WILLIAMSON US 79 (0204-01-070)

Items: 26

County: WILLIAMSON
Length: N/A
Highway: US 79
District: AUSTIN
Control Number: 0204-01-070
DBE Goal: N/A
Project: CC 204-1-70
Guaranty: N/A
Time: 42 WORKING DAYS
Engineer's Estimate: $140,116.73
Date: 04/03/2018 (8 years ago)
Contract Number: N/A
Type: LENGTHEN LEFT TURN LANE
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (6)
E
Engineer's Estimate
$140,116.73
$110,817.60
Over/Under Est: -20.91% -$29,299.13
$159,561.90
Over/Under Est: 13.88% $19,445.17
Amt Left: 43.99% $48,744.30
Over/Under Est: 15.56% $21,800.73
Amt Left: 46.11% $51,099.86
Delta: -1.48% -$2,355.56
Over/Under Est: 17.29% $24,230.27
Amt Left: 48.3% $53,529.40
Delta: -1.50% -$2,429.54
Over/Under Est: 26.84% $37,606.52
Amt Left: 60.37% $66,905.65
Delta: -8.14% -$13,376.25
Over/Under Est: 28.46% $39,877.31
Amt Left: 62.42% $69,176.44
Delta: -1.28% -$2,270.79

Bid Items & Bid Tabulations

26 Total 0 of 26
WILLIAMSON  |  US 79  |  AUSTIN  |  0204-01-070  |  04/03/2018  |  $140,116.73  |  CC 204-1-70  |  LENGTHEN LEFT TURN LANE  |  42 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
COX COMMERCIAL CONSTRUCTION LLC
DENBOW COMPANY INC.
TCB CONSTRUCTION, INC
JOE BLAND CONSTRUCTION, L.P.
AARON CONCRETE CONTRACTORS, L.P.
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.
REMOVING STAB BASE AND ASPH PAV (13")
SY 309.000 $24.000 $20.000 $15.000 $31.500 $22.000 $45.000 $20.000
EXCAVATION (ROADWAY)
CY 122.000 $35.000 $20.000 $65.000 $22.000 $45.000 $70.000 $25.000
EMBANKMENT (FINAL)(ORD COMP)(TY A)
CY 502.000 $30.000 $20.000 $38.000 $48.750 $55.000 $70.000 $71.000
FURNISHING AND PLACING TOPSOIL (4")
SY 2,022.000 $5.000 $2.000 $8.000 $4.500 $3.750 $3.000 $9.000
CELL FBR MLCH SEED(PERM)(RURAL)(CLAY)
SY 2,022.000 $0.600 $0.300 $0.400 $1.000 $1.000 $0.300 $0.320
VEGETATIVE WATERING
MG 17.000 $70.000 $20.000 $35.000 $100.000 $55.000 $35.000 $60.000
FL BS (CMP IN PLC)(TY A GR 5)(FNAL POS)
CY 242.000 $80.000 $50.000 $90.000 $77.630 $50.000 $150.000 $147.000
PRIME COAT (MC-30)
GAL 193.000 $12.000 $5.000 $6.000 $3.000 $6.500 $6.000 $14.500
D-GR HMA(SQ) TY-B PG64-22
TON 151.000 $145.000 $100.000 $96.000 $165.000 $110.000 $114.000 $125.000
D-GR HMA(SQ) TY-D PG70-22
TON 111.000 $155.580 $100.000 $99.000 $165.000 $115.000 $114.000 $155.000
PLANE ASPH CONC PAV (2")
SY 1,002.000 $8.000 $6.000 $7.000 $2.000 $10.000 $7.000 $6.250
MOBILIZATION
LS 1.000 $18,300.000 $10,000.000 $14,400.000 $23,000.000 $16,425.000 $15,000.000 $15,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 3.000 $2,000.000 $2,500.000 $3,000.000 $2,935.000 $10,500.000 $1,500.000 $1,500.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 30.000 $10.000 $15.000 $11.000 $10.000 $11.700 $13.000 $17.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 30.000 $3.000 $5.000 $0.500 $5.000 $5.000 $5.500 $10.000
REFL PAV MRK TY I (W)8"(SLD)(090MIL)
LF 363.000 $2.200 $5.000 $5.000 $5.000 $4.900 $4.300 $4.000
REFL PAV MRK TY I (W)(ARROW)(090MIL)
EA 1.000 $103.990 $250.000 $330.000 $250.000 $805.000 $242.000 $225.000
REFL PAV MRK TY I (W)(WORD)(090MIL)
EA 1.000 $142.150 $300.000 $400.000 $250.000 $874.000 $295.000 $275.000
REFL PAV MRK TY II (W) 8" (SLD)
LF 363.000 $0.400 $2.000 $2.500 $5.000 $1.200 $2.150 $2.000
REFL PAV MRK TY II (W) (ARROW)
EA 1.000 $63.340 $100.000 $110.000 $250.000 $57.500 $81.000 $75.000
REFL PAV MRK TY II (W) (WORD)
EA 1.000 $74.970 $125.000 $140.000 $250.000 $57.500 $108.000 $100.000
REFL PAV MRK TY II (Y) 4" (SLD)
LF 689.000 $1.500 $1.000 $1.400 $4.000 $0.600 $1.100 $1.000
REF PROF PAV MRK TY I(Y)4"(SLD)(090MIL)
LF 689.000 $5.000 $10.000 $11.000 $4.000 $9.200 $8.600 $8.000
REFL PAV MRKR TY II-C-R
EA 9.000 $6.600 $15.000 $17.000 $10.000 $57.500 $13.000 $12.000
ELIM EXT PAV MRK & MRKS (4")
LF 380.000 $2.750 $2.000 $2.000 $9.000 $1.200 $1.600 $1.500
TMA (STATIONARY)
EA 1.000 $400.000 $12,000.000 $18,000.000 $1,700.000 $1,000.000 $8,000.000 $4,500.000
Totals: $140,116.730 $110,817.600 $159,561.900 $161,917.460 $164,347.000 $177,723.250 $179,994.040