REMOVING CONC (MISC)
|
SY
|
2.500
|
$50.000
|
$600.000
|
|
|
EXCAVATION (ROADWAY)
|
CY
|
1,764.000
|
$20.000
|
$33.000
|
|
|
EMBANKMENT (FINAL)(DENS CONT)(TY B)
|
CY
|
2,911.000
|
$18.000
|
$32.000
|
|
|
SPOT SODDING
|
SY
|
4,900.000
|
$7.000
|
$7.500
|
|
|
DRILL SEEDING (PERM) (RURAL) (CLAY)
|
AC
|
3.900
|
$650.000
|
$685.000
|
|
|
DRILL SEEDING (TEMP) (WARM)
|
AC
|
1.950
|
$450.000
|
$540.000
|
|
|
DRILL SEEDING (TEMP) (COOL)
|
AC
|
1.950
|
$450.000
|
$485.000
|
|
|
VEGETATIVE WATERING
|
MG
|
205.000
|
$35.000
|
$20.000
|
|
|
CEMENT
|
TON
|
194.700
|
$160.000
|
$190.000
|
|
|
CEMENT TREAT (SUBGRADE) (8")
|
SY
|
19,674.000
|
$4.000
|
$5.500
|
|
|
PRIME COAT (MC-30)
|
GAL
|
4,919.000
|
$4.000
|
$7.000
|
|
|
D-GR HMA TY-B PG64-22
|
TON
|
6,195.000
|
$100.000
|
$139.000
|
|
|
SUPERPAVE MIXTURES SP-C PG64-22(LEV-UP)
|
TON
|
1,040.000
|
$110.000
|
$165.000
|
|
|
TACK COAT
|
GAL
|
878.000
|
$4.000
|
$5.500
|
|
|
STONE-MTRX-ASPH SMA-D SAC-B PG76-22
|
TON
|
9,554.000
|
$115.000
|
$165.000
|
|
|
FLEXIBLE PAVEMENT STRUCTURE REPAIR(6")
|
SY
|
1,867.000
|
$35.000
|
$78.000
|
|
|
PLAN & TEXT ASPH CONC PAV(0" TO 2")
|
SY
|
3,875.000
|
$2.000
|
$6.500
|
|
|
RIPRAP (CONC)(5 IN)
|
CY
|
1.400
|
$600.000
|
$1,300.000
|
|
|
RIPRAP (MOW STRIP)(4 IN)
|
CY
|
27.000
|
$500.000
|
$700.000
|
|
|
CONC BOX CULV (3 FT X 2 FT)(EXTEND)
|
LF
|
10.000
|
$900.000
|
$540.000
|
|
|
RC PIPE (CL III)(18 IN)
|
LF
|
14.000
|
$70.000
|
$190.000
|
|
|
SET (TY I)(S=3 FT)(HW=3FT)(4:1)(C)
|
EA
|
1.000
|
$9,000.000
|
$6,400.000
|
|
|
SET (TY I)(S= 8 FT)(HW= 3 FT)(4:1) (C)
|
EA
|
1.000
|
$12,000.000
|
$9,600.000
|
|
|
SET (TY II) (18 IN) (RCP) (6: 1) (P)
|
EA
|
1.000
|
$1,000.000
|
$1,300.000
|
|
|
REMOV STR (SET)
|
EA
|
1.000
|
$800.000
|
$550.000
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$256,318.230
|
$264,000.000
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
6.000
|
$7,000.000
|
$6,000.000
|
|
|
ROCK FILTER DAMS (INSTALL) (TY 2)
|
LF
|
120.000
|
$35.000
|
$57.000
|
|
|
ROCK FILTER DAMS (REMOVE)
|
LF
|
120.000
|
$9.000
|
$21.000
|
|
|
TEMP SEDMT CONT FENCE (INSTALL)
|
LF
|
2,101.000
|
$3.400
|
$2.300
|
|
|
TEMP SEDMT CONT FENCE (REMOVE)
|
LF
|
2,101.000
|
$1.000
|
$0.800
|
|
|
BIODEG EROSN CONT LOGS (INSTL) (8")
|
LF
|
330.000
|
$3.500
|
$5.000
|
|
|
BIODEG EROSN CONT LOGS (REMOVE)
|
LF
|
330.000
|
$1.200
|
$0.800
|
|
|
DRIVEWAYS (CONC)
|
SY
|
266.000
|
$100.000
|
$95.000
|
|
|
DRIVEWAYS (ACP)
|
SY
|
649.000
|
$35.000
|
$50.000
|
|
|
DRIVEWAYS (BASE)
|
SY
|
4,008.000
|
$24.000
|
$22.000
|
|
|
RUMBLE STRIPS (CENTERLINE)
|
LF
|
11,477.000
|
$0.500
|
$0.600
|
|
|
MTL W-BEAM GD FEN (TIM POST)
|
LF
|
400.000
|
$35.000
|
$37.000
|
|
|
DOWNSTREAM ANCHOR TERMINAL SECTION
|
EA
|
2.000
|
$1,200.000
|
$700.000
|
|
|
REMOVE METAL BEAM GUARD FENCE
|
LF
|
375.000
|
$5.000
|
$5.500
|
|
|
REMOVE TERMINAL ANCHOR SECTION
|
EA
|
3.000
|
$250.000
|
$270.000
|
|
|
GUARDRAIL END TREATMENT (INSTALL)
|
EA
|
2.000
|
$3,500.000
|
$2,700.000
|
|
|
GUARDRAIL END TREATMENT (REMOVE)
|
EA
|
1.000
|
$600.000
|
$550.000
|
|
|
MAILBOX INSTALL-S (TWW-POST) TY 4
|
EA
|
15.000
|
$280.000
|
$330.000
|
|
|
MAILBOX INSTALL-D (TWW-POST) TY 4
|
EA
|
7.000
|
$300.000
|
$370.000
|
|
|
MAILBOX INSTALL-M (TWW-POST) TY 4
|
EA
|
13.000
|
$380.000
|
$770.000
|
|
|
IN SM RD SN SUP&AM TYS80(1)SA(P-BM)
|
EA
|
1.000
|
$730.000
|
$800.000
|
|
|
IN SM RD SN SUP&AM TYS80(1)SA(T)
|
EA
|
13.000
|
$550.000
|
$790.000
|
|
|
IN SM RD SN SUP&AM TYS80(1)SA(U)
|
EA
|
2.000
|
$800.000
|
$870.000
|
|
|
IN SM RD SN SUP&AM TYS80(1)SB(P-BM)
|
EA
|
2.000
|
$780.000
|
$890.000
|
|
|
IN SM RD SN SUP&AM TYTWT(1)UB(T)
|
EA
|
2.000
|
$780.000
|
$650.000
|
|
|
IN SM RD SN SUP&AM TYTWT(1)WS(P)
|
EA
|
11.000
|
$270.000
|
$550.000
|
|
|
IN SM RD SN SUP&AM TYTWT(1)WS(T)
|
EA
|
16.000
|
$500.000
|
$610.000
|
|
|
RELOCATE SM RD SN SUP&AM TY S80
|
EA
|
1.000
|
$700.000
|
$710.000
|
|
|
REMOVE SM RD SN SUP&AM
|
EA
|
40.000
|
$175.000
|
$110.000
|
|
|
INSTL DEL ASSM (D-DW)SZ 1(FLX)GND
|
EA
|
7.000
|
$150.000
|
$87.000
|
|
|
INSTL DEL ASSM (D-DY)SZ 1(FLX)SRF
|
EA
|
2.000
|
$160.000
|
$110.000
|
|
|
INSTL OM ASSM (OM-2Z)(FLX)GND
|
EA
|
4.000
|
$180.000
|
$90.000
|
|
|
INSTL DEL ASSM (D-SY)SZ 1(BRF)GF2
|
EA
|
12.000
|
$30.000
|
$40.000
|
|
WK ZN PAV MRK SHT TERM (TAB)TY W
|
EA
|
2,315.000
|
$1.400
|
$0.600
|
|
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
|
EA
|
1,741.000
|
$1.300
|
$0.600
|
|
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
|
LF
|
468.000
|
$0.500
|
$1.200
|
|
REFL PAV MRK TY II (W) 4" (BRK)
|
LF
|
2,775.000
|
$0.120
|
$0.330
|
|
REFL PAV MRK TY II (Y) 4" (SLD)
|
LF
|
23,591.000
|
$0.150
|
$0.330
|
|
RE PM W/RET REQ TY I (W)4"(BRK)(100MIL)
|
LF
|
6,430.000
|
$0.400
|
$0.500
|
|
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
|
LF
|
25,634.000
|
$0.500
|
$0.500
|
|
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
|
LF
|
27,069.000
|
$0.400
|
$0.500
|
|
PREFAB PAV MRK TY C (W) (24") (SLD)
|
LF
|
30.000
|
$20.000
|
$14.000
|
|
PREFAB PAV MRK TY C (W) (ARROW)
|
EA
|
1.000
|
$250.000
|
$250.000
|
|
PREFAB PAV MRK TY C (W) (WORD)
|
EA
|
1.000
|
$500.000
|
$280.000
|
|
PREFAB PAV MRK TY C (W) (36")(YLD TRI)
|
EA
|
16.000
|
$50.000
|
$70.000
|
|
REFL PAV MRKR TY I-C
|
EA
|
327.000
|
$10.000
|
$4.500
|
|
REFL PAV MRKR TY II-A-A
|
EA
|
623.000
|
$6.000
|
$4.500
|
|
|
ELIM EXT PAV MRK & MRKS (4")
|
LF
|
29,141.000
|
$0.500
|
$0.600
|
|
|
BONDING COURSE
|
GAL
|
13,803.000
|
$3.000
|
$2.800
|
|
|
PORTABLE CHANGEABLE MESSAGE SIGN
|
EA
|
1.000
|
$9,000.000
|
$25,000.000
|
|
|
TMA (STATIONARY)
|
DAY
|
83.000
|
$300.000
|
$350.000
|
|
|
TMA (MOBILE OPERATION)
|
DAY
|
11.000
|
$800.000
|
$900.000
|
|
Totals: |
$2,900,317.180
|
$3,928,716.030
|