WHEELER SH 152 (0486-01-032)

Items: 59

County: WHEELER
Length: N/A
Highway: SH 152
District: CHILDRESS
Control Number: 0486-01-032
DBE Goal: N/A
Project: STP 2019(591)
Guaranty: N/A
Time: 119 WORKING DAYS
Engineer's Estimate: $9,228,112.87
Date: 04/02/2019 (7 years ago)
Contract Number: N/A
Type: SUPER 2
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (4)
E
Engineer's Estimate
$9,228,112.87
1
Awarded
$9,862,939.49
Over/Under Est: 6.88% $634,826.62
$10,112,947.95
Over/Under Est: 9.59% $884,835.08
Amt Left: 2.53% $250,008.46
$11,703,900.29
Over/Under Est: 26.83% $2,475,787.42
Amt Left: 18.67% $1,840,960.80
Delta: -15.73% -$1,590,952.34
$12,648,589.86
Over/Under Est: 37.07% $3,420,476.99
Amt Left: 28.24% $2,785,650.37
Delta: -8.07% -$944,689.57

Bid Items & Bid Tabulations

59 Total 0 of 59
WHEELER  |  SH 152  |  CHILDRESS  |  0486-01-032  |  04/02/2019  |  $9,228,112.87  |  STP 2019(591)  |  SUPER 2  |  119 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
JCCC, INC.
DUININCK, INC.
J. LEE MILLIGAN, INC.
GILVIN-TERRILL, LTD.
PREPARING ROW
STA 41.000 $2,000.000 $915.590 $1,600.000 $2,500.000 $1,500.000
PREPARING ROW (TREE) (6" TO 24" DIA)
EA 1.000 $605.000 $784.630 $3,000.000 $3,600.000 $1,500.000
REMOVING CONC (FOUNDATIONS)
CY 4.000 $550.000 $185.390 $320.000 $480.000 $500.000
REMOVING CONC (DRIVEWAYS)
SY 18.000 $55.000 $44.240 $46.000 $50.000 $100.000
EXCAVATION (CHANNEL)
CY 5.000 $45.000 $18.740 $66.500 $148.500 $500.000
SUBGRADE WIDENING (ORD COMP)
STA 758.640 $340.000 $274.970 $275.000 $250.000 $1,000.000
EMBANKMENT (FINAL)(ORD COMP)(TY B)
CY 361.900 $27.000 $25.440 $29.500 $50.000 $50.000
BACKFILL (TY A OR B)
STA 786.980 $140.000 $152.660 $195.000 $146.500 $170.000
BLADING
HR 75.000 $170.000 $124.560 $145.000 $290.000 $250.000
DRILL SEEDING (PERM) (RURAL) (SANDY)
AC 40.000 $320.000 $359.000 $330.000 $380.000 $310.000
DRILL SEEDING (TEMP) (WARM)
AC 20.000 $350.000 $300.000 $355.000 $315.000 $330.000
DRILL SEEDING (TEMP) (COOL)
AC 20.000 $350.000 $365.000 $365.000 $385.000 $340.000
VEGETATIVE WATERING
MG 1,560.000 $20.000 $24.490 $24.500 $41.000 $25.000
EMULS ASPH (EROSN CONT)(CSS-1H)
GAL 16,843.120 $3.100 $3.500 $3.450 $3.850 $3.250
D-GR HMA TY-B PG70-22
TON 21,740.750 $95.000 $104.680 $114.000 $121.600 $120.000
D-GR HMA TY-D SAC-A PG 76-28
TON 50,725.000 $105.000 $115.500 $114.000 $131.650 $130.000
PLANE ASPH CONC PAV(0" TO 2")
SY 5,089.000 $2.900 $2.340 $3.250 $4.250 $2.530
PLANE ASPH CONC PAV (2")
SY 10,360.000 $1.800 $1.860 $2.500 $2.900 $2.530
RIPRAP (STONE PROTECTION)(24 IN)
CY 211.640 $125.000 $102.460 $215.000 $155.000 $200.000
CMP (GAL STL 48 IN)
LF 58.000 $115.000 $179.800 $215.000 $235.000 $300.000
SET (TY II) (48 IN) (CMP) (4: 1) (C)
EA 14.000 $4,500.000 $5,128.800 $7,000.000 $3,415.000 $6,000.000
MOBILIZATION
LS 1.000 $688,351.000 $692,853.990 $540,000.000 $954,000.000 $1,200,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 6.000 $11,800.000 $14,620.150 $33,500.000 $29,950.000 $50,000.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 500.000 $30.000 $25.000 $27.000 $44.500 $30.000
CONSTRUCTION EXITS (REMOVE)
SY 500.000 $5.500 $5.000 $10.500 $7.000 $10.000
BIODEG EROSN CONT LOGS (INSTL) (18")
LF 1,000.000 $4.000 $5.020 $5.350 $9.400 $5.700
RUMBLE STRIPS (SHOULDER)
LF 157,687.000 $0.150 $0.100 $0.130 $0.130 $0.200
RUMBLE STRIPS (CENTERLINE)
LF 78,598.000 $0.350 $0.100 $0.170 $0.300 $0.250
MTL W-BEAM GD FEN (STEEL POST)
LF 800.000 $30.000 $30.000 $32.000 $31.600 $30.000
REMOVE METAL BEAM GUARD FENCE
LF 800.000 $4.200 $4.000 $4.300 $4.200 $4.000
GUARDRAIL END TREATMENT (INSTALL)
EA 4.000 $3,200.000 $3,100.000 $3,300.000 $3,265.000 $3,100.000
GUARDRAIL END TREATMENT (REMOVE)
EA 4.000 $330.000 $400.000 $430.000 $420.000 $400.000
MAILBOX INSTALL-S (TWG-POST) TY 1
EA 10.000 $220.000 $210.000 $225.000 $265.000 $250.000
MAILBOX INSTALL-D (TWG-POST) TY 1
EA 2.000 $280.000 $250.000 $270.000 $315.000 $300.000
MAILBOX INSTALL-M (TWG-POST) TY 1
EA 2.000 $415.000 $385.000 $410.000 $474.000 $450.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 22.000 $580.000 $520.000 $555.000 $895.000 $850.000
IN SM RD SN SUP&AM TYS80(1)SA(T)
EA 5.000 $1,300.000 $825.000 $885.000 $1,225.000 $1,165.000
RELOCATE SM RD SN SUP&AM TY 10BWG
EA 39.000 $600.000 $415.000 $445.000 $795.000 $755.000
RELOCATE SM RD SN SUP&AM TY S80
EA 3.000 $520.000 $485.000 $520.000 $875.000 $830.000
INSTL DEL ASSM (D-SW)SZ 1(FLX)GND(BI)
EA 12.000 $130.000 $55.000 $59.000 $142.000 $135.000
INSTL OM ASSM (OM-2Z)(FLX)GND
EA 52.000 $95.000 $60.000 $64.000 $142.000 $135.000
REMOVE DELIN & OBJECT MARKER ASSMS
EA 65.000 $14.000 $25.000 $27.000 $16.000 $15.000
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 4,989.000 $1.100 $1.000 $1.050 $1.150 $1.000
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 7,232.000 $1.100 $1.000 $1.050 $1.200 $1.000
REFL PAV MRK TY I (W)4"(DOT)(100MIL)
LF 1,837.000 $0.800 $0.800 $0.860 $0.450 $0.430
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 2,400.000 $1.000 $0.750 $0.800 $0.880 $0.840
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 30.000 $7.500 $10.000 $10.500 $21.050 $20.000
REFL PAV MRK TY I (W)(ARROW)(100MIL)
EA 20.000 $108.000 $200.000 $215.000 $263.400 $250.000
RE PM W/RET REQ TY I (W)4"(BRK)(100MIL)
LF 17,240.000 $0.350 $0.310 $0.330 $0.450 $0.430
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 156,230.000 $0.350 $0.300 $0.320 $0.450 $0.430
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
LF 6,275.000 $0.350 $0.350 $0.370 $0.450 $0.430
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 165,705.000 $0.350 $0.300 $0.320 $0.450 $0.430
REFL PAV MRKR TY I-C
EA 266.000 $4.200 $3.000 $3.200 $4.200 $4.000
REFL PAV MRKR TY II-A-A
EA 2,300.000 $4.200 $3.000 $3.200 $4.200 $4.000
ELIM EXT PAV MRK & MRKS (24")
LF 30.000 $8.000 $20.000 $21.500 $3.650 $3.400
ELIM EXT PAV MRK & MRKS (ARROW)
EA 6.000 $55.000 $30.000 $32.000 $60.750 $57.640
RELOCATE RDSD FLASH BEACON ASSEMBLY
EA 2.000 $3,500.000 $4,400.000 $4,300.000 $12,115.000 $15,000.000
TMA (STATIONARY)
DAY 91.000 $300.000 $250.000 $300.000 $785.000 $2,600.000
TMA (MOBILE OPERATION)
HR 104.000 $50.000 $95.000 $96.500 $78.500 $95.000
Totals: $9,228,112.872 $9,862,939.508 $10,112,947.954 $11,703,900.292 $12,648,589.860