WICHITA SL 11 (0043-14-024)

Items: 18

County: WICHITA
Length: N/A
Highway: SL 11
District: WICHITA FALLS
Control Number: 0043-14-024
DBE Goal: N/A
Project: BR 2017(880)
Guaranty: N/A
Time: 51 WORKING DAYS
Engineer's Estimate: $317,611.52
Date: 03/07/2017 (9 years ago)
Contract Number: N/A
Type: UPGRADE BRIDGE AND APPROACH RAILING
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (4)
E
Engineer's Estimate
$317,611.52
$351,296.40
Over/Under Est: 10.61% $33,684.88
Over/Under Est: 19.63% $62,353.48
Amt Left: 8.16% $28,668.60
Over/Under Est: 31.17% $99,014.98
Amt Left: 18.6% $65,330.10
Delta: -9.65% -$36,661.50
$491,037.50
Over/Under Est: 54.6% $173,425.98
Amt Left: 39.78% $139,741.10
Delta: -17.86% -$74,411.00

Bid Items & Bid Tabulations

18 Total 0 of 18
WICHITA  |  SL 11  |  WICHITA FALLS  |  0043-14-024  |  03/07/2017  |  $317,611.52  |  BR 2017(880)  |  UPGRADE BRIDGE AND APPROACH RAILING  |  51 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
COPPELL CONSTRUCTION CO., INC.
EARTH BUILDERS, L.P.
SCR CIVIL CONSTRUCTION, LLC
RESTEK, INC.
REMOVING CONC (SIDEWALKS)
SY 38.900 $19.650 $142.000 $20.000 $20.000 $50.000
BACKFILL (TY C)
STA 3.000 $550.800 $1,677.000 $2,200.000 $400.000 $2,500.000
SAND BACKFILL
CY 21.000 $58.000 $198.000 $100.000 $100.000 $150.000
DRILLED SHAFT (12 IN)
LF 40.000 $132.000 $50.000 $150.000 $185.000 $250.000
CL F CONC (MISC)
CY 6.500 $2,000.000 $2,337.000 $700.000 $5,160.000 $2,500.000
RIPRAP (CONC)(4 IN)
CY 2.200 $550.000 $2,732.000 $700.000 $2,400.000 $1,250.000
RIPRAP (MOW STRIP)(4 IN)
CY 4.000 $535.600 $2,989.000 $700.000 $2,400.000 $1,250.000
RETROFIT RAIL (TY C1W)
LF 697.300 $300.000 $296.500 $410.000 $345.000 $425.000
MOBILIZATION
LS 1.000 $26,964.680 $35,000.000 $30,000.000 $41,000.000 $50,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 3.000 $7,000.000 $4,825.000 $2,000.000 $2,500.000 $15,000.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 820.000 $3.800 $5.000 $4.000 $3.500 $6.500
TEMP SEDMT CONT FENCE (REMOVE)
LF 820.000 $1.200 $2.500 $1.000 $1.000 $2.000
CONC SIDEWALKS (4")
SY 157.200 $68.300 $65.000 $70.000 $225.000 $100.000
MTL BEAM GD FEN TRANS (TL2)
EA 1.000 $1,300.000 $5,490.000 $1,600.000 $2,000.000 $2,775.000
GUARDRAIL END TREATMENT (INSTALL)
EA 1.000 $2,680.500 $4,300.250 $3,000.000 $3,000.000 $4,875.000
CRASH CUSH ATTEN (INSTL)
EA 1.000 $12,000.000 $11,516.000 $7,500.000 $12,000.000 $15,000.000
RELOCATE SM RD SN SUP&AM TY 10BWG
EA 4.000 $755.600 $757.000 $500.000 $1,400.000 $1,000.000
WK ZN PAV MRK REMOV (W)4"(SLD)
LF 1,500.000 $0.900 $3.000 $3.000 $4.000 $2.500
Totals: $317,611.525 $351,296.400 $379,965.000 $416,626.500 $491,037.500