Bid Cobra

WICHITA FM 2380 (0283-01-018)

Items: 30

County: WICHITA
Length: N/A
Highway: FM 2380
District: WICHITA FALLS
Control Number: 0283-01-018
DBE Goal: N/A
Project: F 2023(810)
Guaranty: N/A
Time: 119 WORKING DAYS
Engineer's Estimate: $7,131,174.80
Date: 05/05/2023 (3 years ago)
Contract Number: N/A
Type: RESURFACE ROADWAY
Mail/Deliver Bids To: N/A
CALLAN COLTHARP
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (5)
E
Engineer's Estimate
$7,131,174.80
$7,479,603.50
Over/Under Est: 4.89% $348,428.70
$7,736,078.15
Over/Under Est: 8.48% $604,903.35
Amt Left: 3.43% $256,474.65
$8,063,108.80
Over/Under Est: 13.07% $931,934.00
Amt Left: 7.8% $583,505.30
Delta: -4.23% -$327,030.65
Over/Under Est: 28.99% $2,067,659.85
Amt Left: 22.99% $1,719,231.15
Delta: -14.09% -$1,135,725.85
$9,807,315.76
Over/Under Est: 37.53% $2,676,140.96
Amt Left: 31.12% $2,327,712.26
Delta: -6.61% -$608,481.11
Subcontractor Percentage Amount
DUSTROL, INC. 8.75% $654,465.31
TRP CONSTRUCTION GROUP, LLC 2.51% $187,738.05
BARRICADES UNLIMITED 0.73% $54,601.11
W. S. CONSTRUCTION COMPANY 0.42% $31,414.33
CHEROKEE SERVICES 0.36% $26,926.57
TRAFFIC SIGNALS, INC. 0.36% $26,926.57
Total: 13.13% $982,071.94

Bid Items & Bid Tabulations

30 Total 0 of 30
WICHITA  |  FM 2380  |  WICHITA FALLS  |  0283-01-018  |  05/05/2023  |  $7,131,174.80  |  F 2023(810)  |  RESURF ROADWAY  |  119 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
ZACK BURKETT CO.
JAGOE-PUBLIC COMPANY
DUININCK, INC.
EUROVIA ATLANTIC COAST LLC
A. L. HELMCAMP, INC.
BACKFILL (TY B)
STA 200.000 $165.000 $275.000 $175.000 $185.000 $295.000 $500.000
EMULS ASPH (EROSN CONT)(MS-2)
GAL 1,667.000 $4.000 $3.750 $3.000 $4.600 $3.100 $8.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(4")
SY 8,355.000 $45.000 $41.000 $33.000 $46.500 $45.000 $60.000
PLAN & TEXT ASPH CONC PAV(0" TO 2")
SY 267,235.000 $2.250 $2.870 $2.700 $1.500 $2.700 $3.500
CLEANING AND SEALING EXISTING JOINTS
LF 384.000 $75.000 $82.000 $37.000 $44.500 $48.000 $100.000
ADJUSTING MANHOLES
EA 16.000 $1,500.000 $1,755.000 $2,100.000 $2,700.000 $1,150.000 $5,000.000
MOBILIZATION
LS 1.000 $647,000.000 $325,000.000 $730,000.000 $680,000.000 $425,000.000 $600,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 7.000 $4,500.000 $9,183.500 $12,000.000 $33,500.000 $32,000.000 $15,000.000
INTERSECTIONS (ACP)
SY 766.000 $30.000 $30.000 $25.750 $42.500 $50.000 $125.000
DRIVEWAYS (ACP)
SY 726.000 $38.000 $24.000 $37.500 $16.000 $51.000 $100.000
DRIVEWAYS (BASE)
SY 1,577.000 $25.000 $28.000 $24.000 $9.300 $47.000 $50.000
RUMBLE STRIPS (CENTERLINE) ASPHALT
LF 14,684.000 $0.310 $0.530 $0.500 $0.430 $0.300 $1.500
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 1,045.000 $1.000 $1.200 $3.000 $1.400 $2.250 $0.750
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 2,307.000 $1.000 $1.200 $3.000 $1.400 $1.500 $0.750
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 4,573.000 $0.900 $1.230 $1.000 $0.960 $1.050 $1.040
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 586.000 $8.500 $9.360 $6.700 $6.400 $8.000 $6.900
REFL PAV MRK TY I (Y)24"(SLD)(100MIL)
LF 1,139.000 $9.500 $9.360 $6.700 $6.400 $8.000 $6.900
RE PM W/RET REQ TY I (W)4"(BRK)(100MIL)
LF 16,166.000 $0.470 $0.530 $0.450 $0.450 $0.450 $0.480
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 113,461.000 $0.470 $0.530 $0.450 $0.450 $0.450 $0.480
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
LF 19,106.000 $0.470 $0.530 $0.450 $0.450 $0.450 $0.480
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 168,870.000 $0.470 $0.530 $0.440 $0.450 $0.450 $0.480
PREFAB PAV MRK TY C (W) (ARROW)
EA 84.000 $225.000 $332.280 $280.000 $265.000 $284.000 $287.500
PREFAB PAV MRK TY C (W) (WORD)
EA 16.000 $330.000 $437.580 $280.000 $265.000 $374.000 $287.500
REFL PAV MRKR TY I-C
EA 988.000 $4.850 $5.850 $4.500 $4.250 $5.000 $4.600
REFL PAV MRKR TY II-A-A
EA 2,876.000 $4.850 $5.850 $4.500 $4.250 $5.000 $4.600
D-GR HMA TY-D SAC-B PG70-28
TON 4,130.000 $105.000 $119.500 $115.000 $140.000 $144.000 $150.000
STONE-MTRX-ASPH SMA-D SAC-A PG76-22
TON 34,615.000 $130.000 $141.000 $144.000 $152.250 $180.000 $175.000
BONDING COURSE
GAL 21,142.000 $5.000 $4.900 $1.500 $4.200 $2.750 $5.000
TMA (STATIONARY)
DAY 163.000 $195.000 $234.000 $250.000 $215.000 $540.000 $1,000.000
TMA (MOBILE OPERATION)
DAY 10.000 $185.000 $1.000 $10.000 $1,100.000 $940.000 $75.000
Totals: $7,131,174.800 $7,479,603.500 $7,736,078.150 $8,063,108.800 $9,198,834.650 $9,807,315.760