Show Job Controls
Bid Cobra

WICHITA CS (0903-03-083)

Items: 51

County: WICHITA
Length: N/A
Highway: CS
District: WICHITA FALLS
Control Number: 0903-03-083
DBE Goal: N/A
Project: BR 2006(550)
Guaranty: N/A
Time: 123 WORKING DAYS
Engineer's Estimate: $1,085,462.00
Date: 06/07/2017 (9 years ago)
Contract Number: N/A
Type: REPLACE BRIDGE AND APPROACHES
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (4)
E
Engineer's Estimate
$1,085,462.00
$1,293,885.00
Over/Under Est: 19.2% $208,423.00
$1,314,786.50
Over/Under Est: 21.13% $229,324.50
Amt Left: 1.62% $20,901.50
$1,587,534.35
Over/Under Est: 46.25% $502,072.35
Amt Left: 22.7% $293,649.35
Delta: -20.74% -$272,747.85
$1,790,329.75
Over/Under Est: 64.94% $704,867.75
Amt Left: 38.37% $496,444.75
Delta: -12.77% -$202,795.40

Bid Items & Bid Tabulations

51 Total 0 of 51
WICHITA  |  CS  |  WICHITA FALLS  |  0903-03-083  |  06/07/2017  |  $1,085,462.00  |  BR 2006(550)  |  REPLACE BRIDGE AND APPROACHES  |  123 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
EARTH BUILDERS, L.P.
3LW CIVIL LLC
PIERCE R & B LLC
A. L. HELMCAMP, INC.
PREPARING ROW
STA 10.100 $3,500.000 $2,500.000 $2,000.000 $2,000.000 $14,000.000
REMOVING CONC (RIPRAP)
SY 14.000 $20.000 $20.000 $15.000 $100.000 $160.000
REMOVING CONC (SIDEWALKS)
SY 187.000 $20.000 $10.000 $15.000 $20.000 $25.000
REMOVING CONC (CURB OR CURB & GUTTER)
LF 1,801.000 $12.000 $8.000 $5.000 $6.000 $11.000
EXCAVATION (ROADWAY)
CY 335.000 $20.000 $20.000 $30.000 $30.000 $36.000
EMBANKMENT (FINAL)(ORD COMP)(TY B)
CY 85.000 $15.000 $35.000 $50.000 $50.000 $75.000
BLOCK SODDING
SY 1,473.000 $15.000 $6.000 $6.000 $5.600 $5.500
CEMENT
TON 31.000 $200.000 $200.000 $110.000 $200.000 $230.000
CEMENT TREAT(EXIST MATL)(8")
SY 2,373.000 $5.000 $10.000 $5.500 $10.000 $10.000
D-GR HMA TY-B PG70-22
TON 522.000 $80.000 $140.000 $175.000 $121.000 $115.000
D-GR HMA TY-D PG70-22
TON 261.000 $80.000 $160.000 $200.000 $125.000 $116.000
PLANE ASPH CONC PAV (6")
SY 2,619.000 $6.000 $10.000 $6.500 $7.600 $8.000
STRUCT EXCAV (PIPE)
CY 4.000 $20.000 $20.000 $10.000 $140.000 $200.000
CEM STABIL BKFL
CY 10.000 $350.000 $200.000 $125.000 $240.000 $280.000
CEMENT STAB BACKFILL (INLET OR MH)
CY 11.500 $50.000 $200.000 $125.000 $175.000 $280.000
TEMPORARY SPL SHORING
SF 2,716.000 $25.000 $1.000 $40.000 $60.000 $43.000
DRILL SHAFT (RDWY ILL POLE) (30 IN)
LF 8.000 $150.000 $500.000 $375.000 $425.000 $600.000
RIPRAP (CONC)(4 IN)
CY 7.000 $525.000 $500.000 $500.000 $475.000 $750.000
RIPRAP (STONE PROTECTION)(12 IN)
CY 197.400 $175.000 $100.000 $150.000 $115.000 $160.000
RAIL (TY T224)
LF 328.000 $200.000 $160.000 $85.000 $235.000 $240.000
CONC BOX CULV (10 FT X 5 FT)
LF 376.000 $475.000 $860.000 $741.000 $875.000 $915.000
CONC BOX CULV (12 FT X 8 FT)
LF 172.000 $780.000 $1,150.000 $1,022.000 $1,400.000 $1,400.000
RC PIPE (CL III)(18 IN)
LF 96.000 $150.000 $65.000 $50.000 $70.000 $61.000
INLET (COMPL)(CURB)(TY 1)
EA 2.000 $5,500.000 $3,000.000 $5,320.000 $5,500.000 $4,500.000
WINGWALL (FW - S) (HW=5 FT)
EA 2.000 $9,000.000 $20,000.000 $12,000.000 $20,000.000 $33,000.000
WINGWALL (FW - S) (HW=8 FT)
EA 2.000 $10,000.000 $24,000.000 $16,000.000 $40,000.000 $37,000.000
REMOV STR (BOX CULVERT)
EA 7.000 $5,000.000 $8,000.000 $14,300.000 $5,000.000 $8,000.000
REMOV STR (INLET)
EA 2.000 $600.000 $500.000 $2,500.000 $1,000.000 $1,000.000
REMOV STR (HEADWALL)
EA 4.000 $1,500.000 $2,500.000 $12,500.000 $5,000.000 $5,000.000
REMOV STR (PIPE)
LF 57.000 $30.000 $20.000 $5.000 $50.000 $22.000
REMOVE STR (RAIL)
LF 289.000 $50.000 $10.000 $5.000 $35.000 $9.000
MOBILIZATION
LS 1.000 $94,386.000 $120,000.000 $80,000.000 $140,000.000 $170,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 7.000 $8,000.000 $3,500.000 $5,000.000 $2,500.000 $12,000.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 1,635.000 $5.000 $3.000 $4.500 $2.850 $3.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 1,635.000 $1.500 $1.000 $1.500 $0.740 $0.750
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 30.000 $10.000 $10.000 $10.000 $12.500 $9.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 30.000 $2.000 $1.000 $1.000 $2.900 $2.000
CONC CURB (TY II)
LF 138.000 $15.000 $20.000 $12.000 $35.000 $32.000
CONC CURB & GUTTER (TY II)
LF 1,902.000 $25.000 $24.000 $15.000 $42.000 $17.000
DRIVEWAYS (CONC)
SY 164.000 $120.000 $85.000 $70.000 $100.000 $100.000
CONC SIDEWALKS (4")
SY 576.000 $50.000 $65.000 $50.000 $45.000 $55.000
CURB RAMPS (TY 1)
EA 2.000 $2,100.000 $1,600.000 $1,000.000 $2,500.000 $1,800.000
CURB RAMPS (TY 6)
EA 1.000 $2,000.000 $2,500.000 $1,200.000 $3,000.000 $1,800.000
CURB RAMPS (TY 7)
EA 5.000 $2,000.000 $1,800.000 $1,500.000 $2,500.000 $1,800.000
RELOCATE RD IL ASM (TRANS-BASE)
EA 1.000 $2,200.000 $5,000.000 $1,000.000 $750.000 $7,000.000
ALUMINUM SIGNS (TY A)
SF 35.000 $45.000 $30.000 $30.000 $25.000 $45.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 6.000 $600.000 $500.000 $500.000 $750.000 $650.000
REMOVE SM RD SN SUP&AM
EA 6.000 $120.000 $150.000 $100.000 $100.000 $100.000
REFL PAV MRK TY II (W) 4" (BRK)
LF 260.000 $0.250 $15.000 $25.000 $30.000 $30.000
REFL PAV MRK TY II (W) 24" (SLD)
LF 17.000 $2.500 $50.000 $150.000 $112.000 $110.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 28.000 $90.000 $100.000 $120.000 $125.000 $200.000
Totals: $1,085,462.000 $1,293,885.000 $1,314,786.500 $1,587,534.350 $1,790,329.750