WILLIAMSON SH 195 (0836-01-016)

Items: 20

County: WILLIAMSON
Length: N/A
Highway: SH 195
District: AUSTIN
Control Number: 0836-01-016
DBE Goal: N/A
Project: STP 2023(603)HES
Guaranty: N/A
Time: 254 WORKING DAYS
Engineer's Estimate: $3,049,859.26
Date: 08/02/2023 (2 years ago)
Contract Number: N/A
Type: HIGHWAY IMPROVEMENT
Mail/Deliver Bids To: N/A
JASON HUDSON
JOHN PETERS
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (4)
E
Engineer's Estimate
$3,049,859.26
$2,348,911.02
Over/Under Est: -22.98% -$700,948.24
$2,366,516.92
Over/Under Est: -22.41% -$683,342.34
Amt Left: 0.75% $17,605.90
Over/Under Est: -6.94% -$211,775.61
Amt Left: 20.83% $489,172.63
Delta: -19.93% -$471,566.73
Over/Under Est: 1.37% $41,882.68
Amt Left: 31.62% $742,830.92
Delta: -8.94% -$253,658.29

Bid Items & Bid Tabulations

20 Total 0 of 20
WILLIAMSON  |  SH 195  |  AUSTIN  |  0836-01-016  |  08/02/2023  |  $3,049,859.26  |  STP 2023(603)HES  |  HWY IMPRV  |  254 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
GRATIOT CONSTRUCTION, LTD.
DAN WILLIAMS COMPANY
D&S CONCRETE CONTRACTORS LLC
ROADWAY SPECIALTIES, INC.
EMBANKMENT (VEHICLE)(ORD COMP)(TY B)
CY 50.000 $50.000 $100.000 $50.000 $30.000 $125.000
BACKFILL (TY A OR B)
STA 575.000 $170.000 $25.000 $165.000 $100.000 $100.000
BLADING
STA 575.000 $172.770 $150.000 $60.000 $100.000 $100.000
FURNISHING AND PLACING TOPSOIL (4")
SY 58,653.000 $1.510 $0.500 $0.900 $0.750 $4.160
CELL FBR MLCH SEED(PERM)(RURAL)(CLAY)
SY 58,653.000 $0.600 $0.440 $0.440 $0.400 $0.680
CELL FBR MLCH SEED(TEMP)(WARM)
SY 29,326.500 $0.470 $0.400 $0.400 $0.400 $0.610
CELL FBR MLCH SEED(TEMP)(COOL)
SY 29,326.500 $0.520 $0.400 $0.400 $0.400 $0.610
VEGETATIVE WATERING
MG 2,354.000 $10.000 $10.000 $8.000 $3.000 $35.000
SOIL RETENTION BLANKETS (CL 1) (TY A)
SY 58,653.000 $0.730 $1.000 $0.900 $1.500 $2.160
RIPRAP (MOW STRIP)(4 IN)
CY 2,182.000 $570.540 $470.000 $385.000 $700.000 $475.000
MOBILIZATION
LS 1.000 $262,014.000 $228,900.000 $215,000.000 $250,000.000 $457,342.590
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 16.000 $7,995.720 $4,000.000 $6,450.000 $3,000.000 $3,595.240
TEMP SEDMT CONT FENCE (INSTALL)
LF 250.000 $4.110 $6.000 $6.000 $6.000 $4.630
TEMP SEDMT CONT FENCE (REMOVE)
LF 250.000 $0.700 $2.000 $2.000 $1.000 $1.370
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 950.000 $4.680 $9.000 $9.000 $5.000 $4.240
BIODEG EROSN CONT LOGS (REMOVE)
LF 950.000 $0.640 $2.000 $2.000 $1.000 $3.530
CABLE BARRIER SYSTEM (TL-4)
LF 56,753.000 $13.400 $11.000 $12.000 $10.000 $13.380
CABLE BARRIER TERMINAL SECTION (TL-4)
EA 38.000 $3,500.000 $3,100.000 $4,000.000 $2,500.000 $2,068.100
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 430.000 $185.000 $10.000 $65.000 $45.000 $68.250
TMA (STATIONARY)
DAY 209.000 $81.140 $25.000 $140.000 $100.000 $68.250
Totals: $3,049,859.265 $2,348,911.020 $2,366,516.920 $2,838,083.650 $3,091,741.950