WILBARGER US0070 (6466-43-001)

Items: 28

County: WILBARGER
Length: N/A
Highway: US0070
District: WICHITA FALLS
Control Number: 6466-43-001
DBE Goal: 0.0%
Project: RMC - 646643001
Guaranty: N/A
Time: 60 W
Engineer's Estimate: $1,052,583.00
Date: 05/03/2024 (2 years ago)
Contract Number: N/A
Type: REPAIR/REPLACE CONCRETE BARRIER
Mail/Deliver Bids To: N/A
CALLAN COLTHARP
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (3)
E
Engineer's Estimate
$1,052,583.00
Over/Under Est: 21.75% $228,888.75
Over/Under Est: 35.72% $375,937.40
Amt Left: 11.47% $147,048.65
Over/Under Est: 38.13% $401,339.30
Amt Left: 13.46% $172,450.55
Delta: -1.78% -$25,401.90
Subcontractor Percentage Amount
MAR-ZAP CONSTRUCTION, LLC 15.03% $199,925.96
TRAFFIC HIGHWAY MAINTENANCE, LLC 5.22% $69,435.36
LANCO TURF & SEEDING, INC. 0.31% $4,123.56
Total: 20.56% $273,484.88

Bid Items & Bid Tabulations

28 Total 0 of 28
WILBARGER  |  US0070  |  WICHITA FALLS  |  6466-43-001  |  05/03/2024  |  $1,052,583.00  |  RMC - 646643001  |  REPAIR/REPLACE CONC BARRIER  |  60 W
Item Code
Description
Unit
Quantity
Engineer's Estimate
MB WESTERN INDUSTRIAL CONTRACTING CO.
SILVER CREEK CONSTRUCTION, INC.
SCR CIVIL CONSTRUCTION, LLC
REMOVING CONCRETE(MOW STRIP)
LF 300.000 $10.000 $20.000 $20.000 $58.000
EXCAVATION (ROADWAY)
CY 277.000 $15.000 $40.000 $75.000 $29.000
EMBANKMENT (FINAL)(ORD COMP)(TY B)
CY 201.000 $25.000 $85.000 $75.000 $48.000
BROADCAST SEED (PERM) (RURAL) (SANDY)
SY 4,778.000 $0.500 $1.000 $1.000 $1.150
VEGETATIVE WATERING
MG 39.000 $50.000 $250.000 $100.000 $80.000
CONC PVMT (CONT REINF - CRCP) (7")
SY 1,791.000 $125.000 $125.000 $195.000 $195.000
MOBILIZATION
LS 1.000 $92,053.000 $100,000.000 $142,852.000 $145,200.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 4.000 $10,000.000 $4,800.000 $16,000.000 $15,400.000
BIODEG EROSN CONT LOGS (INSTL) (8")
LF 140.000 $10.000 $5.000 $6.000 $14.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 140.000 $2.000 $2.000 $1.000 $4.000
PERM CTB (SGL SLOPE) (TY 1) (42 )
LF 5,375.000 $95.000 $123.000 $117.290 $112.500
REMOVE METAL BEAM GUARD FENCE
LF 200.000 $5.000 $5.000 $10.000 $30.000
RM MTL BM GD FENCE TRANS (THRIE-BEAM)
EA 1.000 $250.000 $100.000 $150.000 $1,000.000
CABLE BARRIER TERMINAL SECTION (TL-3)
EA 2.000 $5,000.000 $7,500.000 $5,000.000 $11,100.000
REMOVE CABLE BARRIER
LF 5,278.000 $15.000 $7.000 $2.000 $3.000
REMOVE CABLE BARRIER TERMINAL SECTION
EA 2.000 $700.000 $1,250.000 $500.000 $1,000.000
GUARDRAIL END TREATMENT (REMOVE)
EA 1.000 $250.000 $350.000 $500.000 $900.000
CRASH CUSH ATTEN (INSTL)(L)(N)(TL3)
EA 2.000 $15,000.000 $31,000.000 $32,000.000 $45,900.000
INSTL DEL ASSM (D-SY)SZ (BRF)CTB
EA 64.000 $20.000 $30.000 $30.000 $60.000
WK ZN PAV MRK REMOV (TRAF BTN) TY Y
LF 8,475.000 $0.750 $3.650 $2.000 $1.050
RE PM W/RET REQ TY I (W)6"(SLD)(100MIL)
LF 8,475.000 $0.500 $2.000 $1.350 $1.050
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
LF 2,120.000 $0.550 $2.500 $1.500 $1.050
RE PM W/RET REQ TY I (Y)6"(SLD)(100MIL)
LF 10,475.000 $0.500 $2.000 $1.350 $1.050
REFL PAV MRKR TY II-C-R
EA 107.000 $5.000 $22.000 $13.500 $8.050
ELIM EXT PAV MRK & MRKS (4")
LF 10,595.000 $0.250 $1.000 $0.670 $0.700
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 67.000 $150.000 $100.000 $300.000 $300.000
TMA (STATIONARY)
DAY 60.000 $200.000 $200.000 $350.000 $550.000
TMA (MOBILE OPERATION)
DAY 10.000 $225.000 $200.000 $500.000 $1,100.000
Totals: $1,052,583.000 $1,281,471.750 $1,428,520.400 $1,453,922.300