Show Job Controls
Bid Cobra

WICHITA US 287 (0043-09-146)

Items: 20

County: WICHITA
Length: N/A
Highway: US 287
District: WICHITA FALLS
Control Number: 0043-09-146
DBE Goal: 0.0%
Project: F 2B24(125)
Guaranty: N/A
Time: 187 WORKING DAYS
Engineer's Estimate: $6,480,380.48
Date: 06/06/2024 (2 years ago)
Contract Number: N/A
Type: SURFACING/ROADWAY RESTORATION
Mail/Deliver Bids To: N/A
CALLAN COLTHARP
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (3)
E
Engineer's Estimate
$6,480,380.48
$7,338,061.32
Over/Under Est: 13.24% $857,680.84
$8,781,730.12
Over/Under Est: 35.51% $2,301,349.64
Amt Left: 19.67% $1,443,668.80
$9,326,040.89
Over/Under Est: 43.91% $2,845,660.41
Amt Left: 27.09% $1,987,979.57
Delta: -6.20% -$544,310.77
Subcontractor Percentage Amount
MISSOURI PETROLEUM PRODUCTS COMPANY LLC 10.09% $742,626.29
DUSTROL, INC. 7.29% $536,545.65
TRP CONSTRUCTION GROUP, LLC 3.43% $252,448.78
TRAFFIC HIGHWAY MAINTENANCE, LLC 0.50% $36,800.11
Total: 21.31% $1,568,420.83

Bid Items & Bid Tabulations

20 Total 0 of 20
WICHITA  |  US 287  |  WICHITA FALLS  |  0043-09-146  |  06/06/2024  |  $6,480,380.48  |  F 2B24(125)  |  SURF/ROADWAY RESTOR  |  187 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
ZACK BURKETT CO.
DUININCK, INC.
A. L. HELMCAMP, INC.
ASPH (AC-20-5TR)
GAL 133,969.000 $3.950 $5.200 $5.400 $5.300
AGGR (TY-PB GR-4 MOD)
CY 2,792.000 $88.000 $105.000 $170.000 $192.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(8")
SY 21,553.000 $56.000 $75.000 $85.000 $96.000
PLANE ASPH CONC PAV (0" TO 1 1/2")
SY 221,431.000 $1.100 $2.090 $2.200 $2.650
MOBILIZATION
LS 1.000 $577,625.000 $600,000.000 $875,000.000 $450,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 11.000 $11,500.000 $4,000.000 $10,000.000 $8,800.000
RUMBLE STRIPS (SHOULDER) ASPHALT
LF 197,906.000 $0.120 $0.260 $0.100 $0.230
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 8,294.000 $1.100 $1.200 $1.500 $1.200
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 19,434.000 $0.900 $1.170 $1.200 $1.050
REFL PAV MRK TY II (W) 6" (BRK)
LF 54,072.000 $0.250 $0.350 $0.350 $0.320
RE PM W/RET REQ TY I (W)6"(BRK)(100MIL)
LF 27,646.000 $0.560 $0.810 $0.820 $0.720
RE PM W/RET REQ TY I (W)6"(SLD)(100MIL)
LF 110,583.000 $0.550 $0.780 $0.800 $0.700
RE PM W/RET REQ TY I (Y)6"(SLD)(100MIL)
LF 110,583.000 $0.550 $0.780 $0.800 $0.700
PREFAB PAV MRK TY C (W) (24") (SLD)
LF 2,999.000 $13.250 $16.670 $17.000 $15.000
REFL PAV MRKR TY II-C-R
EA 1,382.000 $4.250 $5.560 $5.600 $5.000
PFC-C PG76-22 SAC-A
TON 19,153.000 $161.000 $165.000 $200.000 $232.000
BONDING COURSE
GAL 16,128.000 $5.100 $5.800 $4.250 $4.600
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $12,500.000 $7,500.000 $23,500.000 $17,100.000
TMA (STATIONARY)
DAY 492.000 $225.000 $1.000 $1.000 $10.000
TMA (MOBILE OPERATION)
DAY 66.000 $40.000 $1.000 $1.000 $10.000
Totals: $6,480,380.480 $7,338,061.320 $8,781,730.120 $9,326,040.890