Show Job Controls
Bid Cobra

WICHITA US 287 (0043-08-078)

Items: 16

County: WICHITA
Length: N/A
Highway: US 287
District: WICHITA FALLS
Control Number: 0043-08-078
DBE Goal: N/A
Project: STP 2019(438)HES
Guaranty: N/A
Time: 25 WORKING DAYS
Engineer's Estimate: $487,147.45
Date: 01/09/2019 (7 years ago)
Contract Number: N/A
Type: HIGH FRICTION SURFACE TREATMENT
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (4)
E
Engineer's Estimate
$487,147.45
$433,433.00
Over/Under Est: -11.03% -$53,714.45
Over/Under Est: -7.9% -$38,495.70
Amt Left: 3.51% $15,218.75
Over/Under Est: 2.27% $11,062.78
Amt Left: 14.95% $64,777.23
Delta: -11.05% -$49,558.48
Over/Under Est: 61.55% $299,852.55
Amt Left: 81.57% $353,567.00
Delta: -57.97% -$288,789.77

Bid Items & Bid Tabulations

16 Total 0 of 16
WICHITA  |  US 287  |  WICHITA FALLS  |  0043-08-078  |  01/09/2019  |  $487,147.45  |  STP 2019(438)HES  |  HIGH FRICTION SURF TREATMENT  |  25 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
THE TRUESDELL CORPORATION
TOTAL HIGHWAY MAINTENANCE, LLC
DEANGELO BROTHERS LLC
AMERICAN CIVIL CONSTRUCTORS WEST COAST LLC
MOBILIZATION
LS 1.000 $42,467.950 $13,788.650 $10,000.000 $63,000.000 $78,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 2.000 $10,000.000 $14,000.000 $3,500.000 $2,888.000 $9,999.750
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 2.000 $700.000 $1,600.000 $800.000 $445.000 $950.000
IN SM RD SN SUP&AM TYTWT(1)WS(P)
EA 15.000 $500.000 $1,050.000 $500.000 $420.000 $550.000
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 139.000 $3.000 $3.250 $1.000 $3.000 $2.500
WK ZN PAV MRK SHT TERM (TAB)TY Y
EA 596.000 $3.000 $2.750 $1.000 $3.000 $2.500
RE PM W/RET REQ TY I (W)4"(BRK)(100MIL)
LF 460.000 $0.500 $1.100 $0.550 $1.050 $4.000
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 12,856.000 $0.500 $0.800 $0.500 $0.790 $1.500
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
LF 445.000 $0.500 $1.100 $0.550 $1.050 $4.000
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 11,076.000 $0.500 $0.800 $0.500 $0.790 $1.500
REFL PAV MRKR TY II-A-A
EA 140.000 $4.000 $7.500 $7.000 $7.350 $35.000
REFL PAV MRKR TY II-C-R
EA 24.000 $4.000 $7.500 $7.000 $7.350 $35.000
HIGH FRICTION SURFACE COURSE
SY 19,610.000 $20.000 $17.250 $20.500 $19.430 $31.500
PREFORMED IN-LANE(TRANS) RUMBLE STRIP
LF 80.000 $10.000 $22.000 $10.000 $21.000 $38.000
TMA (STATIONARY)
DAY 10.000 $150.000 $320.000 $300.000 $997.500 $500.000
TMA (MOBILE OPERATION)
HR 120.000 $50.000 $50.000 $20.000 $52.500 $50.000
Totals: $487,147.450 $433,433.000 $448,651.750 $498,210.230 $787,000.000