WILBARGER US 287 (0043-05-108)

Items: 25

County: WILBARGER
Length: N/A
Highway: US 287
District: WICHITA FALLS
Control Number: 0043-05-108
DBE Goal: N/A
Project: NH 2019(735)
Guaranty: N/A
Time: 50 WORKING DAYS
Engineer's Estimate: $6,653,793.43
Date: 04/02/2019 (7 years ago)
Contract Number: N/A
Type: MILL AND OVERLAY
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (2)
E
Engineer's Estimate
$6,653,793.43
$6,884,724.00
Over/Under Est: 3.47% $230,930.57
$7,274,355.74
Over/Under Est: 9.33% $620,562.31
Amt Left: 5.66% $389,631.74

Bid Items & Bid Tabulations

25 Total 0 of 25
WILBARGER  |  US 287  |  WICHITA FALLS  |  0043-05-108  |  04/02/2019  |  $6,653,793.43  |  NH 2019(735)  |  MILL AND OVERLAY  |  50 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
DUININCK, INC.
ZACK BURKETT CO.
BACKFILL (TY B)
STA 145.000 $100.000 $185.000 $295.000
PFC (ASPHALT) PG76-22
TON 2,191.000 $110.000 $720.000 $780.000
PFC-C (AGGREGATE)(PG76 MIX) SAC-A
TON 34,357.000 $110.000 $74.000 $61.570
SUPERPAVE MIXTURES SP-D PG70-22
TON 10,674.000 $70.000 $100.000 $91.620
PLANE ASPH CONC PAV(0" TO 2")
SY 498,535.000 $1.000 $1.050 $1.760
MOBILIZATION
LS 1.000 $603,526.680 $360,000.000 $408,295.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 3.000 $5,000.000 $33,500.000 $12,000.000
INTRSCT, DRVWAYS, & TURNOUT (ACP)
SY 30,762.000 $7.830 $14.500 $13.000
RUMBLE STRIPS (CENTERLINE)
LF 12,822.000 $0.170 $0.210 $0.940
RUMBLE STRIPS (SHOULDER) ASPHALT
LF 250,220.000 $0.130 $0.150 $0.270
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 10,784.000 $2.500 $1.050 $1.000
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 1,600.000 $2.000 $1.050 $1.000
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 9,271.000 $1.180 $1.050 $0.910
RE PM W/RET REQ TY I (W)4"(BRK)(100MIL)
LF 35,920.000 $0.780 $0.460 $0.590
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 172,645.000 $0.510 $0.370 $0.460
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
LF 3,187.000 $0.470 $0.460 $0.590
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 156,694.000 $0.470 $0.370 $0.460
PREFAB PAV MRK TY C (W) (24") (SLD)
LF 48.000 $14.500 $12.500 $17.550
PREFAB PAV MRK TY C (W) (RR XING)
EA 3.000 $700.000 $940.000 $760.500
REFL PAV MRKR TY I-C
EA 12.000 $3.650 $5.250 $5.850
REFL PAV MRKR TY II-A-A
EA 321.000 $2.570 $5.250 $5.850
REFL PAV MRKR TY II-C-R
EA 1,790.000 $2.710 $5.250 $3.690
BONDING COURSE
GAL 128,248.000 $1.810 $0.010 $3.220
TMA (STATIONARY)
DAY 50.000 $61.000 $295.000 $125.000
TMA (MOBILE OPERATION)
HR 76.000 $42.000 $94.000 $23.400
Totals: $6,653,793.430 $6,884,724.000 $7,274,355.740