WICHITA US 287 (0043-08-076)

Items: 19

County: WICHITA
Length: N/A
Highway: US 287
District: WICHITA FALLS
Control Number: 0043-08-076
DBE Goal: N/A
Project: STP 2019(305)HES
Guaranty: N/A
Time: 109 WORKING DAYS
Engineer's Estimate: $976,808.86
Date: 01/09/2019 (7 years ago)
Contract Number: N/A
Type: SAFETY LIGHTING
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (5)
E
Engineer's Estimate
$976,808.86
$1,090,136.60
Over/Under Est: 11.6% $113,327.74
Over/Under Est: 13.31% $129,980.42
Amt Left: 1.53% $16,652.68
Over/Under Est: 16.94% $165,488.97
Amt Left: 4.78% $52,161.23
Delta: -3.21% -$35,508.55
$1,372,110.92
Over/Under Est: 40.47% $395,302.06
Amt Left: 25.87% $281,974.32
Delta: -20.12% -$229,813.09
Over/Under Est: 43.66% $426,491.14
Amt Left: 28.73% $313,163.40
Delta: -2.27% -$31,189.08

Bid Items & Bid Tabulations

19 Total 0 of 19
WICHITA  |  US 287  |  WICHITA FALLS  |  0043-08-076  |  01/09/2019  |  $976,808.86  |  STP 2019(305)HES  |  SAFETY LIGHTING  |  109 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
VACA UNDERGROUND UTILITIES INC
AMERICAN LIGHTING AND SIGNALIZATION, LLC
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC.
MICA CORPORATION
DURABLE SPECIALTIES, INC.
DRILL SHAFT (RDWY ILL POLE) (30 IN)
LF 760.000 $205.000 $230.000 $166.750 $207.880 $234.050 $260.000
RIPRAP (CONC)(CL B)
CY 26.600 $800.000 $625.000 $1,311.950 $699.250 $2,276.000 $1,275.000
MOBILIZATION
LS 1.000 $84,324.410 $90,000.000 $103,029.440 $107,111.990 $124,300.000 $135,510.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 7.000 $3,000.000 $3,200.000 $6,991.980 $11,340.000 $17,580.000 $11,500.000
REMOVE RD IL ASM (TRANS-BASE)
EA 16.000 $500.000 $800.000 $905.180 $532.500 $1,130.000 $525.000
REPLACE LUMINAIRE W/LED (250W EQ)
EA 2.000 $1,000.000 $450.000 $645.370 $505.900 $665.000 $754.000
REPLACE LUMINAIRE W/LED (400W EQ)
EA 6.000 $1,200.000 $500.000 $760.390 $566.850 $805.000 $810.000
IN RD IL (TY ST) 50T-10 (400W EQ) LED
EA 7.000 $3,300.000 $3,750.000 $3,408.340 $3,371.850 $3,275.000 $4,600.000
IN RD IL (TY ST) 50T-10-10(400W EQ)LED
EA 69.000 $4,000.000 $4,750.000 $3,486.960 $4,439.750 $4,152.000 $5,500.000
CONDT (PVC) (SCH 40) (2")
LF 19,896.000 $6.000 $8.250 $10.790 $8.770 $10.250 $8.000
CONDT (PVC) (SCH 80) (2") (BORE)
LF 2,095.000 $25.000 $16.500 $17.920 $23.960 $26.600 $30.000
ELEC CONDR (NO.6) BARE
LF 21,991.000 $1.350 $1.500 $1.100 $1.250 $1.680 $2.000
ELEC CONDR (NO.6) INSULATED
LF 45,116.000 $1.600 $1.600 $1.770 $1.370 $1.840 $2.000
GROUND BOX TY A (122311)W/APRON
EA 47.000 $890.000 $850.000 $1,128.220 $831.850 $1,570.000 $950.000
REMOVE GROUND BOX
EA 17.000 $300.000 $300.000 $191.100 $319.500 $380.000 $475.000
REMOVE ELECTRICAL SERVICES
EA 3.000 $700.000 $300.000 $903.050 $1,065.000 $570.000 $850.000
ELC SRV TY A 120/240 060(NS)SS(E)SP(O)
EA 7.000 $5,000.000 $5,000.000 $6,557.860 $5,712.250 $7,510.000 $7,000.000
ELC SRV TY D 120/240 060(NS)SS(E)SP(O)
EA 1.000 $5,000.000 $4,000.000 $6,107.670 $5,627.150 $7,320.000 $7,000.000
TMA (STATIONARY)
DAY 103.000 $150.000 $260.000 $399.330 $281.750 $303.000 $600.000
Totals: $976,808.860 $1,090,136.600 $1,106,789.280 $1,142,297.830 $1,372,110.920 $1,403,300.000