,696.19
Delta:
-0.24%
-$5,237.39
$2,519,156.35
Over/Under Est:
24.54%
$496,322.49
Amt Left:
58.89%
$933,730.90
Delta:
-15.60%
-$340,034.71
| Subcontractor | Percentage | Amount |
|---|---|---|
| TEXAS MATERIALS GROUP, INC. | 7.28% | $115,418.97 |
| A K FUQUAY CONSTRUCTION | 3.85% | $61,038.88 |
| BEAIRD DRILLING SERVICES, INC. | 2.56% | $40,586.89 |
| DIIBS SPECIALISTS, LLC | 2.12% | $33,611.02 |
| STRIPE IT UP, LLC | 1.30% | $20,610.53 |
| PENHALL COMPANY | 0.54% | $8,561.30 |
| GK CONSTRUCTION, LLC | 0.54% | $8,561.30 |
| ROADWAY TRAFFIC CONTROL LLC | 0.49% | $7,768.58 |
| GK CONSTRUCTION, LLC | 0.08% | $1,268.34 |
| Total: | 18.76% | $297,425.81 |
Bid Items & Bid Tabulations
68
Total
0 of 68
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
| Description | Amount |
|---|---|
| LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (PART) | $18,200.00 |
| EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) | $7,000.00 |
| SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) | $35,000.00 |
| CONTRACTOR FORCE ACCOUNT WORK (PART) | $1,000.00 |
| Total: | $61,200.00 |